Proprietary data

Data Center Power & Policy Tracker

Our own database of government actions on data centers and power: moratoriums, grid connection rules, incentives, tariffs and national plans, with official power prices and renewable shares by country. Each item is checked against its source.

In short

As of 4 November 2026, DC Market Insights tracks 422 government actions on data centers and power and official power indicators for 48 countries: 279 actions in force, including 22 restrictions or moratoriums and 33 incentive schemes.

422Actions tracked
48Countries
22Restrictions in force
33Incentives in force

Market snapshot

Data center power and policy: key facts

  • Countries with a restriction or moratorium on new data centers in force: Canada, China, Germany, Denmark, Ecuador, United Kingdom, Ireland, Iceland, Kyrgyzstan, Malaysia, Netherlands, Paraguay, Russia, Taiwan and Uzbekistan.
  • Countries with a data center incentive in force: Argentina, Australia, Brazil, Colombia, France, United Kingdom, Guatemala, Hong Kong, Indonesia, India, Iceland, Kyrgyzstan, Malaysia, Panama, Peru, Pakistan, Paraguay, United States, Uruguay and Venezuela.
  • Industrial electricity price among tracked countries ranges from 33.0 USD/MWh in Paraguay to 240 USD/MWh in Switzerland.
  • Renewable share of electricity generation among tracked countries ranges from 2% in Bangladesh to 100% in Iceland.
  • Latest change: Government agreement with Solaria for a 500 MW data center park under the free zone regime, Uruguay (14 Oct 2026).
Industrial electricity price, USD/MWh (latest year)
Switzerland240 USD/MWh
Ireland234 USD/MWh
United Kingdom234 USD/MWh
Singapore189 USD/MWh
Italy184 USD/MWh
Belgium183 USD/MWh
Hong Kong180 USD/MWh
Germany180 USD/MWh
Austria169 USD/MWh
Luxembourg165 USD/MWh
Netherlands148 USD/MWh
Denmark134 USD/MWh
Spain113 USD/MWh
Malaysia105 USD/MWh
Renewable share of electricity generation (latest year)
Brazil86.8%
Denmark81.5%
Panama74.7%
Canada63.9%
Peru62.6%
Germany58.8%
Government actions by type
Plan or strategy86
Regulation79
Power tariff53
Grid access52
Incentive47
Efficiency rule35
Restriction27
Renewable energy26
Other9
Moratorium8

Countries

Open a country for every action in force, the full timeline and its power indicators.

CountryActionsIn forceRestrictionsIncentivesIndustrial power priceRenewable shareLatest change
China161420—38% (2025)1 Jul 2025
United States15120186.2 USD/MWh (2025)24% (2025)3 Aug 2026
Austria13700169 USD/MWh (2026)78% (2025)12 Oct 2026
United Kingdom13911234 USD/MWh (2026)52.1% (2025)29 Jul 2026
Hong Kong121002180 USD/MWh (2026)—29 Apr 2026
Netherlands12740148 USD/MWh (2025)49% (2025)31 Mar 2026
Switzerland12800240 USD/MWh (2026)70.8% (2025)8 Sep 2026
Taiwan12910—12.7% (2025)19 Aug 2026
Uruguay121103101 USD/MWh (2026)98% (2025)14 Oct 2026
India1170582.1 USD/MWh (2025)28.7% (2026)13 Aug 2026
Nepal11400——12 May 2026
Pakistan1160197.5 USD/MWh (2026)34.7% (2025)7 Sep 2026
Uzbekistan1121083.3 USD/MWh (2026)19.4% (2025)19 Sep 2026
Venezuela11801—77% (2023)13 Aug 2026
Australia10602—39% (2025)24 Sep 2026
Iceland1071242.9 USD/MWh (2022)100% (2026)27 May 2026
Panama1090166.3 USD/MWh (2025)74.7% (2025)19 Aug 2026
Paraguay1081233.0 USD/MWh (2026)—9 Jun 2026
France9401104 USD/MWh (2025)27% (2025)26 May 2026
Germany9710180 USD/MWh (2025)58.8% (2025)24 Sep 2026
Ireland9820234 USD/MWh (2025)41.3% (2024)20 May 2026
Japan9700—23.1% (2024)5 Aug 2026
Singapore9500189 USD/MWh (2025)2.1% (2024)27 Aug 2026
Canada8420—63.9% (2024)13 Aug 2026
Guatemala860284.5 USD/MWh (2025)53.5% (2024)1 Jan 2026
Indonesia860162.9 USD/MWh (2024)16.3% (2025)10 Sep 2026
Kazakhstan8100—14.6% (2025)13 Aug 2026
Kyrgyzstan881141.7 USD/MWh (2026)88% (2024)24 Apr 2026
Luxembourg8700165 USD/MWh (2025)23.3% (2025)16 Apr 2026
Malaysia8511105 USD/MWh (2026)21% (2025)24 Feb 2026
Sri Lanka8000—60.2% (2025)15 Aug 2026
Chile7600—66% (2025)17 Sep 2026
South Korea7200—9.8% (2025)29 Jun 2026
Spain7400113 USD/MWh (2025)55.5% (2025)27 Aug 2026
Sweden730078.5 USD/MWh (2025)—25 Aug 2026
Argentina6502—19.6% (2025)24 Jun 2026
Brazil6301—86.8% (2025)6 Oct 2026
Colombia6602——23 Feb 2026
Denmark6410134 USD/MWh (2025)81.5% (2024)1 Oct 2026
Ecuador6510——30 Sep 2026
Finland630058.4 USD/MWh (2025)57% (2024)8 Oct 2026
Italy6500184 USD/MWh (2025)48% (2025)3 Aug 2026
Mexico6600——4 May 2026
Peru6501—62.6% (2025)26 Sep 2025
Russia6520—17.6% (2025)25 Jul 2026
United Arab Emirates5000120 USD/MWh (2026)8.8% (2024)30 Dec 2025
Bangladesh4200—2% (2025)20 Aug 2025
Belgium4300183 USD/MWh (2025)34.3% (2025)25 Jun 2026

