Country Reports · Forecast 2026-2035

Netherlands AI Data Center Market Size, Share & Forecast to 2035

Market at a glance

The Netherlands AI Data Center market was worth USD 499.1 million in 2025 and is forecast to reach USD 3,040.0 million by 2035, growing at a 19.8% CAGR.

$499.1MMarket size, 2025
$3.04BForecast, 2035
19.8%CAGR, 2025-2035
$47.0MMarket size, 2020
Market size, USD million
47.0 2020 499.1 2025 3,040.0 2035F

Key findings

Driver

Google's EUR 3.7 Billion Dutch Footprint Moves AI Capacity to Groningen

Trend

Blackwell-Class Systems Arrive in Colocation Halls

Challenge

Four-Year Grid Waits Cap New AI Megawatts

Opportunity

Retrofitting Amsterdam's Air-Cooled Halls

What is inside the report

  1. 01Introduction
  2. 02Executive Summary
  3. 03Why Estimates Differ
  4. 04Market Drivers
  5. 05Market Trends
  6. 06Market Challenges
  7. 07Market Opportunities
  8. 08Pricing Analysis
  9. 09Standards and Regulation
  10. 10Market Segmentation
  • 17chapters
  • 2020-2024Historical period
  • 2026-2035Forecast period
  • —Companies profiled

Full table of contents

Segmentation

Component
Electrical Power InfrastructureLiquid and High-Density CoolingBuilding Shell and AI-Ready RacksHigh-Speed Network FabricOperations Services and Software
Buyer Type
Hyperscale Self-BuildColocation and WholesaleGPU Cloud ProvidersResearch and Public AI FactoriesEnterprise On-Premises
Cooling Approach
Air-Cooled High DensityDirect-to-Chip Liquid CoolingImmersion and Rear-Door Cooling
Workload
AI TrainingAI Inference

Recent developments

March 2025

Juvoly unveiled an NVIDIA DGX B200 system at NorthC Rotterdam (Source: NorthC Datacenters).

June 2025

the cabinet and region committed EUR 200 million to the Groningen AI factory (Source: Government of the Netherlands).

October 2025

EuroHPC selected the Netherlands AI Factory in its third wave (Source: EuroHPC Joint Undertaking).

November 2025

Google opened its Winschoten data center (Source: Google).

November 2025

Digital Realty opened AMS11 in Amsterdam (Source: Digital Realty).

September 2026

Eurofiber confirmed it will host the AI factory for SURF, fully operational in early 2028 (Source: Eurofiber).

Full analysis

The Netherlands AI Data Center Market is valued at USD 815.41 million in 2026 and is projected to reach USD 3.04 billion by 2035, up from USD 499.10 million in 2025, a CAGR of 19.80% from 2025 to 2035 (DC Market Insights estimate). The market covers the facility layer built for AI workloads in the Netherlands: power trains, liquid and high-density cooling, AI-ready shells and racks, the high-speed network fabric inside the hall, and the operations services that keep those halls running; GPU servers, electricity bills and cloud revenue sit outside it. What moves the money here is the grid queue rather than chip supply: Netbeheer Nederland counted 14,044 offtake requests for 9,131 MW waiting at regional grid operators in October 2025, so the 125 MW of new IT capacity that did connect in 2025 carried a premium. The 2025 receipt is 31.25 MW of AI-class capacity × USD 13.80 million per MW = USD 431.25 million of new build, plus 8 MW of liquid-cooling retrofits × USD 4.50 million = USD 36.00 million, plus USD 31.85 million of services on the installed AI base. Direct-to-chip liquid cooling is the fastest large segment at 25.95% a year, and Groningen, home of the national AI factory and Google’s Winschoten site, is the fastest region at 24.97% a year.

Key Market Statistics: How Big Is the Netherlands AI Data Center Market in 2026?

DC Market Insights values the Netherlands AI Data Center Market at USD 815.41 million in 2026, 63.38% above the USD 499.10 million of 2025.

  • Market size 2025: USD 499.10 million
  • Market size 2026: USD 815.41 million
  • Market size 2030: USD 2.03 billion
  • Market size 2035: USD 3.04 billion
  • CAGR 2025-2035: 19.80% (low case 16.86%, high case 22.20%)
  • Largest component: Liquid and High-Density Cooling, 34.76% of 2025 value
  • Fastest cooling approach: Immersion and Rear-Door Cooling, 28.39% a year
  • Leading region: Amsterdam Metropolitan Area, 48% of 2025 value
  • Fastest region: Groningen (Eemshaven and Winschoten), 24.97% a year
  • Largest location: Amsterdam (city), USD 119.78 million in 2025
  • Largest buyer type: Hyperscale Self-Build, 46% of 2025 value

Key Takeaways: What Should Buyers Know About the Netherlands AI Data Center Market?

