Data Centers in United Kingdom

Every data center in United Kingdom that we have verified: operator, location, status and capacity, each checked against its source.

In short

As of 7 October 2026, DC Market Insights tracks 171 data centers in United Kingdom run by 44 operators: 129 operational, 7 under construction and 35 planned. Stated operational capacity is 744 MW, with a further 266 MW under construction and 4,889 MW planned. Vantage Data Centers holds the largest share of tracked operational capacity (20%).

171Facilities tracked
44Operators
744 MWOperational (129 sites)
266 MWUnder construction (7 sites)
4,889 MWPlanned (35 sites)

MW = IT capacity where the source states it, otherwise total capacity. 83 of 171 facilities have a stated capacity; the others are counted as sites only.

Equinix LD3 · Equinix · London (approximate location)Equinix LD4 · Equinix · Slough (approximate location)Equinix LD5 · Equinix · Slough (approximate location)Equinix LD6 · Equinix · Slough (approximate location)Equinix LD7 · Equinix · Slough (approximate location)Equinix LD8 · Equinix · London (approximate location)Equinix LD9 · Equinix · London (approximate location)Equinix LD10 · Equinix · Slough (approximate location)Equinix LD11x · Equinix · Slough (approximate location)Equinix LD13x · Equinix · Slough (approximate location)Equinix MA1 · Equinix · Manchester (approximate location)Equinix MA3 · Equinix · Manchester (approximate location)Equinix MA4 · Equinix · Manchester (approximate location)Equinix MA5 · Equinix · Manchester (approximate location)Digital Realty LGW14 · Digital Realty · Woking (approximate location)Digital Realty LGW15 · Digital Realty · Crawley (approximate location)Digital Realty LGW16 · Digital Realty · Crawley (approximate location)Digital Realty LHR13 · Digital Realty · Chessington (approximate location)Digital Realty LHR17 · Digital Realty · West Drayton (approximate location)Digital Realty LHR18 · Digital Realty · London (approximate location)Digital Realty LHR19 · Digital Realty · London (approximate location)Digital Realty LHR20 · Digital Realty · London (approximate location)Digital Realty LHR26 · Digital Realty · Slough (approximate location)Digital Realty LHR27 · Digital Realty · Slough (approximate location)Digital Realty LON1 · Digital Realty · London (approximate location)Digital Realty LON2 · Digital Realty · London (approximate location)Digital Realty LON3 · Digital Realty · London (approximate location)Global Switch London East · Global Switch · London (approximate location)Global Switch London North · Global Switch · London (approximate location)Global Switch London South · Global Switch · London (approximate location)Telehouse North · Telehouse · London (approximate location)Telehouse North Two · Telehouse · London (approximate location)Telehouse East · Telehouse · London (approximate location)Telehouse West · Telehouse · London (approximate location)Telehouse South · Telehouse · London (approximate location)NTT Hemel Hempstead 1 · NTT DATA · Hemel Hempstead (approximate location)NTT Hemel Hempstead 2 · NTT DATA · Hemel Hempstead (approximate location)NTT Hemel Hempstead 3 · NTT DATA · Hemel Hempstead (approximate location)NTT Hemel Hempstead 4 · NTT DATA · Hemel Hempstead (approximate location)NTT London 1 · NTT DATA · Dagenham (approximate location)Iron Mountain LON-1 · Iron Mountain · Slough (approximate location)Iron Mountain LON-2 · Iron Mountain · Slough (approximate location)Iron Mountain LON-3 · Iron Mountain · Slough (approximate location)CyrusOne LON1 · CyrusOne · Slough (approximate