Latest changes

  • OtherAnnouncedUruguay

    Government agreement with Solaria for a 500 MW data center park under the free zone regime

    On 14 October 2026 President Orsi signed an agreement with Solaria Energía y Medio Ambiente for a 500 MW data center technology park in Canelones, San José and Florida under the free zone regime: USD 5.5 billion for data centers plus USD 200 million for 350 MW of solar. Phase 1: 200 MW of data centers and all the solar (around 2029); phase 2 adds 300 MW.

    500 MW Planned data center capacity (200 MW phase 1, 300 MW phase 2)

    Presidencia de la República · Presidencia – Presidente Orsi anunció la mayor inversión en la historia del país

  • Power tariffAnnouncedAustria

    New grid tariff principles (SNE-G-V) from 2027: 50:50 energy/capacity split and cheaper flexible capacity

    E-Control's new Systemnutzungsentgelte-Grundsatzverordnung under the ElWG is the basis for network charges from 1 Jan 2027. The ratio of energy price to capacity price moves in steps over three years to 50:50. Flexible withdrawal capacity is expected to pay only 25% of the regular capacity price, guaranteed for ten years, and replaces the interruptible tariff within three years.

    25 % Expected share of the regular capacity price paid for flexible capacity

    E-Control · Effective 1 Jan 2027 · E-Control Pressegespräch, Neue Regeln für die Energiewende, 12 Oct 2026

  • RestrictionProposedFinland

    Draft Electricity Market Act amendment: priority procedure for grid connection offers when capacity is short, data centres kept out of the top group

    The Ministry of Economic Affairs and Employment (TEM) has circulated a draft bill amending the Electricity Market Act to rank grid connection requests when network capacity is insufficient. Group 1 (protected) covers households, most small and medium industry and critical uses, including non-data-centre consumption sites up to 3 MW connection power; data centres are excluded from group 1 and have different limits from other consumption. Groups 2 to 4 would be processed twice a year. A customer that commits flexible generation of at least 80% of the site's peak power on an organised market moves from group 3 to group 2; a commitment to supply from a named power plant is also possible. Fingrid supports the bill and wants it in force as fast as possible. Comments closed around 8-9 Oct 2026; the bill is expected in Parliament later in autumn 2026. Figures as described in Energiateollisuus' c

    3 MW Group 1 limit for non-data-centre consumption sites (data centres excluded); flexibility threshold 80% of peak power to move from group 3 to group 2. Date = Energiateollisuus statement on the draft (8 Oct 2026); the government consultation page could not

    Ministry of Economic Affairs and Employment (TEM)

  • Grid accessProposedBrazil

    ANEEL Public Consultation 36/2026: transition rule for large-load expansions under PNAST

    ANEEL proposes adapting transmission rules (REN 1.017/2022, network procedures) to PNAST, with a transition rule for load expansions by consumers already in the access process before the new model, including data centers. ONS would prioritise expansions due in 2029 for requests filed by 22 January 2026, subject to remaining capacity and technical validation; it is not an automatic capacity reserve. Contributions run 8 October to 22 November 2026.