  • AI-class capacity is a quarter of new Dutch IT capacity in 2025 (31.25 of 125 MW) and rises to 60% by 2035, because new halls are designed for liquid-cooled racks above 40 kW.
  • Groningen grows 24.97% a year because the 2023 hyperscale decree leaves Het Hogeland as the only zone for new hyperscale campuses and the EUR 200 million AI factory lands there.
  • Operations services grow 33.35% a year because the installed AI base climbs from about 114 MW at the end of 2025 to about 1,106 MW by the end of 2034.
  • Inference passes training around 2028 and rises from 44% to 64% of value by 2035, because Dutch enterprises buy capacity close to Amsterdam’s interconnection hubs.

Executive Summary: How Fast Is the Netherlands AI Data Center Market Growing?

The Netherlands AI Data Center Market size was valued at USD 47.03 million in 2020, reached USD 499.10 million in 2025, and is anticipated to reach USD 3.04 billion by 2035, at a CAGR of 19.80% during the forecast period.

Historical period 2020-2024
Base year 2025
Forecast period 2026-2035
Market size 2025 USD 499.10 million
Market size 2026 USD 815.41 million
CAGR 2025-2035 19.80%
Market size 2035 USD 3.04 billion

The Netherlands AI Data Center Market grew 60.38% a year from 2020 to 2025 from a small base of USD 47.03 million, when AI-class halls were 3% of new Dutch capacity. Growth slows to 19.80% after 2025 because new IT capacity flattens at 230-240 MW a year from 2030 under grid limits, while the AI share keeps rising from 25% to 60%. Statistics Netherlands (CBS) reported that data centres used 5,100 GWh in 2024, 4.6% of national electricity, which is why every AI megawatt competes with households and industry for a connection.

Netherlands AI Data Center Market size 2020-2035: USD 47.03 million in 2020, USD 499.10 million in 2025, USD 3.04 billion by 2035, CAGR 19.80%

Market Scope: What Does the Netherlands AI Data Center Market Include?

The Netherlands AI Data Center Market covers spending on facility infrastructure for AI-class data center capacity in the Netherlands, worth USD 499.10 million in 2025. AI-class means halls designed for accelerator racks of 40 kW and above, mostly with liquid cooling.

Included

  • Electrical power infrastructure for AI halls: medium-voltage switchgear, transformers, UPS, busway and backup generation (USD 153.12 million in 2025).
  • Liquid and high-density cooling, including retrofits of existing halls (USD 173.50 million).
  • Building shell and AI-ready racks, high-speed network fabric inside the hall, and operations services and software.

Excluded

How the segments fit together

Every segment table below sums to the same total each year: component, buyer type, cooling approach and workload each split USD 499.10 million in 2025 and USD 3.04 billion in 2035, and five Dutch regions split the same totals.

Why Do Netherlands AI Data Center Market Estimates Differ?

Estimates differ because they count different layers: DC Market Insights puts the 2026 facility layer at USD 815.41 million, while estimates that add graphics processing unit (GPU) servers count several times that figure. An earlier DC Market Insights edition used a narrower hyperscale-only base and gave less than half of today’s value; this edition counts every AI-class hall, including colocation and research halls, and the bottom-up MW model gives USD 499.10 million.

Element In this report Why
Facility infrastructure for AI halls Yes, USD 467.25 million in 2025 Core of the market
Operations services and software Yes, USD 31.85 million Recurring spend on the installed AI base
GPU servers and accelerators No Counted in the AI Data Center Market
GPU cloud and AI-as-a-service revenue No Service revenue, not infrastructure
Conventional halls below 40 kW per rack No Counted in the Netherland Data Center Infrastructure Market

Broader definitions add AI software platforms, generative AI services, machine learning operations tools and consulting, and some also add GPU rental income; none of these are counted here. Small and medium-sized enterprises (SMEs) are in scope when they buy AI-ready colocation, and they sit inside the Enterprise On-Premises and Colocation and Wholesale rows. Questions about adoption rates among Dutch SMEs by size, or about the design and consulting services market, fall outside this facility scope.

Market Drivers: What Is Driving AI Data Center Spending in the Netherlands?