location)CyrusOne LON2 · CyrusOne · London (approximate location)CyrusOne LON3 · CyrusOne · Slough (approximate location)CyrusOne LON4 · CyrusOne · Slough (approximate location)CyrusOne LON5 · CyrusOne · Slough (approximate location)CyrusOne LON6 · CyrusOne · Iver Heath (approximate location)CyrusOne Southall · CyrusOne · Southall (approximate location)Centersquare Reading LHR3 · Centersquare · Reading (approximate location)LONDON3 (Slough) · Virtus Data Centres · Slough (approximate location)LONDON4 (Slough) · Virtus Data Centres · Slough (approximate location)LONDON9 (Slough) · Virtus Data Centres · Slough (approximate location)LONDON10 (Slough) · Virtus Data Centres · Slough (approximate location)LONDON11 (Slough) · Virtus Data Centres · Slough (approximate location)LONDON19 (Slough) · Virtus Data Centres · Slough (approximate location)KLON-01 (Harlow) · Kao Data · Harlow (approximate location)KLON-02 (Harlow) · Kao Data · Harlow (approximate location)KLON-03 (Harlow) · Kao Data · Harlow (approximate location)KLON-04 (Harlow) · Kao Data · Harlow (approximate location)KLON-05 (Northolt) · Kao Data · Northolt (approximate location)KLON-06 (Slough) · Kao Data · Slough (approximate location)KMAN-01 (Manchester) · Kao Data · Stockport (approximate location)Spring Park · Ark Data Centres · Corsham (approximate location)Spring Park extension (Westwell Road) · Ark Data Centres · Corsham (approximate location)Longcross Park · Ark Data Centres · Chertsey (approximate location)Longcross Park LP02 · Ark Data Centres · Chertsey (approximate location)Hilfield Park (former Mercure Hotel, Elstree) · Ark Data Centres · Elstree (approximate location)Yondr Slough Building 1 · Yondr · Slough (approximate location)Yondr Slough Building 2 · Yondr · Slough (approximate location)Yondr Slough Building 3 · Yondr · Slough (approximate location)Docklands Campus · Ada Infrastructure · London (approximate location)Cardiff (Rover Way) · Latos Data Centres · Cardiff (approximate location)Stockton neural Edge · Latos Data Centres · Stockton-on-Tees (approximate location)LON1 · Serverfarm · Feltham (approximate location)Edinburgh South Gyle SC-1 · Pulsant · Edinburgh (approximate location)Edinburgh SC-2 · Pulsant · Edinburgh (approximate location)Edinburgh SC-3 · Pulsant · Edinburgh (approximate location)Manchester NW-1 · Pulsant · Manchester (approximate location)Rotherham YH-1 · Pulsant · Rotherham (approximate location)Newcastle NE-1 · Pulsant · Newcastle upon Tyne (approximate location)Newcastle NE-2 · Pulsant · North Shields (approximate location)Birmingham WM-1 · Pulsant · Birmingham (approximate location)Milton Keynes SE-1 · Pulsant · Milton Keynes (approximate location)Maidenhead SE-2 · Pulsant · Maidenhead (approximate location)Reading SE-3 · Pulsant · Reading (approximate location)Reading SE-4 · Pulsant · Reading (approximate location)Croydon LN-1 · Pulsant · Croydon (approximate location)Fareham SE-5 · Pulsant · Fareham (approximate location)nLighten Birmingham (BHX1) · nLighten · Birmingham (approximate location)nLighten Bristol (BRS1) · nLighten · Bristol (approximate location)nLighten Chester (MAN1) · nLighten · Chester (approximate location)nLighten Leeds (LBA1) · nLighten · Leeds (approximate location)nLighten Liverpool (LPL1) · nLighten · Liverpool (approximate location)nLighten London (STN1) · nLighten · Hoddesdon (approximate location)nLighten Milton Keynes (LTN1) · nLighten · Milton Keynes (approximate location)nLighten Nottingham (EMA1) · nLighten · Nottingham (approximate location)nLighten Rugby (BHX2) · nLighten · Rugby (approximate location)nLighten Swindon (BRS2) · nLighten · Swindon (approximate location)Datum MCR1 · Datum Datacentres · Manchester (approximate location)Datum MCR2 · Datum Datacentres · Manchester (approximate location)Stellanor London City · Stellanor · London (approximate location)Stellanor London East · Stellanor · London (approximate location)Stellanor London North · Stellanor · London (approximate location)Stellanor London West · Stellanor · Hounslow (approximate location)Stellanor Byfleet · Stellanor · West Byfleet (approximate location)Stellanor Cambridge · Stellanor · Cambridge (approximate location)Stellanor Gatwick · Stellanor · Crawley (approximate location)Stellanor Hemel Hempstead · Stellanor · Hemel Hempstead (approximate location)Stellanor Reading · Stellanor · Reading (approximate location)Stellanor West Yorkshire · Stellanor · Elland (approximate location)Stellanor Woking · Stellanor · Woking (approximate location)iomart DC1 Glasgow · iomart · Glasgow (approximate location)iomart DC2 Central London · iomart · London (approximate location)iomart DC12 North London · iomart · London (approximate location)iomart DC5 Maidenhead · iomart · Maidenhead (approximate location)iomart DC6 and DC7 Manchester City · iomart · Manchester (approximate location)iomart DC13 Manchester Trafford Wharf · iomart · Manchester (approximate location)iomart DC3 Nottingham · iomart · Nottingham (approximate location)iomart DC4 Leicester · iomart · Leicester (approximate location)iomart DC9 Gosport · iomart · Gosport (approximate location)iomart DC11 York · iomart · York (approximate location)iomart DC8 St Asaph · iomart · Saint Asaph (approximate location)DataVita DV1 Lanarkshire · DataVita · Chapelhall (approximate location)DataVita DV2 Glasgow · DataVita · Glasgow (approximate location)Custodian DA2 Dartford · Custodian Data Centres · Dartford (approximate location)Custodian ME14 Maidstone · Custodian Data Centres · Maidstone (approximate location)Volta London (Great Sutton Street) · Volta Data Centres · London (approximate location)Node4 Derby · Node4 · Derby (approximate location)Node4 Leeds · Node4 · Leeds (approximate location)Node4 Northampton (DC4) · Node4 · Northampton (approximate location)Six Degrees Birmingham Central · Six Degrees · Birmingham (approximate location)Six Degrees Studley · Six Degrees · Studley (approximate location)Pure DC London Brent Cross (LON01) Building 1 · Pure DC · London (approximate location)Pure DC London Brent Cross (LON01) Building 2 · Pure DC · London (approximate location)Pure DC London Park Royal (LON02) · Pure DC / SEGRO JV · London (approximate location)Prescient Data Centres Coleraine · Prescient Data Centres · Coleraine (approximate location)Google Waltham Cross · Google · Waltham Cross (approximate location)Microsoft Skelton Grange · Microsoft · Leeds (approximate location)Stargate UK – Cobalt Park · Nscale / OpenAI (Stargate UK) · Wallsend (approximate location)Abbots Langley (Bedmond Road) · Greystoke Land · Abbots Langley (approximate location)Corscale Iver (Court Lane) · Corscale · Iver (approximate location)AWS Iver (Ridgeway) · Amazon Web Services · Iver (approximate location)AWS Swindon (Burderop) · Amazon Web Services · Swindon (approximate location)Teesworks Data Centre · Teesworks Ltd · Middlesbrough (approximate location)Gravity Edge Camberley · Gravity Edge · Camberley (approximate location)Apatura Larbert (Glenbervie) · Apatura · Larbert (approximate location)Ravenscraig AI Data Centre · Apatura · Motherwell (approximate location)
Operational Under construction Planned

