Cologix Data Centers

Data centers operated by Cologix that we have verified: location, status and capacity, each checked against its source.

In short

As of 11 October 2026, DC Market Insights tracks 22 data centers operated by Cologix in 1 country, of which 19 are operational. Stated operational capacity is 40 MW, with a further 51 MW under construction and — planned. The pipeline is 1.3 times the capacity already operating.

22Facilities tracked
1Countries
40 MWOperational (19 sites)
51 MWUnder construction (1 site)
—Planned (2 sites)

MW = IT capacity where the source states it, otherwise total capacity. 2 of 22 facilities have a stated capacity; the others are counted as sites only.

Cologix ASH1 Ashburn · Cologix · Ashburn (approximate location)Cologix ASH2 Ashburn · Cologix · Ashburn (approximate location)Cologix NNJ2 Cedar Knolls · Cologix · Cedar Knolls (approximate location)Cologix NNJ3 Parsippany · Cologix · Parsippany (approximate location)Cologix NNJ4 Cedar Knolls · Cologix · Cedar Knolls (approximate location)Cologix DAL1 Dallas · Cologix · Dallas (approximate location)Cologix DAL2 Dallas · Cologix · Dallas (approximate location)Cologix DAL3 Dallas · Cologix · Dallas (approximate location)JAX1 · Cologix · Jacksonville (approximate location)JAX2 · Cologix · Jacksonville (approximate location)Cologix COL1 · Cologix · Columbus (approximate location)Cologix COL2 · Cologix · Columbus (approximate location)Cologix COL3 · Cologix · Columbus (approximate location)Cologix COL4 · Cologix · Columbus (approximate location)Cologix COL5 · Cologix · Columbus (approximate location)Cologix COL7 · Cologix · Johnstown (approximate location)Cologix COL8 · Cologix · Johnstown (approximate location)Cologix MIN1 · Cologix · Minneapolis (approximate location)Cologix MIN2 · Cologix · Minneapolis (approximate location)Cologix MIN3 · Cologix · Minneapolis (approximate location)Cologix MIN4 · Cologix · Minneapolis (approximate location)Cologix MIN5 · Cologix · Minneapolis (approximate location)
Operational Under construction Planned Select a country on the map to open its page.

Market snapshot

Cologix data centers: key facts

About Cologix

Cologix runs network-neutral interconnection and hyperscale edge data centers in North America. Its website stated in October 2026 that it operates 45+ data centers across 13 North American markets.

Headquarters
Denver, United States
Founded
2010
Tracked footprint
22 facilities in 1 country
Website
cologix.com

Company details checked against company and official sources, 10 Oct 2026.

  • Capacity under construction or planned (51 MW) is 1.3 times the operational base of 40 MW.
  • Its largest operational site is Cologix COL4 in Columbus, United States at 40 MW.
  • The largest project in the pipeline is Cologix ASH2 Ashburn (51 MW, under construction).
  • By type, the tracker lists 20 colocation and 2 hyperscale facilities.
  • 2 of 22 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational40 MW
Under construction51 MW

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Facilities by type
Colocation20
Hyperscale2

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Cologix development pipeline

Under construction and planned facilities with a stated capacity, largest first. 51 MW under construction and — planned in total.

ProjectLocationStatusTypeCapacity
Cologix ASH2 AshburnCologix Ashburn, United States Under construction Colocation 51 MW

Facilities

22 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
Cologix ASH2 AshburnColocation Ashburn, United States Under construction 51 MW total — Operator / official
Cologix COL4Colocation Columbus, United States Operational 40 MW total — Operator / official
Cologix ASH1 AshburnColocation Ashburn, United States Operational — — Operator / official
Cologix COL1Colocation Columbus, United States Operational — 2014 Operator / official
Cologix COL2Colocation Columbus, United States Operational — 2014 Operator / official
Cologix COL3Colocation Columbus, United States Operational — 2018 Operator / official
Cologix COL5Colocation Columbus, United States Operational — — Operator / official
Cologix COL7Hyperscale Johnstown, United States Planned — — Operator / official
Cologix COL8Hyperscale Johnstown, United States Planned — — Operator / official
Cologix DAL1 DallasColocation Dallas, United States Operational — — Operator / official
Cologix DAL2 DallasColocation Dallas, United States Operational — — Operator / official
Cologix DAL3 DallasColocation Dallas, United States Operational — — Operator / official
Cologix MIN1Colocation Minneapolis, United States Operational — — Operator / official
Cologix MIN2Colocation Minneapolis, United States Operational — — Operator / official
Cologix MIN3Colocation Minneapolis, United States Operational — — Operator / official
Cologix MIN4Colocation Minneapolis, United States Operational — — Operator / official
Cologix MIN5Colocation Minneapolis, United States Operational — — Operator / official
Cologix NNJ2 Cedar KnollsColocation Cedar Knolls, United States Operational — — Operator / official
Cologix NNJ3 ParsippanyColocation Parsippany, United States Operational — — Operator / official
Cologix NNJ4 Cedar KnollsColocation Cedar Knolls, United States Operational — — Operator / official
JAX1Colocation Jacksonville, United States Operational — — Operator / official
JAX2Colocation Jacksonville, United States Operational — — Operator / official

Market position

How Cologix compares

Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.

  • In United States, Cologix ranks #36 of 166 tracked operators by capacity, with 0.2% of the country’s tracked MW.
  • United States has 1,173 tracked data centers from 166 operators: 7,181 MW operational and 33,216 MW under construction or planned.
  • Industrial electricity in United States costs 86.2 USD/MWh (2025, latest official figure).
  • Columbus also hosts 1 other tracked data center(s), run by Google.

Data center operators in United States

Tracked facilities1,173166 operators
Operational capacity7,181 MW33,216 MW in the pipeline
Cologix rank by capacity#36of 166 operators · 0.2%
Industrial power price86.2 USD/MWh2025
OperatorFacilitiesOperational MWPipeline MW
PowerHouse Data Centers1760 MW8,807 MW
Meta291,000 MW7,000 MW
Tract15—4,800 MW
Microsoft48—2,000 MW
Vantage Data Centers22135 MW1,734 MW
Crusoe11,200 MW—
SB Energy1—1,200 MW
Centersquare311,125 MW—

All data centers in United States Power and policy in United States

Other data centers in Columbus

  • Google Columbus · Google · Operational

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: the source’s address where given, otherwise the city centre (approximate).
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers does Cologix operate?

DC Market Insights tracks 22 Cologix data center(s) in 1 country as of October 2026: 19 operational, 1 under construction and 2 planned.

Where is Cologix headquartered?

Cologix is headquartered in Denver, United States.

Which other companies operate data centers in United States?

Besides Cologix, the largest operators we track in United States by capacity are PowerHouse Data Centers, Meta, Tract, Microsoft and Vantage Data Centers. The United States page lists all 166 operators.

What rules apply to data centers in United States?

Our Power & Policy Tracker lists 13 government actions on data centers and power in United States, including 0 restriction(s) and 1 incentive scheme(s) in force.

Which other data centers are in Columbus?

Other tracked data centers in Columbus include Google Columbus (Google).

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Need the full list, or a capacity view of one market?

Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.

Talk to an analyst