# Google plans a US$10bn, 1.2 GW campus near Châteauroux, its first in France. Consultation ends 10 January

> Google's CNDP dossier puts its first French self-built campus at about US$10bn and up to 1,200 MW of grid power. The public consultation runs to 10 January 2027.

Publisher: DC Market Insights  
Published: 2026-11-17  
Last updated: 2026-11-17  
Page: https://www.dcmarketinsights.com/news/google-plans-a-us10bn-1-2-gw-campus-near-chateauroux-its-first-in-france-consultation-ends-10-january

## Key takeaways

- Google's first self-built data centre in France, on the ZAC d'Ozans near Châteauroux, is costed at about US$10 billion (about €8.6 billion) for the buildings and Google's share of the grid connection, excluding IT equipment (CNDP concertation dossier).
- The site would draw 120 MW over a 225 kV link in phase 1 and up to 1,200 MW over 400 kV once RTE builds a new Éguzon–Marmagne line (CNDP dossier).
- That is about US$8.3 million per MW of connection power, and 3.7 times all the live data centre capacity in DC Market Insights' France tracker (321.5 MW) (our calculation).
- On 13 November ENGIE signed a memorandum with Google to become its preferred energy supplier for the project, including new clean generation and grid-scale batteries (ENGIE).
- The public concertation run by the CNDP opened on 2 November and closes on 10 January 2027, 54 days from today (CNDP; our count).

Google has put a price and a size on its first French campus. The dossier it filed for the public concertation on the Ozans data centre near Châteauroux, in the Indre département, puts the investment at about US$10 billion and the grid connection at up to 1,200 MW. That is a 1.2 GW hyperscale campus in a part of central France with no large data centre today.

Why now: the concertation opened on 2 November, its first public meetings were held on 9 and 13 November, and on 13 November ENGIE announced it could become Google's "preferred Energy Supplier & Management Partner" for the site. With RTE's own consultation on the 400 kV line that the full campus needs closing on 22 November, the next eight weeks decide whether France's money is starting to move out of Paris and Dunkirk and into the middle of the country.

**US$10bn** Investment in buildings and Google's share of the grid link, excluding IT (CNDP dossier)

**1,200 MW** Connection power at full build, after a new RTE 400 kV line (CNDP dossier)

**10 Jan 2027** Close of the public concertation (CNDP)

## What Google has put on the table

The project is run by Google France with two project companies, Tricolore Computing and Violet Computing, on land in the ZAC d'Ozans at Étrechet, about 10 km from Châteauroux. The dossier describes it as Google's first data centre in France that it would build and operate itself; today Google only rents colocation space in the country.

The numbers in the [dossier de concertation](https://www.debatpublic.fr/sites/default/files/2026-11/dc-ozans-dossier-de-concertation-vf-14-oct_.pdf) are these:

- **Investment:**  "un investissement total d'environ 10 milliards de dollars (soit environ 8,6 milliards d'euros hors taxes)" for six to eight buildings and Google's share of the connection, excluding IT hardware and software. The dossier says it is "encore trop tôt" to estimate the total cost. It is to be funded entirely from Alphabet's own funds, with no public subsidy.
- **Power:**  a 225 kV connection "pour une puissance de 120 MW" for the first building, then a 400 kV connection for 300 MW, which "pourra être portée à 1 200 MW" once RTE builds a new 400 kV line between Éguzon and Marmagne.
- **Buildings:**  a first building of about 30,000 m² on one level, then six to eight buildings in all over 10 to 20 years.
- **Land:**  about 200 hectares in the dossier; the CNDP project page says about 195 hectares. The land price agreed with Châteauroux Métropole was €58.5 million, according to Tom's Guide and Blog du Modérateur; that figure is the land, not the project.
- **Grid works:**  RTE's connection is costed at about €25 million for the 225 kV link and about €100 million for the 400 kV link, €125 million in all, provisionally. For the main supply Google pays 70% and RTE 30%; the redundant supply and the private 400 kV substation are 100% Google.

Timing and scale differ between the two CNDP documents. The [CNDP project page](https://www.debatpublic.fr/data-center-ozans-chateauroux-de-google-et-son-raccordement-electrique-8996) gives phase 1 in 2028-2029, a phase 2 from 2031 and 8 to 10 buildings; the dossier (page 9) speaks of a first building "à l'horizon 2030" and six to eight buildings. Earlier press put the power at "more than 500 MW" (Observatoire des multinationales) or 880 MW to 1.1 GW (Le Monde, cited by Blog du Modérateur). We use the dossier's 1,200 MW connection figure, which is power drawn from the grid, not IT load.