    National Electric Energy Agency (ANEEL)

  • RestrictionAnnouncedDenmark

    Grid emergency plan (akutplan for elnettet): priority model puts most data centres last in the grid connection queue

    Voting agreement of 1 October 2026 between the government (S, SF, M, RV) and V, DF, K, EL and ALT (following a political understanding of 29 June 2026) to pass a bill amending the Electricity Supply Act with a priority model for grid connections when capacity is short. Category 1: protected needs and critical functions (normal demand growth, households, small firms, defence, health); 2: direct electrification, renewables, CCS, hydrogen and PtX; 3: energy storage; 4: certain large energy consumers, as a rule data centres that are not tied to a location. Data centres serving critical societal functions can be placed in category 1. Energinet and grid companies may refuse requests in categories 3 and 4 (appeal to Forsyningstilsynet); grid-friendliness (flexible demand) can improve the position in categories 2 to 4. A separate work stream will look at how data centres can connect without crow

    4 priority category Most data centres placed in category 4 of 4 (lowest); bill still to be passed

    Ministry of Climate, Energy and Utilities (Klima-, Energi- og Forsyningsministeriet); Folketing · Klima-, Energi- og Forsyningsministeriet, 'Aftale om akutplan for elnettet' (1 Oct 2026)

  • Power tariffIn forceEcuador

    ARCONEL temporary high-voltage tariff: average 0.30 USD/kWh (AV1) and 0.29 USD/kWh (AV2) for Oct to Dec 2026

    ARCONEL's board approved a reform of the 2026 tariff level for high-voltage consumers (groups AV1 and AV2): an average price of 30 US cents/kWh for AV1 and 29 US cents/kWh for AV2, applied to consumption in October, November and December 2026. The government says the previous average for this segment was about 12 US cents/kWh; the increase reflects the cost of new thermal generation (power barges) and fuel during the dry season. Residential tariffs do not change.

    300 USD/MWh (AV1 average price) AV1 30 cUSD/kWh = 300 USD/MWh; AV2 29 cUSD/kWh = 290 USD/MWh. Resolution number not given in the bulletin. Earlier average about 12 cUSD/kWh (El Universo, 1 Oct 2026).

    Agencia de Regulación y Control de Electricidad (ARCONEL) · Effective 1 Oct 2026 · Ends 31 Dec 2026 · ARCONEL, Boletín 028 (30 Sep 2026): ARCONEL reforma tarifas para grupos de consumo AV1 y AV2

  • RegulationIn forceEcuador

    Decree 515: self-supply with surplus injection, Autonomous Energy Districts and fast-track for projects up to 100 MW

    Executive Decree 515 (29 September 2026) reforms the General Regulation of the LOSPEE. Consumers and industries may generate their own power and inject surplus into the grid under ARCONEL conditions; Autonomous Energy Districts (Distritos Autónomos Energéticos) can be created for industrial and productive zones, combining generation, storage and local networks (up to 40 years per press reports). Permits are simplified for non-conventional renewable and transition generation up to 100 MW, with preferential price mechanisms. Storage and ancillary services are added, CENACE plans operations on a five-year horizon, and high-voltage customers under the self-generation obligation keep an 18-month period to install it.

    100 MW (simplified permits for renewable and Decree text and Registro Oficial publication not read; content from the ministry bulletin (30 Sep 2026) and Teleamazonas summary. Status in force assumed from signature; confirm on next touch.

    Presidency of the Republic; Ministerio de Ambiente y Energía; ARCONEL · Ministerio de Ambiente y Energía, Boletín de Prensa 368 (30 Sep 2026), Decreto Ejecutivo 515

  • Power tariffProposedAustralia

    Cost recovery for network augmentations – Package 1 (ERC0448)

    Rule change requests from Minister Chris Bowen (ERC0448, ERC0456) to require data centres and other large loads to cover network costs they cause or accelerate when connecting to the NEM. Initiated 24 September 2026; submissions close 5 November 2026; draft determination due 1 April 2027.

