Powered land in Georgia: 341 power nodes, 8 sites and 28 demand rows, each with its source and check date.
29Provisional DCMI Power Readiness Score, out of 100 (DC Market Insights calculation, 55 of 100 weight points with data; final at 90). Missing: time to power, grid congestion and queue backlog, water stress.
First calculated on 4 November 2026.
Verified on 2 November 2026 · Method
Substations are not drawn: we count them by county only.
Project Camellia (OpenAI, Savannah Gateway Industrial Hub) in Effingham County is the largest of the 8 Georgia sites we track, at 3,210 MW; together they state 7,910 MW across 8 counties (DC Market Insights calculation). Georgia-Pacific Cedar Springs at 101 MW leads the 139 MW of plant capacity leaving service. OpenAI names the most stated demand here (3,200 MW of 7,766 MW).
| Data on file | Rows | MW |
|---|---|---|
| Power plants (EIA-860M) | 296 | 52,550 MW |
| Substations 230 kV or more (HIFLD, counted by county) | 45 | |
| ISO queue (no ISO for this grid) | Not loaded yet | |
| Large-load requests (utility filings) | Not loaded yet | |
| Data center sites | 8 | 7,910 MW |
| Demand rows | 28 | 7,766 MW |
| Policy rows | 2 |
Leaving service in Georgia: 139 MW at 4 plants, led by Georgia-Pacific Cedar Springs in Early County (101 MW, retired in July 2025), Multitrade Rabun Gap, LLC in RABUN County (22 MW, retired in April 2025) and Interstate Paper LLC Riceboro in Liberty County (15 MW, retired in September 2025).
Coming: 6,872 MW at 21 planned plants, led by Pepper Hammock Solar and Storage (2,500 MW, planned, in service September 2029), Yates (1,448 MW, planned, in service February 2027) and Smarr Combined Cycle Energy Facility (804 MW, planned, in service June 2029).
Of 45 substations, 19 at 500 kV or more and 26 at 230 kV; Effingham County (7), Fulton County (5) and Chatham County (3) hold the most.
| Power node | Kind | County | MW | Date | Source |
|---|---|---|---|---|---|
| Pepper Hammock Solar and Storage | Planned plant | Wayne County | 2,500 MW | planned, in service September 2029 | EIA Form 860M, September 2026 |
| Yates | Planned plant | Coweta County | 1,448 MW | planned, in service February 2027 | EIA Form 860M, September 2026 |
| Smarr Combined Cycle Energy Facility | Planned plant | Monroe County | 804 MW | planned, in service June 2029 | EIA Form 860M, September 2026 |
| Talbot County Energy | Planned plant | Talbot County | 262 MW | planned, in service January 2029 | EIA Form 860M, September 2026 |
| Peach Wood Solar | Planned plant | Mitchell County | 261 MW | planned, in service December 2030 | EIA Form 860M, September 2026 |
| Rock House Solar | Planned plant | McDuffie County | 250 MW | planned, in service November 2027 | EIA Form 860M, September 2026 |
| Conez Solar, LLC | Planned plant | Emanuel County | 150 MW | planned, in service June 2027 | EIA Form 860M, September 2026 |
| Laurens Solar | Planned plant | Laurens County | 150 MW | planned, in service June 2028 | EIA Form 860M, September 2026 |
| Crossroads Solar – GA | Planned plant | Liberty County | 150 MW | planned, in service July 2029 | EIA Form 860M, September 2026 |
| SR Bacon II | Planned plant | Bacon County | 115 MW | planned, in service December 2027 | EIA Form 860M, September 2026 |
1 of the 8 Georgia sites state no MW and no power date yet, so they have no page of their own.
| Site | County | Acres | MW (source words) | Time to power (source words) | Status | Source |
|---|---|---|---|---|---|---|
| Project Camellia (OpenAI, Savannah Gateway Industrial Hub) | Effingham County | 3,210 MW | idea | State, 29 July 2026 | ||
| White Oak Technology Park (Project JGK, Columbia County Data Center) | Columbia County | 2,862 | 1,400 MW | idea | State, 16 June 2026 | |
| Project Arrowhead | Irwin County | 1,066 | 1,250 MW | idea | State, 10 April 2026 | |
| Pine Ridge Technology Park | Twiggs County | 291.5 | 900 MW (County site plan: 9 buildings, 100 MW each. Total 900 MW is a DC Market Insights calculation) | zoned | County, 18 September 2025 | |
| Nixon Technology Center | Richmond County | 388 | 600 MW | idea | State, 19 October 2026 | |
| Project Azalea | McDuffie County | 200 | 400 MW | idea | County, 13 February 2026 | |
| Kingston Technology Hub | Bartow County | 559 | 150 MW | idea | State, 4 September 2026 | |
| Project Sail | Coweta County | idea | State, 31 December 2024 |
22 buyers, 28 rows; evidence: 18 from company, 9 from press and 1 from state filing.
Our Power and Policy tracker holds 2 rules for Georgia.
Georgia: 29 out of 100, provisional, from 55 weight points.
| Factor | Points | Basis |
|---|---|---|
| Time to power | Not loaded yet | no stated power date |
| Available or freeing MW | 0.6 of 20 | 139 MW freeing (full points at 5,000 MW, DC Market Insights calculation) |
| Grid congestion and queue backlog | Not loaded yet | no ISO queue covers this grid; utility queues not loaded yet |
| Policy | 6 of 15 | in force: 1 plan, 1 tariff |
| Land and permitting | 7 of 10 | best site by status and acres; opposition events not tracked yet |
| Fiber and latency to the nearest hub | 2.4 of 10 | 24 live data centers tracked in the state (full points at 100) |
| Water stress | Not loaded yet | water stress index not loaded yet |
Effingham County (Project Camellia (OpenAI, Savannah Gateway Industrial Hub)), Coweta County and Richmond County and 5 more counties.
Early County, with 101 MW of the 139 MW state total.
22 buyers; by stated MW, OpenAI leads. Each row is on the Georgia demand page.
We list 8 Georgia sites and do not sell land; each site names its source.
"Georgia PSC certification of 9,985 MW of new Georgia Power generation (large-load certification)" (19 December 2025) is the newest.
Ask for these below. There is no price on this page.