Market snapshot

United Kingdom data center market: key facts

  • Capacity under construction or planned (5,155 MW) is 6.9 times the operational base of 744 MW.
  • The three largest operators by operational capacity, Vantage Data Centers, Virtus Data Centres and NTT DATA, hold 44% of tracked operational MW.
  • Elsham Tech Park Ltd (Greystoke) has the largest development pipeline in United Kingdom: 1,000 MW under construction or planned.
  • The largest operational facility we track is Cardiff Campus (Newport) (Vantage Data Centers, Newport) at 148 MW.
  • The largest project in the pipeline is Elsham Tech Park (1,000 MW, planned).
  • London is the largest cluster: 79 of 171 facilities and 29% of tracked capacity.
  • By type, the tracker lists 112 colocation, 34 hyperscale and 25 edge facilities.
  • 3 facilities publish a PUE figure; the lowest is 1.15 at DataVita DV1 Lanarkshire (DataVita) and the median is 1.20.
  • 83 of 171 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational744 MW
Under construction266 MW
Planned4,889 MW

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Largest operators in United Kingdom by tracked capacity, MW
Apatura850 MW
QTS720 MW
ILI Group600 MW
Equinix250 MW
CyrusOne176 MW
Google163 MW

OperationalUnder construction or planned

Capacity by market in United Kingdom, MW
London1,713 MW
Scotland1,498 MW
Humber1,386 MW
North East England721 MW
Slough285 MW
South Wales148 MW
Manchester34 MW
M4 Corridor27 MW
Swindon19.3 MW
North West England15.6 MW

OperationalUnder construction or planned

Facilities by type
Colocation112
Hyperscale34
Edge25

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Market context

What shapes the United Kingdom data center market

Policy, power, land and demand, each statement checked against its source. Reviewed 7 October 2026. Government sources are linked; the full source list comes with the Excel data.

A March 2026 parliamentary POSTnote states that the UK has around 450 large data centres (a techUK estimate) using about 2% of UK electricity (2.4 GW of capacity, a NESO estimate from July 2025), and that DSIT estimates of 2024 colocation capacity found London had more capacity than the other regions combined. UK Parliament, Parliamentary Office of Science and Technology (POSTnote 762)

Policy and incentives

On 12 September 2024 the UK government announced that data centres would be designated as Critical National Infrastructure, the first new designation since the Space and Defence sectors gained the status in 2015. Department for Science, Innovation and Technology (GOV.UK)

The Delivering AI Growth Zones policy paper of 13 November 2025 set out electricity discounts of up to £24/MWh in Scotland, £16/MWh in Cumbria and £14/MWh in the North East for data centres in AI Growth Zones, planned from April 2027 subject to legislative timetables. Department for Science, Innovation and Technology (GOV.UK)

Data centres have had a Climate Change Agreements umbrella agreement since 24 July 2014. It was amended in January 2022 to add a fifth target period, and in May 2022 to let facilities be added until 30 June 2022. GOV.UK (BEIS, now DESNZ)

Power and grid

Ofgem approved connections reform modification CMP434 (WACM2) on 15 April 2025, which introduced a 'first ready and needed, first connected' gated process for most new transmission connection applications; it was implemented on 10 June 2025. Ofgem

NESO stated that before connections reform the Great Britain connections queue had grown to over 700GW, with shovel-ready projects waiting up to 10 years for a connection. National Energy System Operator (NESO)

A DESNZ consultation published on 11 March 2026 stated that the queue for data centre connections was over 50GW at transmission alone, and that the transmission demand queue stood at 96GW at the end of June 2025. Department for Energy Security and Net Zero (GOV.UK)

On 29 July 2026 Ofgem opened a consultation, which closed in September 2026, proposing a data centre commitment fee and queue management milestones to reduce the number of non-viable projects in the connections queue. Ofgem

The Clean Power 2030 Action Plan defines its 2030 target as Great Britain generating enough clean power to meet total annual electricity demand, with clean sources producing at least 95% of Great Britain's generation in a typical weather year. Department for Energy Security and Net Zero (GOV.UK)

Land, zoning and sites

England's National Planning Policy Framework (paragraph 86(c)) says planning policies should identify suitable locations for uses such as laboratories, gigafactories, data centres, digital infrastructure, and freight and logistics. GOV.UK (MHCLG) – National Planning Policy Framework, chapter 6