Three named projects and one rule drive the Netherlands AI Data Center Market: Google’s Groningen build-out, the national AI factory and the 2023 hyperscale decree that steers large AI campuses north, and hyperscale plus research buyers hold 51% of the USD 499.10 million spent in 2025.

Google’s EUR 3.7 Billion Dutch Footprint Moves AI Capacity to Groningen

Google opened its AI-focused Winschoten data center in November 2025 and said it has invested more than EUR 3.7 billion in Dutch digital infrastructure, according to the Google release of 18 November 2025. Google also started a EUR 600 million data center at Westpoort in Groningen in April 2024 (Source: Google Netherlands). DC Market Insights estimates that hyperscale self-build accounts for 46% of the 2025 market, or USD 229.59 million.

The EUR 200 Million Groningen AI Factory Anchors Public Demand

The cabinet and the northern provinces committed EUR 200 million to a Dutch AI factory in Groningen, split into EUR 70 million from the Ministry of Economic Affairs and Defence, EUR 60 million from the regional Nij Begun programme and EUR 70 million requested from Europe, according to the Government of the Netherlands announcement of 27 June 2025. The EuroHPC Joint Undertaking selected the Netherlands AI Factory in its third wave, as stated in the EuroHPC Joint Undertaking selection of 10 October 2025, and Eurofiber will host the system for SURF, the cooperative ICT organisation of Dutch education and research, with direct-to-chip cooling, with full operation expected in early 2028 (Source: Eurofiber). Research and Public AI Factories hold a 5% share of 2025 value in the DC Market Insights model and keep about 3% by 2035.

The 70 MW Hyperscale Rule Sends New AI Campuses North

National rules ban new hyperscale campuses above 70 MW of connection and 10 hectares outside Het Hogeland and Hollands Kroon, a threshold the government restated to Parliament in April 2026 (Source: Tweede Kamer). Inside Amsterdam, a 99 MW project at Plimsollweg built as three 33 MW towers on 2.2 hectares does not count as hyperscale under that rule (Source: Tweede Kamer, April 2026), so dense AI towers remain possible in the city. That is why Hollands Kroon holds 21% and Groningen 19% of 2025 value.

Liquid cooling is replacing air in the Netherlands AI Data Center Market: direct-to-chip systems rise from 40% of 2025 value to 66% by 2035 in the DC Market Insights model.

Blackwell-Class Systems Arrive in Colocation Halls

Juvoly unveiled one of the first NVIDIA Corporation DGX B200 systems (an eight-GPU AI server) in the Netherlands at NorthC’s Rotterdam data center in March 2025 (Source: NorthC Datacenters), and Digital Realty opened AMS11 in Amsterdam as an AI-optimised facility in November 2025 (Source: Digital Realty). Colocation and Wholesale grows 21.36% a year, faster than hyperscale self-build at 18.13%.

Operators Look for Their Own Power

Equinix and ULC-Energy agreed in August 2025 to explore up to 250 MWe of small modular reactor power for Dutch data centers (Source: Equinix). Google said it has supported more than 1 GW of clean-energy capacity in the Netherlands (Source: Google, November 2025). On-site and contracted power changes where AI halls can be built, which favours Groningen’s wind landing points.

Market Challenges: What Limits the Netherlands AI Data Center Market?

Grid congestion is the main limit: TenneT alone held 212 offtake requests totalling 38 GW in October 2025, according to the Netbeheer Nederland queue update of 6 October 2025.

Four-Year Grid Waits Cap New AI Megawatts

The Dutch Data Center Association (DDA) reports that a grid connection took 10 weeks in 2016 and 4.5 years on average in 2026. DC Market Insights therefore holds new Dutch IT capacity at 230-240 MW a year after 2030, so the market’s 19.80% a year comes from a rising AI share of a capped flow of new megawatts, not from more megawatts.

No Budget Room for an AI Gigafactory

A March 2026 decision note to the State Secretary found no room in the current budget for further EuroHPC commitments and put an AI gigafactory at about 100,000 GPUs and EUR 3-5 billion per site, favouring market financing (Source: Tweede Kamer). Without a gigafactory, the high case of USD 3.71 billion by 2035 needs private capital; the base case assumes none.

Market Opportunities: Where Is the Money in Dutch AI Data Centers?

The two largest openings in the Netherlands AI Data Center Market are liquid-cooling retrofits, 8 MW in 2025 and 9-12 MW a year after that, and operations services, whose share of value rises from 6.38% in 2025 to 18.64% by 2035.

