# Britain will pay up to GBP 180m to host a 30 MW AI supercomputer, GBP 6m per MW. Bids close 25 November

> Britain opened a grant of up to £180m on 11 November to host a 30 MW AI supercomputer, about £6m per MW of IT load. Bids close at midday on 25 November.

Publisher: DC Market Insights  
Published: 2026-11-19  
Last updated: 2026-11-19  
Page: https://www.dcmarketinsights.com/news/britain-will-pay-up-to-gbp-180m-to-host-a-30-mw-ai-supercomputer-gbp-6m-per-mw-bids-close-25-november

## Key takeaways

- The UK government opened a grant competition on 11 November worth up to approximately £180 million to build and run the data centre for its new AI Research Resource (AIRR) supercomputer (Find a Grant).
- The host must deliver 10 MW of IT load by 31 March 2028 and 30 MW by 31 March 2029, backed by a firm grid import offer of at least 14 MVA, rising to 41 MVA (Find a Grant).
- That works out at about £6.0 million per MW of IT load for the building, power, cooling, security and operation to March 2030, excluding the computer itself (our calculation).
- The grid ask is 1.37 to 1.40 MVA per MW of IT load. Digital Realty's new private 300 MVA link for a 200 MW Frankfurt campus is 1.50 (our calculation from Find a Grant and DCNN).
- Bids close at midday on 25 November 2026. The government expects to tell applicants the outcome by 8 January 2027 (Find a Grant).

The British government has put a public price on a mid-sized AI data centre. For up to about £180 million, it wants a UK research organisation and its partners to find land, secure grid power, build a liquid-cooled hall and run it until March 2030 for a supercomputer that the state will buy separately.

The numbers matter beyond one competition. They show what a buyer with no commercial margin to protect thinks 30 MW of AI-ready space costs in Britain in 2026, how much grid headroom it asks for per megawatt, and how little time it allows. Applicants have 14 days from launch to bid, and they need a written grid offer in hand before they apply.

**£180m** Maximum grant for the AIRR supercomputer host site and data centre (Find a Grant)

**£6.0m** Grant per MW of IT load at 30 MW, building and running costs to March 2030 (our calculation)

**25 Nov** Bids close at 12:00 midday; outcome due by 8 January 2027 (Find a Grant)

## How we got here: a £750m machine that needs a home

The competition is the second step of a plan the Department for Science, Innovation and Technology (DSIT) set out in July. Its expression-of-interest notice, first published on 17 July 2026, put the budget for the new "heterogeneous" AIRR supercomputer at £750 million. It split that money four ways: £150 million for an Advanced Market Commitment to buy novel inference hardware, a further £250 million procurement for more specialised hardware in phase 2, and £350 million for established-vendor hardware plus the data centre and its infrastructure, [according to the notice](https://www.gov.uk/government/publications/expression-of-interest-airr-heterogeneous-supercomputer-host-site-selection/expression-of-interest-airr-heterogeneous-supercomputer-host-site-selection).

The July notice asked for a site able to take up to 10 MW in phase 1, going live in early 2028, and 20 to 30 MW in total in phase 2, going live in the 2029/30 financial year. It asked for "access to high-density cooling", ISO 27001 and Cyber Essentials Plus certification, or a credible plan to get them by December 2028. Expressions of interest closed on 10 August 2026.

The formal grant competition opened at 3pm on 11 November. The [Find a Grant notice](https://find-lb.find-a-grant-support.service.cabinetoffice.gov.uk/grants/airr-heterogeneous-supercomputer-host-site-and-data-centre-grant-competition-1) names the funder as the Department for Business, Innovation, Science and Trade, with a DSIT contact address, and offers "up to approximately £180 million", subject to approvals.

## What the £180m buys, and what it does not

The grant pays for the design, construction or modification, commissioning and operation of the hosting facility. The notice lists land and accommodation (including dedicated co-location or lease arrangements), power supply and electrical infrastructure, cooling and fire protection, physical security and building-management systems, connectivity to the Janet research network, and the staff and maintenance directly tied to running the data centre. It is capital and resource funding, with costs covered up to 31 March 2030.