    Australian Energy Market Commission (AEMC) · AEMC

  • Efficiency ruleProposedGermany

    Gesetz zur Beschleunigung der Umsetzung der Energieeffizienzrichtlinie (EnEfG-Novelle), Drucksache 21/8027

    Government bill, first reading in the Bundestag on 24 September 2026, referred to the Ausschuss für Wirtschaft und Energie (hearing 5 October 2026). It loosens minimum efficiency requirements for data centres, extends the deadline for new facilities from two to four years, moves the 100 percent renewable electricity requirement to 1 January 2030, and limits waste heat use to cases with a suitable nearby heat network.

    Bundesregierung / Deutscher Bundestag · Deutscher Bundestag

  • RegulationProposedAustria

    Draft EIA Act amendment 2026: mandatory EIA for new data centers of 100 MW or more (Z 19a)

    A ministry draft amending the UVP-G 2000 (138/ME, sent for consultation on 20 Sep 2026, comments due 1 Nov 2026) adds a data center category to Annex 1: new data centers with installed connection capacity of at least 100 MW need a full environmental impact assessment, and those of at least 50 MW in protected areas of category D need case-by-case screening. The explanatory notes say the UVP-G currently has no data center category.

    100 MW Installed connection capacity above which a new data center needs a full EIA (50 MW in category D areas)

    Federal Ministry for Agriculture, Forestry, Climate and Environmental Protection, Regions and Water Management (BMLUK) · Parlament Österreich, 138/ME XXVIII. GP, draft Anhang 1

  • Grid accessAnnouncedUzbekistan

    Instruction to secure 1 GW stable power supply for AI and data centre special zone in Karakalpakstan

    At a 19 September 2026 meeting in Nukus, it was stated that 6 projects totalling USD 8 billion will be implemented in the special zone created for AI and data centres in Karakalpakstan; officials were instructed to develop a five-year programme and provide investors with stable power supply of 1 gigawatt. Annual cloud and AI export target of USD 600 million was also set.

    1 GW Power supply to be ensured for investors in the AI/data centre special zone

    President of the Republic of Uzbekistan · Republic of Karakalpakstan · Government portal gov.uz

  • OtherAnnouncedUzbekistan

    Launch of AI data processing centre projects in Kungrad and Takhiatash ($2.281bn) and modular computing centre ($150m)

    During the President's visit to Karakalpakstan on 18 September 2026, the first stage of a USD 150 million modular intelligent computing centre in Takhiatash district was launched, projects with Chinese partners to create AI data processing centres (and digital currency production) in Kungrad and Takhiatash districts totalling USD 2.281 billion were presented, and a data processing centre is to be built in Takhtakupyr district.

    2,281 USD million Combined value of digital currency production and AI data centre projects in Kungrad and Takhiatash

    President of the Republic of Uzbekistan · Republic of Karakalpakstan · President of the Republic of Uzbekistan (president.uz)

Questions

Where is electricity cheapest for data centers?

Among the countries we track, the industrial electricity price is lowest in Paraguay (33.0 USD/MWh) and highest in Switzerland (240 USD/MWh), using each country’s latest official figure.

Which countries restrict new data centers?

Among tracked countries, restrictions or moratoriums are in force in Canada, China, Germany, Denmark, Ecuador, United Kingdom, Ireland, Iceland, Kyrgyzstan, Malaysia, Netherlands, Paraguay, Russia, Taiwan and Uzbekistan. Each country page lists the rule, the authority and the dates.

Which countries offer incentives for data centers?

Data center incentives are in force in Argentina, Australia, Brazil, Colombia, France, United Kingdom, Guatemala, Hong Kong, Indonesia, India, Iceland, Kyrgyzstan, Malaysia, Panama, Peru, Pakistan, Paraguay, United States, Uruguay and Venezuela among the countries we track.

Where does this data come from?

Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.

What counts as a restriction or moratorium?

A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.

How are power prices compared?

We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.

How often is it updated?

Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.

Global capacity

How much data center capacity is installed worldwide?

Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.

Open the Global Capacity Tracker

Choosing a market or a site?

Our analysts prepare country briefings on power, grid access, incentives and permits, with every source, in Excel.