Retrofitting Amsterdam’s Air-Cooled Halls

Amsterdam has little new space, so operators convert halls in place: DC Market Insights models 8 MW of retrofits in 2025 rising to 12 MW a year from 2027 at USD 4.50 million per MW (2025 prices), which suits cooling and electrical suppliers already on site.

Services for a Growing Northern AI Estate

Groningen’s share rises from 19% to 29% of value by 2035, worth USD 881.01 million in 2035, and every new AI megawatt there needs maintenance, controls and liquid-loop services at USD 0.42 million per MW a year (2025 prices).

Pricing: How Much Does an AI Data Center Megawatt Cost in the Netherlands?

In the Netherlands AI Data Center Market, an AI-class megawatt costs USD 13.80 million of facility infrastructure in 2025 (DC Market Insights estimate), 23% more than the USD 11.25 million of a conventional Dutch megawatt in the Netherland Data Center Infrastructure Market.

Year New AI hall, USD million per MW Liquid-cooling retrofit, USD million per MW Operations services, USD million per MW a year
2020 12.50 4.08 0.38
2025 13.80 4.50 0.42
2030 15.24 4.97 0.46
2035 16.82 5.49 0.51

The USD 13.80 million splits into USD 4.90 million electrical, USD 4.40 million cooling, USD 3.90 million shell and racks and USD 0.60 million network fabric. Public anchors bracket it: the Government of Portugal estimates about EUR 8 billion of initial investment per extra gigawatt (EUR 8 million per MW), and the Dutch decision note puts a 100,000-GPU gigafactory at EUR 3-5 billion including part of the IT. Eurostat put Dutch non-household electricity at EUR 0.1179 per kWh in the second half of 2025, above the EU average of EUR 0.1095, which raises the value of efficient cooling.

Standards and Regulation: Which Rules Apply to AI Data Centers in the Netherlands?

Four rules shape the Netherlands AI Data Center Market, and the 70 MW hyperscale threshold decides where 40% of 2025 value sits.

  • Decree of 20 December 2023 (Staatsblad 2023, 492): new hyperscale campuses above 10 hectares and 70 MW only in Het Hogeland, with growth of existing campuses in Hollands Kroon (Source: Staatsblad).
  • Amsterdam data center policy: a 670 MVA connection envelope and half of the available space released up to 2030 (Source: Municipality of Amsterdam, December 2023).
  • Commission Delegated Regulation (EU) 2024/1364: annual energy and water reporting for data centers of 500 kW and above, with the Dutch window running from 16 March to 15 May 2026 (Source: RVO).
  • EU AI Act and EuroHPC rules: the AI factory must give access to start-ups, researchers and industry under EuroHPC terms (Source: EuroHPC Joint Undertaking).

Market Segmentation: Which Segment Carries the Value in the Netherlands AI Data Center Market?

Liquid and High-Density Cooling carries the most value at USD 173.50 million in 2025, 34.76% of the market, because retrofits add to new-build cooling.

By Component

Operations Services and Software is the fastest component at 33.35% a year as the installed AI base compounds.

Component 2025 (USD million) Share 2025 2035 (USD million) CAGR 2025-2035
Electrical Power Infrastructure 153.12 30.68% 860.12 18.84%
Liquid and High-Density Cooling 173.50 34.76% 821.73 16.83%
Building Shell and AI-Ready Racks 121.88 24.42% 684.59 18.84%
High-Speed Network Fabric 18.75 3.76% 105.32 18.84%
Operations Services and Software 31.85 6.38% 566.23 33.35%

By Buyer Type

Enterprise On-Premises grows fastest at 23.29% from a small base, and GPU Cloud Providers follow at 22.00%.

Buyer Type 2025 (USD million) Share 2025 2035 (USD million) CAGR 2025-2035
Hyperscale Self-Build 229.59 46.00% 1,215.19 18.13%
Colocation and Wholesale 179.68 36.00% 1,245.57 21.36%
GPU Cloud Providers 49.91 10.00% 364.56 22.00%
Research and Public AI Factories 24.96 5.00% 91.14 13.83%
Enterprise On-Premises 14.97 3.00% 121.52 23.29%

By Cooling Approach

Immersion and Rear-Door Cooling grows 28.39% a year; Direct-to-Chip Liquid Cooling becomes the largest approach by 2035 at USD 2.01 billion.

Cooling Approach 2025 (USD million) Share 2025 2035 (USD million) CAGR 2025-2035
Air-Cooled High Density 259.53 52.00% 546.84 7.74%
Direct-to-Chip Liquid Cooling 199.64 40.00% 2,005.07 25.95%
Immersion and Rear-Door Cooling 39.93 8.00% 486.08 28.39%

By Workload

AI Inference grows 24.37% a year against 14.62% for AI Training.

