| 8 Oct |
Sesterce → Sesterce Campus, former Kaipola paper mill, JämsäAI campus plan on former paper mill site |
Land / campus |
FinlandJämsä |
$11.19BConverted from EUR |
200 |
Announced |
Company / official |
| 6 Oct |
Applied Digital → Up to 1GW potential power capacity site in Finland (first non-US development)Site/power capacity agreement |
Land / campus |
Finland |
Not disclosed |
1,000 |
Announced |
Company / official |
| 5 Oct |
atNorth → FIN05, 28.6ha site, Salo (75MW phase 1; up to 230MW)Campus announcement |
Land / campus |
FinlandSalo |
$2.24BConverted from EUR |
75 |
Announced |
Company / official |
| 9 Sep |
Google → Loviisa nuclear power plant life extension (supply for Google's Finnish data centers)Nuclear PPA (life extension, 22 years) |
Power deal |
FinlandLoviisa |
Not disclosed |
— |
Announced |
Company / official |
| 9 Sep |
Google → Data center and clean energy investment in Finland (Hamina, Kajaani, Muhos, Vaala)Campus investment plan |
Land / campus |
FinlandHamina / Kajaani / Muhos / Vaala |
$15.15BConverted from EUR |
— |
Announced |
Company / official |
| 2 Sep |
CPP Investments (c.51%) and Equinix (c.34%), with Partners Group reinvesting (c.10%) → atNorth (Nordic data center developer and operator)Acquisition (controlling stake) – completion |
M&A |
Nordics (Iceland, Norway, Sweden, Finland, Denmark) |
$4.00B |
— |
Closed |
Company / official |
| 1 Sep |
Cerebras Systems → 165MW AI data centre in Mikkeli (phased 50MW, 80MW, 165MW)Campus announcement with seven-year capacity agreement |
Land / campus |
FinlandMikkeli |
Not disclosed |
165 |
Announced |
Company / official |
| 13 Aug |
Nebius → Second Nebius data center in MäntsäläCampus announcement |
Land / campus |
FinlandMäntsälä |
Not disclosed |
70 |
Announced |
Trade press |
| 22 Jul |
SMBC, ABN AMRO, Citi, Societe Generale, Natixis CIB → Pure DC Seinäjoki AI campus (SJK01) Phase 1Debt facility |
Financing |
FinlandSeinäjoki |
$1.48BConverted from EUR |
110 |
Closed |
Company / official |