*Figure 1. Google Ozans grid connection power by stage against all live MW in our France tracker. Source: [CNDP concertation dossier](https://www.debatpublic.fr/sites/default/files/2026-11/dc-ozans-dossier-de-concertation-vf-14-oct_.pdf); DC Market Insights facilities data, 17 Nov 2026.*

## What changed on 13 November: ENGIE as the power partner

ENGIE and Google signed a memorandum of understanding under which ENGIE "could become Google's preferred Energy Supplier & Management Partner, subject to entering into further agreements", [ENGIE said on 13 November](https://en.newsroom.engie.com/news/engie-and-google-to-partner-on-energy-solutions-for-a-potential-data-center-project-near-chateauroux-france-28082-314df.html). The scope covers a "balanced, large-scale and multi-technology clean energy portfolio, including renewable generation arrangements at a national level", utility-scale and behind-the-meter battery storage for grid integration, energy efficiency for local homes, electric mobility, and an assessment of waste heat recovery for district heating, "free of charge".

ENGIE stressed that the new clean capacity should not raise power prices for French households or businesses. The release gives no MW, no price and no contract term; it is not a power purchase agreement.

> Our proposed project in Châteauroux is designed to support the local community.

***Aris Karcanias** , EMEA Head of Energy & Infrastructure, Google — [ENGIE newsroom, 13 Nov 2026](https://en.newsroom.engie.com/news/engie-and-google-to-partner-on-energy-solutions-for-a-potential-data-center-project-near-chateauroux-france-28082-314df.html)*

> Data centers are becoming an important part of our energy systems.

***Edouard Neviaski** , Executive Vice President, Supply & Energy Management, ENGIE — [ENGIE newsroom, 13 Nov 2026](https://en.newsroom.engie.com/news/engie-and-google-to-partner-on-energy-solutions-for-a-potential-data-center-project-near-chateauroux-france-28082-314df.html)*

## How we got here: France opened the door, the grid sets the pace

Google referred the project to the Commission nationale du débat public (CNDP) on 24 March 2026, and the CNDP decided on 1 April to hold a concertation préalable with three guarantors, according to [Blog du Modérateur](https://www.blogdumoderateur.com/data-centers-projet-google-chateauroux-methode-francaise/). The Châteauroux council had voted the land sale agreement in June 2025.

The national frame is unusually supportive. Law no. 2026-403 on simplifying economic life (26 May 2026) made large data centres eligible for the status of project of major national interest (article 35), and the state has identified 63 sites for data centres with Business France, according to the policy entries in our [France power and policy page](https://www.dcmarketinsights.com/data/power-policy/france). A tax cut of €10.5 per MWh on electricity for large data centres was announced in February 2025.

The constraint is the grid, and Ozans shows it in miniature. The existing high-voltage lines at the site are full, according to Blog du Modérateur and the [Observatoire des multinationales](https://multinationales.org/en/investigations/behind-the-data-center-boom-in-france/google-in-chateauroux-the-inside-story-of-a-massive-data-center-project). The Éguzon–Marmagne corridor was raised from 1,400 MW to 2,200 MW of transit by works in 2021-22; the new 400 kV line would take it to about 7,600 MW, the dossier says. Both outlets put that line at about €300 million, with works not before 2032. Until then, Google's campus is capped at the 120 MW and 300 MW stages.

Nationally, RTE had reserved "près de 18 GW" for about 80 data centre projects by May 2026, up from about 5 GW for about 40 projects at the end of 2024, according to [RTE](https://www.rte-france.com/bases-electricite/consommation-electricite/essor-data-centers-france). About 7 GW of that is in Île-de-France and about 6 GW in Hauts-de-France. RTE is now preparing to replace "premier arrivé, premier servi" with "premier prêt, premier servi", giving priority to mature projects, [ITforBusiness reported on 9 November](https://www.itforbusiness.fr/raccordement-datacenters-rte-premier-pret-premier-servi-109627). On 16 November [CFNEWS Infra](https://www.cfnewsinfra.net/L-actualite/Bilans/Data-centers-RTE-trie-les-projets) headlined that RTE is now sorting the projects.