Workload 2025 (USD million) Share 2025 2035 (USD million) CAGR 2025-2035
AI Training 279.50 56.00% 1,093.67 14.62%
AI Inference 219.60 44.00% 1,944.31 24.37%

DC Exclusive: The Dutch AI Compute Site Tracker, 8 Projects From Winschoten to Rotterdam

This tracker is a DC Market Insights estimate, modelled on 11 inputs and 8 named projects; it shows that in the Netherlands AI Data Center Market northern sites carry 40% of 2025 value while Amsterdam keeps the interconnection-led inference demand.

Project Location Status and date What it adds
Google Winschoten Groningen Opened November 2025 AI-focused hyperscale; part of EUR 3.7 billion Dutch investment
Google Westpoort Groningen city Construction from April 2024 EUR 600 million, about 125 direct jobs
Netherlands AI Factory (SURF, hosted by Eurofiber) Groningen Building 2027, full operation early 2028 EUR 200 million public funding, direct-to-chip cooling
Microsoft Middenmeer next phase Hollands Kroon Announced 10 September 2025 Campus west of the A7; no MW published
Plimsollweg towers Amsterdam Answer to Parliament April 2026 About 99 MW in three 33 MW towers on 2.2 hectares
Digital Realty AMS11 Amsterdam Opened November 2025 AI-optimised colocation
Juvoly DGX B200 at NorthC Rotterdam Unveiled March 2025 One of the first Blackwell systems in the country
Equinix and ULC-Energy Netherlands Agreement August 2025 Up to 250 MWe of small modular reactor power explored

Read with the location model, the tracker explains why Winschoten grows 25.56% a year and Groningen city 33.71% a year, the two fastest locations, while Amsterdam (city) grows 16.40%.

Regional Insights: Where in the Netherlands Are AI Data Centers Built?

The Amsterdam Metropolitan Area leads with USD 239.57 million in 2025, 48% of the Netherlands AI Data Center Market, and Groningen (Eemshaven and Winschoten) grows fastest at 24.97% a year.

Region 2025 (USD million) Share 2025 2035 (USD million) CAGR 2025-2035
Amsterdam Metropolitan Area 239.57 48% 1,154.43 17.03%
Hollands Kroon (Middenmeer) 104.81 21% 607.60 19.21%
Groningen (Eemshaven and Winschoten) 94.83 19% 881.01 24.97%
Rotterdam, The Hague and Utrecht 39.93 8% 243.04 19.80%
East and South Netherlands 19.96 4% 151.90 22.50%

Amsterdam Metropolitan Area

Amsterdam’s share falls from 48% to 38% by 2035 because the city releases only half its data center space up to 2030, yet value still grows to USD 1.15 billion through dense towers such as Plimsollweg.

Hollands Kroon (Middenmeer)

Microsoft’s next campus phase keeps Hollands Kroon at about 20% of value, USD 607.60 million by 2035.

Groningen (Eemshaven and Winschoten)

Groningen rises from USD 94.83 million to USD 881.01 million because it is the only zone open to new hyperscale campuses and it hosts the AI factory.

Rotterdam, The Hague and Utrecht

Enterprise and research inference keeps this region at 8% of value, USD 243.04 million by 2035; Rotterdam hosts the Juvoly DGX B200 cluster.

East and South Netherlands

Eindhoven’s semiconductor cluster lifts East and South Netherlands to USD 151.90 million by 2035, 22.50% a year.

Location Analysis: Which Dutch Locations Lead in AI Data Centers?

In the Netherlands AI Data Center Market, Amsterdam (city) is the largest location with USD 119.78 million in 2025, and Groningen city (Westpoort and Zernike) is the fastest at 33.71% a year.