It does not pay for the supercomputer, its installation, integration and acceptance, or for system administration, user support and research software engineering. Those sit in the separate hardware budgets.

| AIRR host competition | Requirement |
| --- | --- |
| Grant | Up to approximately £180m, subject to approvals; costs to 31 March 2030 |
| Phase 1 | Power and cooling for 10 MW of IT load by 31 March 2028 |
| Phase 2 | 30 MW of IT load in total by 31 March 2029 |
| Grid | Written, verifiable DNO offer of firm import capacity: at least 14 MVA for phase 1, at least 41 MVA by 31 March 2029 |
| Cooling | Liquid cooling named in the objectives; no PUE or kW-per-rack figure on the notice page |
| Lead applicant | UK research organisation eligible for UKRI funding; commercial co-location partners may join if UK-incorporated |
| Key dates | Questions by 20 Nov (12pm); answers by 24 Nov; bids close 25 Nov (12pm); evaluation 27 Nov to 1 Dec; outcome by 8 Jan 2027; grant agreement by 15 Jan 2027 |

Source: [Find a Grant, AIRR Heterogeneous Supercomputer Host Site and Data Centre Grant Competition, opened 11 Nov 2026](https://find-lb.find-a-grant-support.service.cabinetoffice.gov.uk/grants/airr-heterogeneous-supercomputer-host-site-and-data-centre-grant-competition-1). [Data Centre Review (12 Nov 2026)](https://datacentrereview.com/2026/11/uk-government-offers-180m-for-ai-data-centre-but-theres-a-catch/) reported the first 10 MW as due by 31 December 2027; the official notice says 31 March 2028, and its objectives describe readiness in "mid 2028". We use the notice.

## The economics: about £6m per MW, with operations included

Spread across the full 30 MW, £180 million is £6.0 million per MW of IT load (our calculation). That figure is not a pure construction cost. It also has to cover land or a lease, the grid connection, security, Janet links and roughly two years of operation after phase 1 goes live. A bidder that already owns a powered shell can put more of it into fit-out; a bidder starting on a greenfield site cannot.

How much of the £350 million "established hardware plus data centre" envelope from July is now going to the building is not stated. If the £180 million comes entirely from that envelope, about £170 million would be left for established-vendor hardware (our calculation). The notices do not say so, and we treat that split as an open question.

Power is the cost that does not stop. DC Market Insights tracks the UK industrial power price at US$233.7 per MWh for 2026, up from US$223.39 in 2025. At that price, 30 MW of IT load running flat out for a year uses 262.8 GWh and costs about US$61.4 million before cooling and losses; 10 MW costs about US$20.5 million (our calculation, DC Market Insights data). The notice is not fully clear on who carries the energy bill: its introduction says operation is "funded separately", while its summary includes "operation of the hosting facility" in the grant. Bidders will want that settled in the 24 November answers.

The Banque de France made the same point in a 4 November note: in AI-dedicated data centres, electricity "accounts for as much as 60% of their operating costs", [authors Josef Nasr and Thaddée Toulouse wrote](https://www.banque-france.fr/en/publications-and-statistics/publications/data-centres-and-energy-environmental-cost-faulty-price-signal).

## The tech: 1.37 MVA per MW and a liquid-cooled hall

The grid ask tells you how much overhead the government expects. Phase 1 needs 14 MVA of import for 10 MW of IT load, or 1.40 MVA per MW. Phase 2 needs 41 MVA for 30 MW, or 1.37. At a power factor of 0.95, 41 MVA is about 39 MW of real power, which leaves room for roughly 30% on top of the IT load for cooling, power conversion and building services (our calculation; the power factor is our assumption). That is consistent with a modern liquid-cooled design rather than an older air-cooled hall.

*Figure 1. Grid import capacity per MW of IT load: the UK AIRR host requirement and Digital Realty's Frankfurt campus. Source: [Find a Grant](https://find-lb.find-a-grant-support.service.cabinetoffice.gov.uk/grants/airr-heterogeneous-supercomputer-host-site-and-data-centre-grant-competition-1); [DCNN](https://dcnnmagazine.com/projects-and-infrastructure/digital-realty-energises-110kv-frankfurt-connection/); our calculation.*

The harder requirement is the grid offer itself. Applicants must hold a written, verifiable offer from a distribution network operator before they bid. In London and Frankfurt, "the waiting time for connection to the electricity grid is up to 10 years", the Banque de France note said. In practice, that limits the field to sites that already have capacity reserved, which favours university campuses with existing high-voltage supplies and co-location operators with spare headroom.

The notice names liquid cooling among the facility's objectives but sets no PUE, water or rack-density figure on its main page. Those details may sit in the scope and evaluation document attached to the competition.