*Figure 2. Where Google's 1.2 GW fits in France's data centre grid pipeline. Source: [RTE](https://www.rte-france.com/bases-electricite/consommation-electricite/essor-data-centers-france) (page dated 1 Jun 2026); CNDP dossier; DC Market Insights data.*

## Who gains, and how much

**Central France.**  Ozans is outside the two regions that hold 13 of RTE's 18 GW of reservations. A single 1.2 GW site would be about 6.7% of all reserved data centre capacity in France and 3.7 times the 321.5 MW of live capacity in our France tracker, which holds 55 facilities (our calculation; DC Market Insights data). The mayor of Châteauroux sees it as a turning point.

> A historic opportunity for development, job creation and activity for our département.

***Gil Avérous** , Mayor of Châteauroux and President of Châteauroux Métropole (translated from French) — [Blog du Modérateur, 25 Sep 2026](https://www.blogdumoderateur.com/data-centers-projet-google-chateauroux-methode-francaise/)*

**Jobs are contested.**  Avérous has spoken of nearly 1,000 direct and indirect jobs. Blog du Modérateur and the Observatoire des multinationales both apply a ratio of one job per 10,000 m² of floor space and get about 200 direct jobs. We report both and add neither.

**ENGIE and RTE.**  At full build and an 80% load factor, the campus would use about 8.4 TWh a year (1,200 MW × 8,760 hours × 0.8, our calculation). That is about 84% of what all French data centres use today, roughly 10 TWh or about 2% of national consumption, according to RTE. Priced at the 2025 French industrial power price in our tracker, US$104.41 per MWh, it is a power bill of about US$880 million a year (our calculation; Google's actual price is not public). Phase 1 alone, at 120 MW, is about 0.84 TWh.

| Measure | Value | Basis |
| --- | --- | --- |
| Investment, excluding IT | ~US$10bn (~€8.6bn) | CNDP dossier |
| Investment per MW of connection power | ~US$8.3m (~€7.2m) | Our calculation |
| RTE connection works, provisional | €125m (€25m 225 kV + €100m 400 kV) | CNDP dossier |
| Connection cost per MW at 1,200 MW | ~€104,000 | Our calculation |
| Annual use at 80% load, full build | ~8.4 TWh | Our calculation |
| Annual power bill at 2025 industrial price | ~US$880m | Our calculation; DC Market Insights data |
| Power density of the site | ~6.2 MW per hectare (1,200 MW on 195 ha) | Our calculation |
| Share of France's 2025 data centre market value | Investment ≈ 93% of US$10.75bn | Our calculation; DC Market Insights estimate |

Sources: [CNDP dossier](https://www.debatpublic.fr/sites/default/files/2026-11/dc-ozans-dossier-de-concertation-vf-14-oct_.pdf); [RTE](https://www.rte-france.com/bases-electricite/consommation-electricite/essor-data-centers-france); [DC Market Insights, France Data Center Market](https://www.dcmarketinsights.com/report/france-data-center-market). Per-MW figures use connection power, not IT load, and exclude servers, so they are not comparable with all-in AI campus costs. The market comparison sets a multi-year investment against one year of market value; it shows scale only.

**Who may lose.**  Local resistance is real. In Étrechet, three deputy mayors and a councillor resigned by a letter dated 10 September, and the mayor gave up her sash on 15 September, Blog du Modérateur reported. Objections raised locally include land take, water, tax contribution and exposure to US law, the Observatoire des multinationales reported. We did not find a water-use figure in the parts of the dossier we read; the environment workshop on 25 November is where it should be tested.

> We can no longer remain in office or take on a project that contradicts our deepest convictions.

***Marie-Pierre Chabenat-Canals** , then second deputy mayor of Étrechet, to Le Monde (translated from French) — [Blog du Modérateur, 25 Sep 2026](https://www.blogdumoderateur.com/data-centers-projet-google-chateauroux-methode-francaise/)*

## The wider pattern: France's pledges are turning into dossiers

France is the European market where announced money is largest. The consultancy Trendeo counted €88.3 billion of data centre investment announced in France in the first half of 2026 alone, [France Épargne reported](https://www.france-epargne.fr/news/data-centers-883-milliards-annonces-en-france-18-gw-en-attente-de-raccordement); RTE puts Choose France 2026 at "plus de 93 milliards". Those are different bases and must not be added. Google's €8.6 billion is about a tenth of Trendeo's half-year figure (our calculation).

