Apatura Data Centers
Data centers operated by Apatura that we have verified: location, status and capacity, each checked against its source.
In short
As of 10 October 2026, DC Market Insights tracks 7 data centers operated by Apatura in 1 country, of which 0 are operational.
MW = IT capacity where the source states it, otherwise total capacity. 7 of 7 facilities have a stated capacity; the others are counted as sites only.
Market snapshot
Apatura data centers: key facts
About Apatura
Apatura develops data centre and battery energy storage sites in the UK. Its 2 July 2026 release states a portfolio of nine data centre sites in Scotland's Central Belt with Gate 2-compliant grid connections totalling 2.4 GW, and offices in Edinburgh and York.
- Headquarters
- York, United Kingdom
- Founded
- 2014
- Ownership
- Majority-owned by Felstead Ford Limited (Companies House PSC register, 2023)
- Tracked footprint
- 7 facilities in 1 country
- Website
- apatura.energy
Data center business
- Apatura's community benefit page names five campuses: Larbert (300MW, Falkirk), Ravenscraig (550MW, North Lanarkshire), Wester Hermiston (200MW, City of Edinburgh), Freeport West Lothian (250MW) and Westerhill (300MW, East Dunbartonshire).
- Apatura's 2 July 2026 release states its digital infrastructure portfolio includes nine data centre sites in Scotland's Central Belt with Gate 2-compliant grid connections totalling 2.4 GW, of which six sites are designed for large-scale data centres.
- With offices in Edinburgh and York, Apatura has secured more than 5 GW of grid connections across the UK, most of them in Scotland.
- Companies House lists Apatura DC Ltd (16041291), incorporated 25 October 2024, SIC 63110 Data processing, hosting and related activities, registered at 3rd Floor 1 Ashley Road, Altrincham. UK Companies House
- Apatura states it works with hyperscalers and data centre operators to identify and develop sites, and publishes a Sustainable Data Centre Charter setting principles for its developments.
- Apatura is progressing a portfolio of grid-connected projects with a pipeline of 10.6GW, including 7.25GW in Scotland.
Recent updates
- Apatura published its Community Benefit Commitment naming five data centre campuses with MW figures and annual community benefit amounts.
- Apatura announced Group CFO Tony Wright (from 1 July 2026) and Chief Technology Officer Benny Benford, who leads its AI strategy and data analytics.
- Apatura announced that plans for the 300MW Larbert Data Centre Campus at Glenbervie Business Park were submitted to Falkirk Council; the full application has been accepted and awaits a decision, with first power and operations scheduled for 2028.
- Apatura announced its Ravenscraig proposal for a data centre on 160 acres of the former steelworks, with 550 megawatts of grid connections due online by 2030 and a bid under review for the UK Government's AI Growth Zone initiative.
Company details checked against company and official sources, 10 Nov 2026.
- The largest project in the pipeline is Ravenscraig AI Data Centre by Apatura (550 MW, planned).
- By type, the tracker lists 5 other and 2 hyperscale facilities.
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Apatura development pipeline
Under construction and planned facilities with a stated capacity, largest first. — under construction and 2,100 MW planned in total.
| Project | Location | Status | Type | Capacity |
|---|---|---|---|---|
| Ravenscraig AI Data CentreApatura | Motherwell, United Kingdom | Planned | Hyperscale | 550 MW |
| Apatura ColdstreamApatura | Coldstream, United Kingdom | Planned | Other | 300 MW |
| Apatura Larbert (Glenbervie)Apatura | Larbert, United Kingdom | Planned | Hyperscale | 300 MW |
| Westerhill Data Centre CampusApatura | East Dunbartonshire, United Kingdom | Planned | Other | 300 MW |
| Freeport West Lothian Data Centre CampusApatura | West Lothian, United Kingdom | Planned | Other | 250 MW |
| Apatura CumnockApatura | Cumnock, United Kingdom | Planned | Other | 200 MW |
| Wester Hermiston Data Centre CampusApatura | Edinburgh, United Kingdom | Planned | Other | 200 MW |
Facilities
7 facilities match. Each is checked against its source; source links come with the Excel data.
| Facility | Location | Status | Capacity | Year | Source |
|---|---|---|---|---|---|
| Ravenscraig AI Data CentreHyperscale | Motherwell, United Kingdom | Planned | 550 MW total | — | Trade press |
| Apatura ColdstreamOther | Coldstream, United Kingdom | Planned | 300 MW total | — | Trade press |
| Apatura Larbert (Glenbervie)Hyperscale | Larbert, United Kingdom | Planned | 300 MW total | — | Trade press |
| Westerhill Data Centre CampusOther | East Dunbartonshire, United Kingdom | Planned | 300 MW total | — | Operator / official |
| Freeport West Lothian Data Centre CampusOther | West Lothian, United Kingdom | Planned | 250 MW total | — | Operator / official |
| Apatura CumnockOther | Cumnock, United Kingdom | Planned | 200 MW total | — | Trade press |
| Wester Hermiston Data Centre CampusOther | Edinburgh, United Kingdom | Planned | 200 MW total | — | Operator / official |
Market position
How Apatura compares
Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.
- In United Kingdom, Apatura ranks #1 of 54 tracked operators by capacity, with 24% of the country’s tracked MW.
- United Kingdom has 197 tracked data centers from 54 operators: 1,025 MW operational and 7,741 MW under construction or planned.
- Industrial electricity in United Kingdom costs 234 USD/MWh (2026, latest official figure).
Data center operators in United Kingdom
| Operator | Facilities | Operational MW | Pipeline MW |
|---|---|---|---|
| Elsham Tech Park Ltd (Greystoke) | 1 | — | 1,000 MW |
| QTS | 1 | — | 720 MW |
| ILI Group | 1 | — | 600 MW |
| Ark Data Centres | 10 | 275 MW | 314 MW |
| Humber Tech Park | 1 | — | 386 MW |
| Slough Holdings UK | 1 | — | 300 MW |
| Equinix | 15 | — | 250 MW |
| Virtus Data Centres | 11 | 96.9 MW | 145 MW |
All data centers in United Kingdom Power and policy in United Kingdom
How we build the tracker
- Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
- A second analyst re-opens each source before a facility is published.
- Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
- Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
- Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
- Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
- Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.
Questions
How many data centers does Apatura operate?
DC Market Insights tracks 7 Apatura data center(s) in 1 country as of October 2026: 0 operational, 0 under construction and 7 planned.
Where is Apatura headquartered?
Apatura is headquartered in York, United Kingdom. Ownership: Majority-owned by Felstead Ford Limited (Companies House PSC register, 2023).
Which other companies operate data centers in United Kingdom?
Besides Apatura, the largest operators we track in United Kingdom by capacity are Elsham Tech Park Ltd (Greystoke), QTS, ILI Group, Ark Data Centres and Humber Tech Park. The United Kingdom page lists all 54 operators.
What rules apply to data centers in United Kingdom?
Our Power & Policy Tracker lists 13 government actions on data centers and power in United Kingdom, including 1 restriction(s) and 1 incentive scheme(s) in force.
Where does this data come from?
Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.
What does the MW figure mean?
We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.
How exact are the map locations?
When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.
How often is it updated?
The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.
Can I get the data in Excel?
Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.
Global capacity
How much data center capacity is installed worldwide?
Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.
Need the full list, or a capacity view of one market?
Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.