Rank Location Region 2025 (USD million) 2035 (USD million) CAGR 2025-2035
1 Amsterdam (city) Amsterdam Metropolitan Area 119.78 546.84 16.40%
2 Middenmeer (Agriport A7) Hollands Kroon (Middenmeer) 104.81 607.60 19.21%
3 Haarlemmermeer (Schiphol) Amsterdam Metropolitan Area 69.87 303.80 15.83%
4 Eemshaven Groningen (Eemshaven and Winschoten) 59.89 455.70 22.50%
5 Almere Amsterdam Metropolitan Area 29.95 212.66 21.66%
6 Winschoten Groningen (Eemshaven and Winschoten) 24.96 243.04 25.56%
7 Zaanstad Amsterdam Metropolitan Area 19.96 91.14 16.40%
8 Rotterdam Rotterdam, The Hague and Utrecht 17.47 106.33 19.80%
9 Utrecht Rotterdam, The Hague and Utrecht 12.48 75.95 19.80%
10 Eindhoven East and South Netherlands 12.48 91.14 22.00%
11 Groningen city (Westpoort and Zernike) Groningen (Eemshaven and Winschoten) 9.98 182.28 33.71%
12 The Hague Rotterdam, The Hague and Utrecht 9.98 60.76 19.80%

The twelve locations hold 98.5% of 2025 value; the rest sits in smaller enterprise and edge sites.

Forecast Scenarios: What Could the Netherlands AI Data Center Market Reach by 2035?

The Netherlands AI Data Center Market base case reaches USD 3.04 billion by 2035, with a range of USD 2.37 billion to USD 3.71 billion.

Scenario 2035 (USD million) CAGR 2025-2035 What it assumes
Low 2,369.62 16.86% Grid waits stay above 4 years; AI share 50% of new capacity by 2035
Base 3,037.98 19.80% 230-240 MW of new IT a year, AI share 60% by 2035
High 3,706.34 22.20% A market-financed AI gigafactory and faster TenneT reinforcement

Key Players and Market Share: Who Leads the Netherlands AI Data Center Market?

The top three buyers, Google, Microsoft and Equinix, hold about 52% of 2025 spend (DC Market Insights estimate based on site MW), and suppliers are led by Schneider Electric and Vertiv.

  • Google
  • Microsoft
  • Equinix
  • Digital Realty
  • NorthC Datacenters
  • Iron Mountain
  • Eurofiber
  • SURF
  • Schneider Electric
  • Vertiv
  • ABB
  • Eaton
  • Siemens
  • Stulz
  • Rittal
  • NVIDIA

Schneider Electric reported third-quarter 2026 revenue of EUR 11.46 billion, up 16.9% organically, and said regional colocation customers are adopting a turnkey approach (Source: Schneider Electric). Vertiv reported second-quarter 2026 net sales of USD 3.27 billion, 24% above a year earlier (Source: Vertiv filing). Equinix said in October 2025 that land in Amsterdam and four other metros supports more than 900 MW (Source: Equinix).

Recent Developments: What Changed in Dutch AI Data Centers in 2025-2026?

Six dated events since March 2025 shaped the Netherlands AI Data Center Market, which DC Market Insights values at USD 815.41 million in 2026.

  • In March 2025, Juvoly unveiled an NVIDIA DGX B200 system at NorthC Rotterdam (Source: NorthC Datacenters).
  • In June 2025, the cabinet and region committed EUR 200 million to the Groningen AI factory (Source: Government of the Netherlands).
  • In October 2025, EuroHPC selected the Netherlands AI Factory in its third wave (Source: EuroHPC Joint Undertaking).
  • In November 2025, Google opened its Winschoten data center (Source: Google).
  • In November 2025, Digital Realty opened AMS11 in Amsterdam (Source: Digital Realty).
  • In September 2026, Eurofiber confirmed it will host the AI factory for SURF, fully operational in early 2028 (Source: Eurofiber).

Research Methodology: How the Model Sizes the Netherlands AI Data Center Market

The model counts 16 annual cohorts of new Dutch IT capacity, 125 MW in 2025, times an AI share of 25%, times USD 13.80 million per AI megawatt, plus retrofits and services; it gives USD 499.10 million in 2025.

Capacity follows the Netherland Data Center Infrastructure Market (installed base above 1.5 GW at the end of 2025, as the DDA reports), and the AI share rises from 3% in 2020 to 60% in 2035. Prices rise 2% a year. Services cost USD 0.42 million per prior-year installed AI megawatt, with 1.5% of the base retired each year. Three bound checks hold: (1) ceiling, the 2025 value is 25.4% of the USD 1.96 billion Dutch infrastructure market; (2) ceiling, 1,106 MW of installed AI capacity by the end of 2034 is below the DDA’s 2.8 GW expectation for the whole Dutch market in 2031; (3) floor, Google’s EUR 600 million Westpoort build alone spread over three years is about USD 225 million a year, below the hyperscale row of USD 229.59 million. The wider country picture is in the Netherland Data Center Market, and a comparable neighbour is the Belgium AI Data Center Market. Full method: research methodology.