## What private builders are paying for power and space

The public tender lands in a week when private operators showed what power costs them. On 17 November, Digital Realty said it had energised a dedicated 110 kV connection to its Digital Park Fechenheim campus in Frankfurt, [DCNN reported](https://dcnnmagazine.com/projects-and-infrastructure/digital-realty-energises-110kv-frankfurt-connection/). The roughly 16 km underground line from the Karben substation provides up to 300 MVA, took about 20 months to build and commission, and cost "several hundred million euros". The campus is planned for 11 data centres and up to 200 MW of IT capacity; three are operating and a fourth is due in 2027. If "several hundred million" means €200 million to €300 million, the grid link alone costs €1.0 million to €1.5 million per MW of IT (our calculation; the range is our assumption).

> Access to power has become one of the defining factors for digital infrastructure in Frankfurt.

***Volker Ludwig** , Managing Director Central Europe, Digital Realty — [DCNN, 17 Nov 2026](https://dcnnmagazine.com/projects-and-infrastructure/digital-realty-energises-110kv-frankfurt-connection/)*

Grid capacity is also becoming an asset for power companies. Uniper has secured about 700 MW of grid capacity for data centre projects across Europe, on more than 10 potential sites in the UK, Germany, Sweden and the Netherlands, at least five of them in the UK, [Data Centre Review reported](https://datacentrereview.com/2026/11/uniper-bets-on-old-power-station-sites-to-meet-data-centre-demand/) on 17 November, citing the Financial Times. At the former Ratcliffe-on-Soar coal plant, Uniper has applied for a new 720 MW connection to National Grid.

In Munich, Deutsche Telekom is spending just under another €250 million to take its Industrial AI Cloud at Tucherpark to 20 MW, with Nvidia Blackwell Ultra B300 chips, cooling water from the nearby Eisbach and waste heat for the surrounding district, the German news agency dpa [reported on 9 November](https://www.cio.de/article/4246270/deutsche-telekom-ruestet-auf-ki-fabrik-verdoppelt-kapazitaet.html). That figure includes the chips, so it is not comparable with the UK grant, which excludes the computer.

| Project | Spend | Capacity | What the money covers | Source |
| --- | --- | --- | --- | --- |
| UK AIRR host site (grant) | Up to ~£180m | 30 MW IT by Mar 2029 | Building, power, cooling, security, network, operation to Mar 2030; no computer | Find a Grant |
| Digital Realty Fechenheim grid link | "Several hundred million euros" | 300 MVA for up to 200 MW IT | 110 kV line and connection only | DCNN |
| Deutsche Telekom Munich AI factory | Just under €250m more | Up to 20 MW | Expansion including Nvidia B300 chips | dpa via CIO |
| Uniper former power station sites | Not disclosed | ~700 MW grid capacity secured | Grid connections on 10+ sites | Data Centre Review |

Sources as linked in the text. The four figures cover different scopes and currencies and should not be compared as like-for-like cost per MW.

## Who gains and who is squeezed

**Universities and national labs with power on site.**  The lead applicant must be a research organisation eligible for UKRI funding, with experience of running a national-scale compute service. Sites that already host national systems and have spare grid capacity start with an advantage that money alone cannot buy in 14 days.

**Co-location operators outside London.**  Commercial providers can join a bid as UK-incorporated partners under a memorandum of understanding. For an operator with an energised shell and 14 MVA of unused headroom, a government anchor tenant at about £6 million per MW is an attractive way to fill space.

**Contractors and the mechanical and electrical supply chain.**  A 10 MW hall in about 16 months from the January grant agreement is tight. Turner & Townsend's 2026 Global Construction Market Intelligence report found that more than 70% of the 112 markets it surveys report tightening or overstretched contractor capacity for data centres, and that 100% of its UK respondents cite shortages of qualified mechanical, electrical and plumbing workers. London is the fifth most expensive place to build in its survey, at US$6,032 per square metre.

> There's a very real risk that growth in the pool of skilled labor needed to build data centers won't keep up with demand.