SI 2026/13, made 7 January 2026 and in force 8 January 2026, adds data centres to the business or commercial projects that can be directed into the Nationally Significant Infrastructure Project consenting regime under the Planning Act 2008. legislation.gov.uk – Infrastructure Planning (Business or Commercial Projects) (Amendment) Regulations 2026

On 10 February 2025 the government said the first AI Growth Zone would be at Culham, Oxfordshire, and invited proposals for sites with large existing power connections of 500+ MW or a clear plan to increase energy capacity. GOV.UK (DSIT press release)

The government's AI Growth Zones collection lists zones announced for Oxfordshire (30 April 2025), the North East (16 September 2025), North Wales (13 November 2025), South Wales (20 November 2025) and Scotland (29 January 2026). GOV.UK (DSIT) – AI Growth Zones collection

The North Wales AI Growth Zone, confirmed on 13 November 2025, has a base at Prosperity Parc on Anglesey and another at Trawsfynydd in Gwynedd. GOV.UK (DSIT press release)

Demand and connectivity

A March 2026 parliamentary POSTnote says the UK has around 450 large data centres using about 2% of UK electricity (2.4 GW of capacity, NESO estimate, July 2025), and that London had more capacity than the other regions combined. UK Parliament POST – POSTnote 762: What are data centres and how sustainable are they?

Ofcom reported that, as of January 2026, full fibre was available to 82% of UK homes (24.9 million) and gigabit-capable broadband to 89% (27.1 million). Ofcom – Connected Nations update: Spring 2026

A September 2025 report by Parliament's Joint Committee on the National Security Strategy says around 64 subsea cables land in the UK, including 45 international systems, which carry 99% of UK international data traffic. UK Parliament JCNSS – Subsea telecommunications cables: resilience and crisis preparedness

Sustainability, water and climate

The Climate Change Act 2008, as amended in June 2019, requires the net UK carbon account for 2050 to be at least 100% lower than the 1990 baseline. legislation.gov.uk – Climate Change Act 2008, section 1

DESNZ's Digest of UK Energy Statistics 2026 reports that renewable sources supplied 52.1% of UK electricity generation in 2025. DESNZ – Digest of UK Energy Statistics (DUKES) 2026

POSTnote 762 (March 2026), citing a 2025 techUK operator survey, says around half of the data centres in England use water for cooling, and that planning authorities may ask for water impact assessments. UK Parliament POST – POSTnote 762

The Commons Environmental Audit Committee ran an inquiry into risks and opportunities to the sustainability of UK data centres, covering energy and water use and net zero; it closed to evidence on 6 April 2026 and held oral evidence sessions on 10 June and 1 July 2026. UK Parliament – Environmental Audit Committee inquiry

Operators in United Kingdom

All operators
OperatorFacilitiesOperational MWPipeline MWShare of operational MW
Equinix15—250 MW—
Pulsant1422.1 MW—3%
Digital Realty13———
Virtus Data Centres1196.9 MW145 MW13%
Stellanor11———
iomart11———
nLighten1079.3 MW—11%
CyrusOne768 MW108 MW9.1%
Ark Data Centres754 MW36 MW7.3%
Kao Data741.6 MW86.6 MW5.6%
NTT DATA584.3 MW—11%
Telehouse518 MW—2.4%
Colt DCS4—57 MW—
Datum Datacentres4———
Iron Mountain335.8 MW25 MW4.8%
Yondr3—40 MW—
Node43———
Global Switch3—40 MW—
DataVita241 MW—5.5%
Pure DC220 MW70 MW2.7%
Microsoft2———
Custodian Data Centres2———
Amazon Web Services2—27 MW—
Latos Data Centres2———
Six Degrees2———
Apatura2—850 MW—
Google2—163 MW—
Vantage Data Centers1148 MW—20%
Gravity Edge120 MW—2.7%
Centersquare115 MW—2%
Serverfarm1———
Humber Tech Park1—386 MW—
Pure DC / SEGRO JV1—56 MW—
Elsham Tech Park Ltd (Greystoke)1—1,000 MW—
Nscale1—50 MW—
Volta Data Centres1———
Teesworks Ltd1———
Corscale1—140 MW—
ILI Group1—600 MW—
QTS1—720 MW—

Largest data center projects in United Kingdom

Under construction and planned facilities with a stated capacity, largest first. 266 MW under construction and 4,889 MW planned in total.