Table of contents

  • 17 chapters
  • 1 figures
  • 11 data tables
  1. 01Introduction
    • 1.1Market Definition and Scope
    • 1.2Included and Excluded
    • 1.3How the Segments Fit Together
  2. 02Executive Summary
    • 2.1Market Snapshot, 2025, 2026 and 2035
    • 2.2Key Market Statistics
    • 2.3Key Takeaways
  3. 03Why Estimates Differ
    • 3.1Scope Comparison Table
    • 3.2In-Scope Buyer Groups
  4. 04Market Drivers
    • 4.1Google's EUR 3.7 Billion Dutch Footprint Moves AI Capacity to Groningen
    • 4.2The EUR 200 Million Groningen AI Factory Anchors Public Demand
    • 4.3The 70 MW Hyperscale Rule Sends New AI Campuses North
  5. 05Market Trends
    • 5.1Blackwell-Class Systems Arrive in Colocation Halls
    • 5.2Operators Look for Their Own Power
  6. 06Market Challenges
    • 6.1Four-Year Grid Waits Cap New AI Megawatts
    • 6.2No Budget Room for an AI Gigafactory
  7. 07Market Opportunities
    • 7.1Retrofitting Amsterdam's Air-Cooled Halls
    • 7.2Services for a Growing Northern AI Estate
  8. 08Pricing Analysis
    • 8.1Cost per AI Megawatt, 2020-2035
    • 8.2Public Price Anchors
  9. 09Standards and Regulation
    • 9.1Hyperscale Decree (Staatsblad 2023, 492)
    • 9.2Amsterdam Data Center Policy
    • 9.3Delegated Regulation (EU) 2024/1364
    • 9.4EU AI Act and EuroHPC Access Rules
  10. 10Market Segmentation
    • 10.1By Component
    • 10.2By Buyer Type
    • 10.3By Cooling Approach
    • 10.4By Workload
  11. 11DC Exclusive: Dutch AI Compute Site Tracker
    • 11.18 Named Projects
    • 11.2Location Growth Read-Across
  12. 12Regional Insights
    • 12.1Amsterdam Metropolitan Area
    • 12.2Hollands Kroon (Middenmeer)
    • 12.3Groningen (Eemshaven and Winschoten)
    • 12.4Rotterdam, The Hague and Utrecht
    • 12.5East and South Netherlands
  13. 13Location Analysis
    • 13.1Amsterdam (city)
    • 13.2Middenmeer (Agriport A7)
    • 13.3Haarlemmermeer (Schiphol)
    • 13.4Eemshaven
    • 13.5Almere
    • 13.6Winschoten
    • 13.7Zaanstad
    • 13.8Rotterdam
    • 13.9Utrecht
    • 13.10Eindhoven
    • 13.11Groningen city (Westpoort and Zernike)
    • 13.12The Hague
  14. 14Forecast Scenarios
    • 14.1Low Case
    • 14.2Base Case
    • 14.3High Case
  15. 15Key Players and Market Share
    • 15.1Google
    • 15.2Microsoft
    • 15.3Equinix
    • 15.4Digital Realty
    • 15.5NorthC Datacenters
    • 15.6Iron Mountain
    • 15.7Eurofiber
    • 15.8SURF
    • 15.9Schneider Electric
    • 15.10Vertiv
    • 15.11ABB
    • 15.12Eaton
    • 15.13Siemens
    • 15.14Stulz
    • 15.15Rittal
    • 15.16NVIDIA
  16. 16Recent Developments
    • 16.12025
    • 16.22026
  17. 17Research Methodology
    • 17.1Capacity Cohort Model
    • 17.2Bound Checks
  1. Fig. 1Netherlands AI Data Center Market Size, 2020-2035 (USD million)
  1. Table 1Executive Summary Attributes
  2. Table 2Scope Comparison
  3. Table 3Cost per AI Megawatt, 2020-2035
  4. Table 4Market by Component, 2025 and 2035
  5. Table 5Market by Buyer Type, 2025 and 2035
  6. Table 6Market by Cooling Approach, 2025 and 2035
  7. Table 7Market by Workload, 2025 and 2035
  8. Table 8Dutch AI Compute Site Tracker
  9. Table 9Market by Region, 2025 and 2035
  10. Table 10Top 12 Locations, 2025 and 2035
  11. Table 11Forecast Scenarios, 2035

About this report

Amit JainDeepti Agrawal

Written by Amit Jain and reviewed by Deepti Agrawal, Senior Editor, Research. Figures are built top-down and bottom-up and reconciled before publication, with 2025 as the base year.