***Stephanie Marshall** , Managing Director, Real Estate Cost Management, Turner & Townsend — [Turner & Townsend, 8 Jul 2026](https://www.turnerandtownsend.com/en-us/news/growth-of-ai-infrastructure-driving-job-creation-in-global-construction-market/)*

## The wider pattern: power, not concrete, sets the price

The UK tender is small next to the private pipeline. DC Market Insights tracks 197 UK data centre facilities, with 1,025 MW live, 332 MW under construction and 7,409 MW planned. The AIRR host's 30 MW equals 2.9% of tracked live capacity and about 9% of the capacity under construction (our calculation, DC Market Insights data, 19 November 2026).

*Figure 2. UK data centre capacity tracked by DC Market Insights, by status, against the AIRR host's 30 MW. Source: [DC Market Insights data](https://www.dcmarketinsights.com/data/power-policy/united-kingdom); [Find a Grant](https://find-lb.find-a-grant-support.service.cabinetoffice.gov.uk/grants/airr-heterogeneous-supercomputer-host-site-and-data-centre-grant-competition-1).*

| UK measure | Value | Source |
| --- | --- | --- |
| Tracked UK facilities | 197 (115 with MW) | DC Market Insights data |
| Live capacity | 1,025 MW | DC Market Insights data |
| Under construction | 332 MW | DC Market Insights data |
| Planned | 7,409 MW | DC Market Insights data |
| Industrial power price, 2026 | US$233.7 per MWh | DC Market Insights data |
| AIRR host energy at full IT load, 30 MW, one year | 262.8 GWh, about US$61.4m | Our calculation |

Source: DC Market Insights data, read 19 November 2026. Planned capacity includes projects without a grid offer; the tracked live figure covers only facilities with a stated MW.

Across Europe, the argument is shifting to who pays for the grid. RWE chief executive Markus Krebber said in October that the cost of grid build-out for new demand "is currently not paid by those who are causing the problem", [Bloomberg reported](https://www.energyconnects.com/news/renewables/2026/october/data-center-boom-raises-issue-of-who-pays-for-grid-rwe-says/). In our view, the UK competition answers that question for one site by requiring the bidder to bring its grid offer, and so its connection cost, to the table.

> This is currently not paid by those who are causing the problem.

***Markus Krebber** , Chief Executive Officer, RWE — [Bloomberg via Energy Connects, 7 Oct 2026](https://www.energyconnects.com/news/renewables/2026/october/data-center-boom-raises-issue-of-who-pays-for-grid-rwe-says/)*

### What it means for operators, investors and vendors

Our view, based on the figures above:

- **Use £6m per MW as a public benchmark, not a build cost.**  It bundles land, grid, fit-out and about two years of operation; a bidder with a powered shell should model the fit-out share separately.
- **Grid headroom is the entry ticket.**  Without a written DNO offer of 14 MVA now and 41 MVA by March 2029, a bid fails eligibility. Operators with spare MVA outside London should look at partnering with a university lead before 25 November.
- **Price the energy risk.**  At US$233.7 per MWh, 30 MW of IT load costs about US$61.4m a year before cooling. Bidders should get clarity in the 24 November answers on whether the grant or the operator carries it.
- **Plan for about 1.37 MVA per MW.**  That ratio leaves roughly 30% for cooling and losses, which points to liquid cooling. Vendors of cold plates, coolant distribution units and dry coolers should expect specifications in that range.
- **Lock in contractors early.**  With more than 70% of markets reporting tight data centre contractor capacity, 10 MW by 31 March 2028 needs long-lead plant ordered soon after the 15 January 2027 grant agreement.

For the market this tender sits in, see our [Government Data Center Market](https://www.dcmarketinsights.com/report/government-data-center-market) report and the [UK AI Data Center Market](https://www.dcmarketinsights.com/report/uk-ai-data-center-market) report, which puts UK AI data centre spending at US$3.16 billion in 2026. For the liquid cooling such a hall needs, see the [Data Center Cold Plate Market](https://www.dcmarketinsights.com/report/data-center-cold-plate-market) report, and for the wider build-out the [Europe Data Center Infrastructure Market](https://www.dcmarketinsights.com/report/europe-data-center-infrastructure-market) report. UK rules, grid reforms and power prices are tracked on our [United Kingdom power and policy page](https://www.dcmarketinsights.com/data/power-policy/united-kingdom).

## What to watch next

- **20 November 2026, 12pm:**  deadline for clarification questions on the AIRR host competition.
- **24 November 2026:**  answers to clarification questions due to be published.
- **25 November 2026, 12pm:**  bids close.
- **27 November to 1 December 2026:**  evaluation of applications.
- **8 January 2027:**  applicants told the outcome.
- **15 January 2027:**  grant agreement due to be signed.
- **31 March 2028 and 31 March 2029:**  10 MW and 30 MW of IT load due to be ready.