What is new is that a hyperscaler has filed a costed, phased plan with a public timetable. Many of the 18 GW of reservations may never be used; [Institut Quorum](https://www.institut-quorum.fr/article-data-centers-reseau-electrique) notes that recently connected sites use only about 20% of the power they requested. RTE's maturity rule is designed to separate those from projects like Ozans.

| Project | Size | Money | Status |
| --- | --- | --- | --- |
| Google, Ozans (Châteauroux), France | 120 MW → up to 1,200 MW | ~US$10bn excl. IT | CNDP concertation to 10 Jan 2027; ENGIE MoU 13 Nov |
| Brookfield–Drax AI campus, UK | >1 GW; phase 1 100 MW | >£20bn incl. chips; phase 1 £2.5bn | Public consultation this month |
| Google, Finland (four sites) | Not disclosed | ≥€13bn | Build 2027-28; Fortum nuclear PPA |
| Data4, France (DCMI tracker) | 255 MW live, 950 MW pipeline | n/a | Largest tracked French pipeline |

Sources: CNDP dossier; our analyses of [Brookfield–Drax](https://www.dcmarketinsights.com/news/brookfields-us27bn-drax-ai-campus-prices-phase-1-at-us33m-per-mw-its-public-consultation-starts-this-month) (4 Nov) and [Finland](https://www.dcmarketinsights.com/news/finland-drew-e23-billion-of-data-centre-pledges-after-ending-its-tax-break-its-grid-queue-law-is-next) (20 Oct), with primary sources listed there; DC Market Insights facilities data (FR), 17 Nov 2026. Money figures use different scopes (with or without chips) and must not be compared per MW.

### What it means for operators, investors and vendors

Our view, based on the figures above:

- **Operators: follow the 400 kV corridors, not the cities.**  Ozans works because a 2,200 MW line passes nearby and RTE can take it to about 7,600 MW. Sites next to existing 400 kV lines with spare transit are the next Châteauroux.
- **Plan for 120 MW, not 1.2 GW, until 2032.**  The full campus depends on an Éguzon–Marmagne line whose works are not expected before 2032. Model the first five years on the 120 MW and 300 MW stages.
- **Investors: price the US$8.3m per MW as shell and power only.**  With IT equipment excluded, the all-in AI cost per MW is several times higher; financing for comparable campuses should be sized on that basis.
- **Utilities: the ENGIE model is the template.**  A preferred-supplier deal bundling new clean generation, batteries and heat recovery answers the question of who pays; expect it in other French and EU tenders.
- **Vendors: 225 kV and 400 kV substation kit is the first order.**  Two substations and about 10 km of overhead 400 kV line, plus €125m of connection works, come before the halls.
- **Developers: get ready for "premier prêt, premier servi".**  RTE's maturity rule will reward projects with land, permits and a public dossier; 18 GW of reservations will not all survive it.

For the size of the French market, see our [France Data Center Market](https://www.dcmarketinsights.com/report/france-data-center-market), [France AI Data Center Market](https://www.dcmarketinsights.com/report/france-ai-data-center-market) and [France Data Center Infrastructure Market](https://www.dcmarketinsights.com/report/france-data-center-infrastructure-market) reports. National rules, tariffs and grid procedures are tracked on our [France power and policy page](https://www.dcmarketinsights.com/data/power-policy/france) within the [Data Center Power & Policy Tracker](https://www.dcmarketinsights.com/data/power-policy).

## What to watch next

- **22 November 2026:**  RTE's concertation on the Éguzon–Marmagne 400 kV line, which the full campus needs, closes.
- **25 and 28 November 2026:**  environment workshop in Déols (25 Nov) and public site visits (25 and 28 Nov).
- **3 and 10 December 2026:**  workshops on employment and training, then on planning, socio-economics and energy, in Châteauroux.
- **17 December 2026:**  public meeting in Étrechet.
- **Week of 4 January 2027:**  summary public meeting.
- **10 January 2027:**  the concertation closes.
- **By about 10 February 2027:**  the guarantors publish their report, one month after the close; Google and RTE then have two months to respond, to about 10 April 2027 (our count).

## Frequently asked questions

### How much will Google invest in its Châteauroux data centre?

About US$10 billion, or about €8.6 billion before tax, for six to eight buildings and Google's share of the grid connection, according to the CNDP concertation dossier. IT hardware and software are excluded, and the project is funded from Alphabet's own funds with no public subsidy.

