In short

As of 7 October 2026, DC Market Insights tracks 5 data centers operated by Portus Data Centers in 1 country, of which 3 are operational.

5Facilities tracked
1Countries
—Operational (3 sites)
5.5 MWUnder construction (1 site)
12.8 MWPlanned (1 site)

MW = IT capacity where the source states it, otherwise total capacity. 2 of 5 facilities have a stated capacity; the others are counted as sites only.

HH2 · Portus Data Centers · Hamburg (approximate location)HH3 · Portus Data Centers · Hamburg (approximate location)HH4 · Portus Data Centers · Hamburg (approximate location)Munich 1 (MUC1) · Portus Data Centers · Kirchheim bei München (approximate location)Munich 2 (MUC2) · Portus Data Centers · Kirchheim bei München (approximate location)
Operational Under construction Planned Select a country on the map to open its page.

Market snapshot

Portus Data Centers data centers: key facts

  • The largest project in the pipeline is HH4 by Portus Data Centers (12.8 MW, planned).
  • 2 of 5 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Under construction5.5 MW
Planned12.8 MW

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Portus Data Centers development pipeline

Under construction and planned facilities with a stated capacity, largest first. 5.5 MW under construction and 12.8 MW planned in total.

ProjectLocationStatusTypeCapacity
HH4Portus Data Centers Hamburg, Germany Planned Colocation 12.8 MW
Munich 2 (MUC2)Portus Data Centers Kirchheim bei München, Germany Under construction Colocation 5.5 MW

Facilities

5 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
HH4Colocation Hamburg, Germany Planned 12.8 MW IT — Operator / official
Munich 2 (MUC2)Colocation
History
  1. Under construction
  2. Under construction
Kirchheim bei München, Germany Under construction 5.5 MW total — Trade press
HH2Colocation Hamburg, Germany Operational — 2009 Operator / official
HH3Colocation Hamburg, Germany Operational — 2019 Operator / official
Munich 1 (MUC1)Colocation Kirchheim bei München, Germany Operational — 2019 Trade press

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: the source’s address where given, otherwise the city centre (approximate).
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers does Portus Data Centers operate?

DC Market Insights tracks 5 Portus Data Centers data centers in 1 countries as of October 2026: 3 operational, 1 under construction and 1 planned.

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Need the full list, or a capacity view of one market?

Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.

Talk to an analyst