ProjectLocationStatusTypeCapacity
Elsham Tech ParkElsham Tech Park Ltd (Greystoke) Elsham Planned Hyperscale 1,000 MW
QTS CamboisQTS Blyth Planned Hyperscale 720 MW
Cato (Auchtertool)ILI Group Auchtertool Planned Hyperscale 600 MW
Ravenscraig AI Data CentreApatura Motherwell Planned Hyperscale 550 MW
Humber Tech ParkHumber Tech Park South Killingholme Planned Hyperscale 386 MW
Apatura Larbert (Glenbervie)Apatura Larbert Planned Hyperscale 300 MW
Equinix Hertfordshire CampusEquinix South Mimms Planned Hyperscale 250 MW
Docklands CampusAda Infrastructure London Planned Hyperscale 210 MW
Google North Weald AirfieldGoogle North Weald Bassett Planned Hyperscale 163 MW
Corscale Iver (Court Lane)Corscale Iver Planned Colocation 140 MW
CyrusOne LON6CyrusOne Iver Heath Planned Hyperscale 108 MW
Abbots Langley (Bedmond Road)Greystoke Land Abbots Langley Planned Hyperscale 96 MW

How United Kingdom compares in Europe

Countries in the same region, by tracked capacity. Coverage grows as each country is researched.

CountryFacilitiesOperatorsOperational MWPipeline MW
United Kingdom17144744 MW5,155 MW
Germany17050819 MW3,782 MW
Russia10017371 MW211 MW

Data center deals in United Kingdom

Our Deal Tracker lists 17 deals in United Kingdom since January 2026, with $25.14B in disclosed value.

  • Third Point (lead), Nvidia, Apollo, Citadel and others → Nscale (AI cloud platform and data center operator) Financing $3.36B
  • Consortium of 13 banks incl. Standard Chartered, BNP Paribas, Crédit Agricole CIB, Société Générale → VIRTUS Data Centres UK and European portfolio (incl. 78MW Saunderton campus, LONDON19 Slough) Financing $3.24B
  • Unnamed neocloud operator → 14MW of AI-ready capacity at Green Mountain LON-East campus, Romford Land / campus · 14 MW
  • ING, ABN AMRO, Santander, Scottish National Investment Bank, Siemens Financial Services (lenders); National Wealth Fund (GBP 202m guarantee) → DataVita DV1 expansion and new DV3, North Lanarkshire AI Growth Zone Financing $405.8M
  • Nebius → AI capacity at Vantage CWL1 campus, Newport (South Wales AI Growth Zone) Land / campus
  • Partners Group → AVK Power Solutions (UK data center power/microgrid provider) M&A $1.00B