Read our methodology

How we built this

  • Historical period2020-2024
  • Base year2025
  • Forecast period2026-2035
  • Sizing approachTop-down + bottom-up

Need more than the report?

Advisory on this market

Due diligence, site selection and market entry work, by the analysts who wrote this report.

See consulting services

Frequently asked questions

What is the size of the Netherlands AI Data Center Market in 2026?

USD 815.41 million in 2026, up 63.38% from USD 499.10 million in 2025, according to DC Market Insights estimates. The market is projected to reach USD 3.04 billion by 2035, a CAGR of 19.80% from 2025.

How fast is the Netherlands AI Data Center Market growing?

19.80% a year from 2025 to 2035, after 60.38% a year from 2020 to 2025. The AI share of new Dutch IT capacity rises from 25% to 60% while new capacity is held at 230-240 MW a year by grid limits.

What does the Netherlands AI Data Center Market include?

USD 499.10 million of 2025 spend on facility infrastructure for AI-class halls: electrical power, liquid and high-density cooling, shells and AI-ready racks, network fabric and operations services. GPU servers, electricity and cloud revenue are excluded.

How much does an AI data center megawatt cost in the Netherlands?

USD 13.80 million of facility infrastructure per AI megawatt in 2025, DC Market Insights estimates, against USD 11.25 million for a conventional Dutch megawatt. Liquid-cooling retrofits cost about USD 4.50 million per megawatt.

Which region leads the Netherlands AI Data Center Market?

The Amsterdam Metropolitan Area, with USD 239.57 million or 48% of 2025 value. Groningen (Eemshaven and Winschoten) grows fastest at 24.97% a year because it is the only zone open to new hyperscale campuses.

Which segment grows fastest in the Netherlands AI Data Center Market?

Operations Services and Software, at 33.35% a year to USD 566.23 million by 2035. By cooling approach, Immersion and Rear-Door Cooling grows fastest at 28.39% a year.

What is the Groningen AI factory?

A EUR 200 million national AI facility funded by the cabinet, Defence and the northern region, selected by EuroHPC in October 2025. Eurofiber will host it for SURF with direct-to-chip cooling, fully operational in early 2028.

How does grid congestion affect AI data centers in the Netherlands?

14,044 offtake requests for 9,131 MW waited at regional grid operators in October 2025, and connections take about 4.5 years. DC Market Insights therefore caps new Dutch IT capacity at 230-240 MW a year after 2030.

Who are the leading companies in the Netherlands AI Data Center Market?

Google, Microsoft and Equinix hold about 52% of 2025 spend, DC Market Insights estimates. Digital Realty, NorthC, Iron Mountain and Eurofiber run AI-ready colocation, and Schneider Electric and Vertiv lead equipment supply.

Why do Netherlands AI Data Center Market estimates differ?

USD 815.41 million in 2026 counts only the facility layer of AI-class halls. Estimates that add GPU servers, AI software or GPU rental income are several times larger; an earlier DC Market Insights edition counted only hyperscale halls.

Get this report

How do I get the full report?

Request a quote; we reply by email within one business day.

How and when will I receive the report?

By email, within 24-48 business hours of payment.

How can I pay?

Once you accept the quote, we email you a secure payment link.

Can I see a sample first?

Yes. Request a free sample and we will email it to you.

Can the report be tailored to my needs?

Yes. We can add countries, segments or data cuts. Talk to an analyst about the scope you need.

Can I get an invoice or pay against a purchase order?

Write to sales@dcmarketinsights.com and our team will help.

Refund and returns policy

Request a quote

Netherlands AI Data Center Market

Tell us what you need. We reply by email with scope, delivery date and a quote, usually within one business day.

Contact Form

Your data is safe with us

  • Your details stay private. We never sell or share them.
  • Used only to reply to your message
  • No spam: we only send what you asked for
  • Encrypted (SSL) form, handled by our own team

Privacy Policy

Free sample

Netherlands AI Data Center Market

See the structure, tables and charts before you decide.

Smallform of Sample request

Your data is safe with us

  • Your details stay private. We never sell or share them.
  • Used only to send your sample and answer your questions
  • No spam: we only send what you asked for
  • Encrypted (SSL) form, handled by our own team

Privacy Policy

Talk to an analyst

Ask the team that built this report

Different scope, country or data cut? A senior analyst replies within one business day.

Contact Form

Your data is safe with us

  • Your message goes straight to our research team
  • Your details stay private. We never sell or share them.

Privacy Policy