Proprietary data

Switch Datacenters Data Centers

Data centers operated by Switch Datacenters that we have verified: location, status and capacity, each checked against its source.

In short

As of 10 October 2026, DC Market Insights tracks 5 data centers operated by Switch Datacenters in 1 country, of which 3 are operational.

5Facilities tracked
1Countries
—Operational (3 sites)
—Under construction (0 sites)
—Planned (2 sites)

MW = IT capacity where the source states it, otherwise total capacity. 0 of 5 facilities have a stated capacity; the others are counted as sites only.

AMS3 · Switch Datacenters · Woerden (approximate location)AMS4 · Switch Datacenters · Amsterdam (approximate location)
Operational Under construction Planned Select a country on the map to open its page.

Market snapshot

Switch Datacenters data centers: key facts

  • 0 of 5 facilities have a capacity stated by their source; the totals above count only those.

Facilities

5 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
AMS2Colocation Netherlands Operational — — Trade press
AMS3Colocation Woerden, Netherlands Operational — 2017 Trade press
AMS4Colocation Amsterdam, Netherlands Operational — — Trade press
AMS5Colocation Netherlands Planned — — Trade press
Switch Datacenters Schiphol (Principal site)Colocation Netherlands Planned — — Trade press

Market position

How Switch Datacenters compares

Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.

  • In Netherlands, Switch Datacenters is one of 30 operators we track.
  • Netherlands has 99 tracked data centers from 30 operators: 79.1 MW operational and 10 MW under construction or planned.
  • Industrial electricity in Netherlands costs 148 USD/MWh (2025, latest official figure).

Data center operators in Netherlands

Tracked facilities9930 operators
Operational capacity79.1 MW10 MW in the pipeline
Switch Datacenters rank by capacity#10of 30 operators
Industrial power price148 USD/MWh2025
OperatorFacilitiesOperational MWPipeline MW
NorthC1447 MW—
NTT DATA120.7 MW—
Iron Mountain2—10 MW
maincubes15 MW—
QTS44.8 MW—
Penta Infra41.6 MW—
Digital Realty12——
Equinix12——

All data centers in Netherlands Power and policy in Netherlands

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: the source’s address where given, otherwise the city centre (approximate).
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers does Switch Datacenters operate?

DC Market Insights tracks 5 Switch Datacenters data center(s) in 1 country as of October 2026: 3 operational, 0 under construction and 2 planned.

Which other companies operate data centers in Netherlands?

Besides Switch Datacenters, the largest operators we track in Netherlands by capacity are NorthC, NTT DATA, Iron Mountain, maincubes and QTS. The Netherlands page lists all 30 operators.

What rules apply to data centers in Netherlands?

Our Power & Policy Tracker lists 12 government actions on data centers and power in Netherlands, including 4 restriction(s) and 0 incentive scheme(s) in force.

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Need the full list, or a capacity view of one market?

Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.

Talk to an analyst