All United Kingdom deals in the Deal Tracker

Facilities

171 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
Elsham Tech ParkElsham Tech Park Ltd (Greystoke) Elsham Planned 1,000 MW total — Trade press
QTS CamboisQTS Blyth Planned 720 MW total — Trade press
Cato (Auchtertool)ILI Group Auchtertool Planned 600 MW total — Trade press
Ravenscraig AI Data CentreApatura Motherwell Planned 550 MW total — Trade press
Humber Tech ParkHumber Tech Park South Killingholme Planned 386 MW IT — Trade press
Apatura Larbert (Glenbervie)Apatura Larbert Planned 300 MW total — Trade press
Equinix Hertfordshire CampusEquinix South Mimms Planned 250 MW total — Operator / official
Docklands CampusAda Infrastructure London Planned 210 MW IT — Operator / official
Google North Weald AirfieldGoogle
History
  1. Planned
  2. Planned
North Weald Bassett Planned 163 MW total — Trade press
Cardiff Campus (Newport)Vantage Data Centers
2 deals
  • ABS investors → Vantage Data Centers Cardiff campus (CWL11, CWL13) – EMEA ABS
  • Nebius → AI capacity at Vantage CWL1 campus, Newport (South Wales AI Growth Zone)
  • All deals in the Deal Tracker
Newport Operational 148 MW IT — Operator / official
Corscale Iver (Court Lane)Corscale Iver Planned 140 MW total — Trade press
CyrusOne LON6CyrusOne Iver Heath Planned 108 MW IT — Operator / official
Abbots Langley (Bedmond Road)Greystoke Land Abbots Langley Planned 96 MW total — Trade press
Saunderton CampusVirtus Data Centres
1 deal
  • Consortium of 13 banks incl. Standard Chartered, BNP Paribas, Crédit Agricole CIB, Société Générale → VIRTUS Data Centres UK and European portfolio (incl. 78MW Saunderton campus, LONDON19 Slough) US$3,239m
  • All deals in the Deal Tracker
Saunderton Planned 75 MW IT — Operator / official
Pure DC London Brent Cross (LON01) Building 2Pure DC London Under construction 70 MW total — Operator / official
London 4 (Hayes)Colt DCS Hayes Under construction 57 MW IT — Operator / official
Pure DC London Park Royal (LON02)Pure DC / SEGRO JV London Planned 56 MW IT — Operator / official
Longcross ParkArk Data Centres Chertsey Operational 54 MW IT — Trade press
Nscale LoughtonNscale Loughton Under construction 50 MW total — Operator / official
DataVita DV1 LanarkshireDataVita
1 deal
  • ING, ABN AMRO, Santander, Scottish National Investment Bank, Siemens Financial Services (lenders); National Wealth Fund (GBP 202m guarantee) → DataVita DV1 expansion and new DV3, North Lanarkshire AI Growth Zone US$406m
  • All deals in the Deal Tracker
Chapelhall Operational 40 MW total 2016 Operator / official
Global Switch London SouthGlobal Switch London Planned 40 MW IT — Operator / official
Yondr Slough Building 3Yondr
1 deal
Slough Under construction 40 MW IT — Trade press
KLON-04 (Harlow)Kao Data Harlow Planned 36 MW IT — Operator / official
Longcross Park LP02Ark Data Centres Chertsey Planned 36 MW IT — Trade press
KMAN-01 (Manchester)Kao Data Stockport Planned 33 MW IT — Operator / official
LONDON19 (Slough)Virtus Data Centres
1 deal
  • Consortium of 13 banks incl. Standard Chartered, BNP Paribas, Crédit Agricole CIB, Société Générale → VIRTUS Data Centres UK and European portfolio (incl. 78MW Saunderton campus, LONDON19 Slough) US$3,239m
  • All deals in the Deal Tracker
Slough Planned 32.5 MW IT — Operator / official
NTT London 1NTT DATA Dagenham Operational 32 MW IT — Operator / official
AWS Swindon (Burderop)Amazon Web Services Swindon Planned 27 MW total — Trade press
Iron Mountain LON-2Iron Mountain Slough Operational 27 MW total — Operator / official
LONDON4 (Slough)Virtus Data Centres Slough Operational 26.6 MW IT — Operator / official
Iron Mountain LON-3Iron Mountain Slough Under construction 25 MW total — Operator / official
LONDON5 (Stockley Park)Virtus Data Centres Hayes Operational 24 MW IT — Operator / official
LONDON9 (Slough)Virtus Data Centres Slough Under construction 24 MW IT — Operator / official
NTT Hemel Hempstead 4NTT DATA Hemel Hempstead Operational 24 MW IT — Operator / official
Gravity Edge CamberleyGravity Edge Camberley Operational 20 MW total — Trade press
KLON-06 (Slough)Kao Data Slough Operational 20 MW IT — Operator / official
NTT Hemel Hempstead 3NTT DATA Hemel Hempstead Operational 20 MW IT — Operator / official
Pure DC London Brent Cross (LON01) Building 1Pure DC London Operational 20 MW total — Operator / official
nLighten Swindon (BRS2)nLighten Swindon Operational 19.3 MW total — Operator / official
CyrusOne LON4CyrusOne Slough Operational 18 MW IT — Operator / official
CyrusOne LON5CyrusOne Slough Operational 18 MW IT — Operator / official
Telehouse SouthTelehouse London Operational 18 MW total 2022 Operator / official
KLON-03 (Harlow)Kao Data Harlow Planned 17.6 MW IT — Operator / official
LONDON6 (Stockley Park)Virtus Data Centres Hayes Operational 16 MW IT — Operator / official
Centersquare Reading LHR3Centersquare Reading Operational 15 MW total — Operator / official
CyrusOne LON2CyrusOne London Operational 14 MW IT — Operator / official
LONDON11 (Slough)Virtus Data Centres Slough Planned 13.3 MW IT — Operator / official
LONDON2 (Hayes)Virtus Data Centres Hayes Operational 12.3 MW IT — Operator / official
nLighten Bristol (BRS1)nLighten Bristol Operational 10.8 MW total — Operator / official
nLighten Birmingham (BHX1)nLighten Birmingham Operational 9.6 MW total — Operator / official

