In short

As of 25 November 2026, DC Market Insights tracks 4 data centers operated by KT Cloud in 1 country, of which 2 are operational. Stated operational capacity is 26 MW, with a further 50 MW under construction and 50 MW planned. The pipeline is 3.8 times the capacity already operating.

4Facilities tracked
1Countries
26 MWOperational (2 sites)
50 MWUnder construction (1 site)
50 MWPlanned (1 site)

MW = IT capacity where the source states it, otherwise total capacity. 3 of 4 facilities have a stated capacity; the others are counted as sites only.

Gasan AI Data Center · KT Cloud · Seoul (approximate location)Mokdong 2 Data Center · KT Cloud · Seoul (approximate location)Ansan AI Data Center · KT Cloud · Ansan (approximate location)Cheongna AI Data Center · KT Cloud · Incheon (approximate location)
Operational Under construction Planned Pin = exact site location; dot = city (approximate) Select a country on the map to open its page.

Market snapshot

KT Cloud data centers: key facts

  • Capacity under construction or planned (100 MW) is 3.8 times the operational base of 26 MW.
  • Its largest operational site is Gasan AI Data Center in Seoul, South Korea at 26 MW.
  • The largest project in the pipeline is Ansan AI Data Center by KT Cloud (50 MW, under construction).
  • By type, the tracker lists 2 colocation and 2 hyperscale facilities.
  • 3 of 4 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational26 MW
Under construction50 MW
Planned50 MW

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Facilities by type
Colocation2
Hyperscale2

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

KT Cloud development pipeline

Under construction and planned facilities with a stated capacity, largest first. 50 MW under construction and 50 MW planned in total.

ProjectLocationStatusTypeCapacity
Ansan AI Data CenterKT Cloud Ansan, South Korea Under construction Hyperscale 50 MW
Cheongna AI Data CenterKT Cloud Incheon, South Korea Planned Hyperscale 50 MW

Facilities

4 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
Ansan AI Data CenterHyperscale Ansan, South Korea Under construction 50 MW total — Trade press
Cheongna AI Data CenterHyperscale
History
  1. Announced
  2. Planned
Incheon, South Korea Planned 50 MW total — Trade press
Gasan AI Data CenterColocation
History
  1. Operational
  2. Operational
Seoul, South Korea Operational 26 MW IT 2025 Trade press
Mokdong 2 Data CenterColocation Seoul, South Korea Operational — — Trade press

Market position

How KT Cloud compares

Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.

  • In South Korea, KT Cloud ranks #4 of 16 tracked operators by capacity, with 11% of the country’s tracked MW.
  • South Korea has 50 tracked data centers from 16 operators: 730 MW operational and 388 MW under construction or planned.
  • Seoul also hosts 10 other tracked data center(s), run by LG Uplus, ST Telemedia Global Data Centres, Digital Edge and SK Broadband.

Data center operators in South Korea

Tracked facilities5016 operators
Operational capacity730 MW388 MW in the pipeline
KT Cloud rank by capacity#4of 16 operators · 11%
Renewable share of generation9.8%2025
OperatorFacilitiesOperational MWPipeline MW
NAVER2270 MW—
LG Uplus13261 MW—
Digital Edge538.4 MW120 MW
IGIS Asset Management180 MW—
Samsung SDS6—60 MW
Keppel1—60 MW
Princeton Digital Group1—48 MW
ST Telemedia Global Data Centres130 MW—

All data centers in South Korea Power and policy in South Korea

Other data centers in Seoul

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
  • Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers does KT Cloud operate?

DC Market Insights tracks 4 KT Cloud data center(s) in 1 country as of November 2026: 2 operational, 1 under construction and 1 planned.

Which other companies operate data centers in South Korea?

Besides KT Cloud, the largest operators we track in South Korea by capacity are NAVER, LG Uplus, Digital Edge, IGIS Asset Management and Samsung SDS. The South Korea page lists all 16 operators.

What rules apply to data centers in South Korea?

Our Power & Policy Tracker lists 7 government actions on data centers and power in South Korea, including 0 restriction(s) and 0 incentive scheme(s) in force.

Which other data centers are in Seoul?

Other tracked data centers in Seoul include Gasan Center (LG Uplus), STTGDC SEL1 (STT Seoul 1) (ST Telemedia Global Data Centres), Nonhyeon Center (LG Uplus) and Sangam Center (LG Uplus).

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Global capacity

How much data center capacity is installed worldwide?

Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.

Open the Global Capacity Tracker

Need the full list, or a capacity view of one market?

Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.

Talk to an analyst