IXcellerate Data Centers

Data centers operated by IXcellerate that we have verified: location, status and capacity, each checked against its source.

In short

As of 7 October 2026, DC Market Insights tracks 10 data centers operated by IXcellerate in 1 country, of which 5 are operational. Stated operational capacity is 128 MW, with a further 40 MW under construction and 34 MW planned. The pipeline is 0.6 times the capacity already operating.

10Facilities tracked
1Countries
128 MWOperational (5 sites)
40 MWUnder construction (1 site)
34 MWPlanned (4 sites)

MW = IT capacity where the source states it, otherwise total capacity. 7 of 10 facilities have a stated capacity; the others are counted as sites only.

IXcellerate MOS1 · IXcellerate · Moscow (approximate location)IXcellerate MOS2 · IXcellerate · Moscow (approximate location)IXcellerate MOS3 · IXcellerate · Moscow (approximate location)IXcellerate MOS4 · IXcellerate · Moscow (approximate location)IXcellerate MOS5 · IXcellerate · Moscow (approximate location)IXcellerate MOS6 · IXcellerate · Moscow (approximate location)IXcellerate MOS7 · IXcellerate · Moscow (approximate location)IXcellerate MOS8 · IXcellerate · Moscow (approximate location)IXcellerate MOS11 (Vёshki) · IXcellerate · Mytishchi (approximate location)IXcellerate MOS12 (Vёshki) · IXcellerate · Mytishchi (approximate location)
Operational Under construction Planned Select a country on the map to open its page.

Market snapshot

IXcellerate data centers: key facts

About IXcellerate

IXcellerate operates commercial data centres in Moscow, offering colocation of server and telecom equipment. As stated on its website in October 2026, it has more than five operating data centres across three locations: the North campus in Altufyevo (MOS1-MOS4), the South site in Biryulyovo (MOS5) and a new campus in Vyoshki.

Tracked footprint
10 facilities in 1 country
Website
ixcellerate.ru

Company details checked against company and official sources, 7 Oct 2026.

  • Capacity under construction or planned (74 MW) is 0.6 times the operational base of 128 MW.
  • Its largest operational site is IXcellerate MOS5 in Moscow, Russia at 64 MW.
  • The largest project in the pipeline is IXcellerate MOS11 (Vёshki) (40 MW, under construction).
  • 7 of 10 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational128 MW
Under construction40 MW
Planned34 MW

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

IXcellerate development pipeline

Under construction and planned facilities with a stated capacity, largest first. 40 MW under construction and 34 MW planned in total.

ProjectLocationStatusTypeCapacity
IXcellerate MOS11 (Vёshki)IXcellerate Mytishchi, Russia Under construction Colocation 40 MW
IXcellerate MOS7IXcellerate Moscow, Russia Planned Colocation 34 MW

Facilities

10 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
IXcellerate MOS5Colocation Moscow, Russia Operational 64 MW total — Operator / official
IXcellerate MOS11 (Vёshki)Colocation Mytishchi, Russia Under construction 40 MW total — Operator / official
IXcellerate MOS7Colocation Moscow, Russia Planned 34 MW total — Operator / official
IXcellerate MOS3Colocation Moscow, Russia Operational 30 MW total — Operator / official
IXcellerate MOS1Colocation Moscow, Russia Operational 13.7 MW total — Operator / official
IXcellerate MOS2Colocation Moscow, Russia Operational 13 MW total — Operator / official
IXcellerate MOS4Colocation Moscow, Russia Operational 7 MW total 2022 Operator / official
IXcellerate MOS12 (Vёshki)Colocation Mytishchi, Russia Planned — — Operator / official
IXcellerate MOS6Colocation Moscow, Russia Planned — — Operator / official
IXcellerate MOS8Colocation Moscow, Russia Planned — — Operator / official

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: the source’s address where given, otherwise the city centre (approximate).
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers does IXcellerate operate?

DC Market Insights tracks 10 IXcellerate data centers in 1 countries as of October 2026: 5 operational, 1 under construction and 4 planned.

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Need the full list, or a capacity view of one market?

Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.

Talk to an analyst