Get the data

Every data center in United Kingdom, in Excel

Every facility with operator, city, status, capacity, year and source, plus summaries and the status history. Built from the live tracker the moment you download.

Data Centers in United Kingdom: Capacity Sheet

171 facilities

Every tracked data center in United Kingdom with operator, city, status, MW, year and source, plus summaries by city and operator and the status history. Excel, updated weekly.

$199 USD

Buy now

Excel · instant download · secure checkout by PayPal

All countries

Global Data Center Database: annual licence

1,199 facilities

Every facility in the tracker worldwide, in Excel, with sources and status history. A fresh file every month for a year.

$1,499 USD / year

Subscribe

Full database now, a fresh file every month. Renews yearly; cancel anytime in PayPal.

Custom cut

One operator, one city, a capacity pipeline or a site-selection shortlist, prepared by our analysts.

Talk to an analyst

Free weekly alert: data centers in United Kingdom

Every Monday: facilities added, status changes and new deals, each checked against its source. Nothing when nothing changed. Unsubscribe in one click.

Secure checkout

Data pack

Loading secure checkout…

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: the source’s address where given, otherwise the city centre (approximate).
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers are there in United Kingdom?

DC Market Insights tracks 171 data centers in United Kingdom as of October 2026: 129 operational, 7 under construction and 35 planned, run by 44 operators. The count grows as we verify more sites.

What is the data center capacity of United Kingdom?

Tracked operational capacity in United Kingdom is 744 MW, with 266 MW under construction and 4,889 MW planned. These totals use the capacity each source states (IT load where given) and cover 83 of 171 tracked facilities.

Which companies operate the most data center capacity in United Kingdom?

By tracked operational capacity, the largest operators in United Kingdom are Vantage Data Centers (148 MW), Virtus Data Centres (96.9 MW) and NTT DATA (84.3 MW).

Where are the data centers in United Kingdom located?

The largest clusters by tracked capacity are London (79 facilities), Scotland (9 facilities) and Humber (2 facilities). The map above shows every site.

Which new data centers are being built in United Kingdom?

We track 266 MW under construction and 4,889 MW planned. The largest projects are Elsham Tech Park (1,000 MW), QTS Cambois (720 MW) and Cato (Auchtertool) by ILI Group (600 MW).

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.