### How much power will the Google data centre near Châteauroux use?

Phase 1 connects 120 MW at 225 kV. A 400 kV connection follows at 300 MW and can rise to 1,200 MW once RTE builds a new Éguzon–Marmagne line. At 80% load, 1,200 MW is about 8.4 TWh a year (our calculation).

### When does the public consultation on Google's Ozans project end?

The CNDP concertation runs from 2 November 2026 to 10 January 2027, with workshops on 25 November, 3 and 10 December and a public meeting in Étrechet on 17 December. The guarantors report about a month after the close.

### What did ENGIE and Google agree?

On 13 November 2026 they signed a memorandum under which ENGIE could become Google's preferred energy supplier for the project. It covers new clean generation, battery storage and heat recovery, but gives no MW, price or term and is not a power purchase agreement.

## Sources

1. ENGIE, "ENGIE and Google to partner on energy solutions for a potential data center project near Châteauroux, France", 13 Nov 2026. [Link](https://en.newsroom.engie.com/news/engie-and-google-to-partner-on-energy-solutions-for-a-potential-data-center-project-near-chateauroux-france-28082-314df.html)
2. Commission nationale du débat public (CNDP), "Data center Ozans (Châteauroux) de Google et son raccordement électrique", updated 2 Nov 2026. [Link](https://www.debatpublic.fr/data-center-ozans-chateauroux-de-google-et-son-raccordement-electrique-8996)
3. Google France / RTE, Dossier de concertation, Data center d'Ozans, Sept 2026 (via CNDP). [Link](https://www.debatpublic.fr/sites/default/files/2026-11/dc-ozans-dossier-de-concertation-vf-14-oct_.pdf)
4. RTE, "Les data centers en chiffres clés", page dated 1 Jun 2026. [Link](https://www.rte-france.com/bases-electricite/consommation-electricite/essor-data-centers-france)
5. ITforBusiness, "Raccordement des datacenters : RTE privilégie les projets prêts", 9 Nov 2026. [Link](https://www.itforbusiness.fr/raccordement-datacenters-rte-premier-pret-premier-servi-109627)
6. CFNEWS Infra, "Data centers : RTE trie les projets", 16 Nov 2026. [Link](https://www.cfnewsinfra.net/L-actualite/Bilans/Data-centers-RTE-trie-les-projets)
7. Blog du Modérateur, "Data centers : ce que le projet de Google à Châteauroux dit de la méthode française", 25 Sep 2026. [Link](https://www.blogdumoderateur.com/data-centers-projet-google-chateauroux-methode-francaise/)
8. Observatoire des multinationales, "Google in Châteauroux: the inside story of a massive data center project", 10 Mar 2026. [Link](https://multinationales.org/en/investigations/behind-the-data-center-boom-in-france/google-in-chateauroux-the-inside-story-of-a-massive-data-center-project)
9. Tom's Guide France, "Châteauroux dans le viseur de Google : un projet à 58,5 millions d'euros en discussion", 30 Jun 2025. [Link](https://www.tomsguide.fr/chateauroux-dans-le-viseur-de-google-un-projet-a-585-millions-deuros-en-discussion/)
10. France Épargne, "Data centers : 88,3 milliards annoncés en France au S1 2026" (Trendeo figures), 1 Sep 2026. [Link](https://www.france-epargne.fr/news/data-centers-883-milliards-annonces-en-france-18-gw-en-attente-de-raccordement)
11. Institut Quorum, "Data centers : 18 GW demandés, une acceptabilité à construire", 17 Sep 2026. [Link](https://www.institut-quorum.fr/article-data-centers-reseau-electrique)
12. DC Market Insights, France facilities, policy and metrics data, 17 Nov 2026. [Link](https://www.dcmarketinsights.com/data/power-policy/france)
13. DC Market Insights, France Data Center Market report. [Link](https://www.dcmarketinsights.com/report/france-data-center-market)
14. DC Market Insights, "Brookfield's US$27bn Drax AI campus prices phase 1 at US$33m per MW", 4 Nov 2026. [Link](https://www.dcmarketinsights.com/news/brookfields-us27bn-drax-ai-campus-prices-phase-1-at-us33m-per-mw-its-public-consultation-starts-this-month)