## Frequently asked questions

### How much will the UK pay to host its new AI supercomputer?

Up to approximately £180 million, subject to approvals. The grant covers the data centre's design, construction, power, cooling, security, network links and operation up to 31 March 2030. It does not cover the supercomputer hardware, which has its own budget within the £750 million programme.

### What is the cost per MW of the UK AIRR host site?

About £6.0 million per MW of IT load, by our calculation, spreading £180 million over the 30 MW required by 31 March 2029. The figure includes land, grid, fit-out and operation, so it is higher than a pure shell-and-core build cost and lower than a full AI facility with chips.

### How much grid power does the AIRR data centre need?

Firm import capacity of at least 14 MVA for phase 1 (10 MW of IT load) and at least 41 MVA by 31 March 2029 (30 MW). That is 1.37 to 1.40 MVA per MW of IT load. Applicants must hold a written grid offer from a distribution network operator when they bid.

### When is the deadline for the AIRR host competition?

Bids close at 12pm on 25 November 2026. Clarification questions are due by 12pm on 20 November and answers by 24 November. The government expects to tell applicants the outcome by 8 January 2027 and to sign the grant agreement by 15 January 2027.

## Sources

1. Find a Grant (UK government), "AIRR Heterogeneous Supercomputer Host Site and Data Centre Grant Competition", opened 11 Nov 2026. [Link](https://find-lb.find-a-grant-support.service.cabinetoffice.gov.uk/grants/airr-heterogeneous-supercomputer-host-site-and-data-centre-grant-competition-1)
2. Department for Science, Innovation and Technology, "Expression of Interest: AIRR Heterogeneous Supercomputer Host Site Selection", 17 Jul 2026, updated 29 Jul 2026. [Link](https://www.gov.uk/government/publications/expression-of-interest-airr-heterogeneous-supercomputer-host-site-selection/expression-of-interest-airr-heterogeneous-supercomputer-host-site-selection)
3. Data Centre Review, "UK Government offers £180m for AI data centre – but there's a catch", 12 Nov 2026. [Link](https://datacentrereview.com/2026/11/uk-government-offers-180m-for-ai-data-centre-but-theres-a-catch/)
4. DCNN, "Digital Realty energises 110kV Frankfurt connection", 17 Nov 2026. [Link](https://dcnnmagazine.com/projects-and-infrastructure/digital-realty-energises-110kv-frankfurt-connection/)
5. Data Centre Review, "Uniper bets on old power station sites to meet data centre demand", 17 Nov 2026. [Link](https://datacentrereview.com/2026/11/uniper-bets-on-old-power-station-sites-to-meet-data-centre-demand/)
6. CIO (dpa), "Deutsche Telekom rüstet auf: KI-Fabrik verdoppelt Kapazität", 9 Nov 2026. [Link](https://www.cio.de/article/4246270/deutsche-telekom-ruestet-auf-ki-fabrik-verdoppelt-kapazitaet.html)
7. Banque de France, Josef Nasr and Thaddée Toulouse, "Data centres and Energy: the environmental cost of a faulty price signal", Eco Notepad 470, 4 Nov 2026. [Link](https://www.banque-france.fr/en/publications-and-statistics/publications/data-centres-and-energy-environmental-cost-faulty-price-signal)
8. Turner & Townsend, "Growth of AI infrastructure driving job creation in global construction market", 8 Jul 2026. [Link](https://www.turnerandtownsend.com/en-us/news/growth-of-ai-infrastructure-driving-job-creation-in-global-construction-market/)
9. Turner & Townsend, "Global Construction Market Intelligence 2026: UK", 2026. [Link](https://publications.turnerandtownsend.com/global-construction-market-intelligence-2026/uk)
10. Energy Connects (Bloomberg), "Data Center Boom Raises Issue of Who Pays for Grid, RWE Says", 7 Oct 2026. [Link](https://www.energyconnects.com/news/renewables/2026/october/data-center-boom-raises-issue-of-who-pays-for-grid-rwe-says/)
11. DC Market Insights, "Data Center Power & Policy in United Kingdom" (facilities, MW by status and power price data), read 19 Nov 2026. [Link](https://www.dcmarketinsights.com/data/power-policy/united-kingdom)