Proprietary data

Atomdata (Rosatom) Data Centers

Data centers operated by Atomdata (Rosatom) that we have verified: location, status and capacity, each checked against its source.

In short

As of 17 November 2026, DC Market Insights tracks 7 data centers operated by Atomdata (Rosatom) in 1 country, of which 5 are operational. Stated operational capacity is 102 MW.

7Facilities tracked
1Countries
102 MWOperational (5 sites)
—Under construction (0 sites)
—Planned (2 sites)

MW = IT capacity where the source states it, otherwise total capacity. 4 of 7 facilities have a stated capacity; the others are counted as sites only.

Kalininsky data center (Udomlya) · Atomdata (Rosatom) · Udomlya (approximate location)Atomdata Xelent · Atomdata (Rosatom) · Saint Petersburg (approximate location)Atomdata StoreData · Atomdata (Rosatom) · Moscow (approximate location)Atomdata Moscow-2 · Atomdata (Rosatom) · Moscow (approximate location)Atomdata Innopolis · Atomdata (Rosatom) · Innopolis (approximate location)Atomdata Arktika · Atomdata (Rosatom) · Polyarnye Zori (approximate location)Atomdata Xelent-2 · Atomdata (Rosatom) · Saint Petersburg (approximate location)
Operational Under construction Planned Pin = exact site location; dot = city (approximate) Select a country on the map to open its page.

Market snapshot

Atomdata (Rosatom) data centers: key facts

About Atomdata (Rosatom)

ATOMDATA (JSC ATOMDATA) is the competence centre of Russia's Rosatom State Corporation for a geo-distributed, disaster-resilient data center network and for cloud, telecom and integration services. Its own pages say the Rosatom network has five data centers in Moscow, Saint Petersburg, Tver Region and the Republic of Tatarstan with 6,570 rack spaces and more than 93 MW of power (September 2026); two more sites, Xelent-2 in Saint Petersburg and Arktika in Polyarnye Zori, Murmansk Region, are in design.

Headquarters
Moscow, Russia
Founded
2020
Ownership
Rosatom State Corporation group (within JSC RoKIT)
Parent company
Rosatom State Corporation
Tracked footprint
7 facilities in 1 country
Website
atomdata.ru

Data center business

  • Rosatom's deputy director for IT said at the 21st Data Center Forum in Moscow (2-3 September 2026) that the data center at the Kalinin nuclear power plant, with 80 MW of capacity, was launched in 2019, and that demand is moving from 20-50 MW to 100-200 MW per site; Rosatom supports the Ministry of Digital Development's plan for a general scheme of data center locations.
  • ATOMDATA was created in 2020 as the commercial operator of Rosatom's geo-distributed network of disaster-resilient data centers and as a supplier of cloud and infrastructure services. The group now has four companies: JSC ATOMDATA (data center, cloud and telecom services), JSC Atomdata-Center (design, construction and operation of the network and of Rosenergoatom's infrastructure sites), JSC Atomdata-Innopolis (resident of the Innopolis special economic zone, running the Innopolis data center) and JSC Atomdata-Integration (systems integrator).
  • Company timeline: in 2014 Rosatom started the concept of a data center network on power generation sites; in 2015 construction of the data center at the Kalinin nuclear power plant began, taking Rosenergoatom into the data center market; ATOMDATA was set up in March 2020 and Atomdata-Center in October 2020; the Xelent and StoreData data centers were bought in 2021 and the Moscow-2 data center in 2023, with data centers put into commercial operation in 2024.
  • Site figures on the ATOMDATA home page: Kalininsky (Udomlya, Tver Region) 4,800 rack spaces and 48 MW full power, Tier III; Moscow-2 (Moscow) 3,640 rack spaces and 36 MW supplied power, Tier IV; Xelent (Saint Petersburg) 954 rack spaces and 10 MW connection capacity, Tier III; Innopolis (Tatarstan) 1,000 rack spaces and 8 MW in its first phase, Tier III; StoreData (Moscow) 170 rack spaces and 1,600 kVA supplied power, Tier III. The page totals 93 MW of supplied power and 6,570 rack spaces.
  • Moscow-2 holds Tier IV Design and Tier IV Facility certificates (both listed with the date 28 April 2025). PCI DSS certificates are listed for the Xelent and Kalininsky sites (1 August 2025) and for Moscow-2 (16 February 2026), and a GOST R ISO 9001-2015 quality certificate dated 9 September 2026.
  • ATOMDATA sells colocation, public, private, hybrid and critical-information-infrastructure clouds, a cloud for personal data under Federal Law 152-FZ, dedicated servers including GPU servers, network services under Roskomnadzor licences and information security services. It holds a Roskomnadzor telecom licence renewed on 25 June 2025 and valid to 25 June 2030.

Recent updates

  • 6 November 2026: ATOMDATA, part of the JSC RoKIT perimeter, joined Rosatom's stand at Kazan Digital Week 2026 (29-31 October); its director of special projects spoke on AI data center status and on linking computing capacity with power generation.
  • 28 September 2026: ATOMDATA said Rosatom's network has five data centers with 6,570 rack spaces and more than 93 MW; Moscow-2 (3,640 rack spaces, 36 MW) won a 2025 Data Center Awards prize for engineering systems, and CNews Analytics ranked Rosatom third among Russian data center providers by rack spaces in 2025.
  • 18 September 2026: at the 70th IAEA General Conference in Vienna, ATOMDATA presented a concept for a coastal data center next to a floating power unit (PEB-100, two RITM-200M reactors, 100 MW in total), with liquid cooling using seawater and sized for AI workloads.
  • 29 July 2026: at ELECTROFORUM 2026 ATOMDATA said the draft take-or-pay rule for grid capacity was revised with industry input, adding a grace period until a data center reaches design occupancy.
  • 27 July 2026: the ATOMDATA group placed second in TAdviser's ranking of the fastest-growing Russian IT companies and rose from 69th to 35th in TAdviser500; the CEO said new data centers in Moscow and Innopolis are adding revenue as they fill up.
  • 5 February 2026: Oleg Zolotarev was appointed CEO of JSC ATOMDATA on 22 January 2026, to scale the data center business and launch new digital services.

Company details checked against company and official sources, 17 Nov 2026.

  • Its largest operational site is Kalininsky data center (Udomlya) in Udomlya, Russia at 48 MW.
  • 4 of 7 facilities have a capacity stated by their source; the totals above count only those.

Facilities

7 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
Kalininsky data center (Udomlya)Colocation
History
  1. Under construction
  2. Operational
  3. Operational
Udomlya, Russia Operational 48 MW total 2019 Operator / official
Atomdata Moscow-2Colocation
History
  1. Under construction
  2. Operational
  3. Operational
Moscow, Russia Operational 36 MW total — Operator / official
Atomdata XelentColocation Saint Petersburg, Russia Operational 10 MW total — Operator / official
Atomdata InnopolisColocation Innopolis, Russia Operational 8 MW total 2024 Operator / official
Atomdata ArktikaColocation Polyarnye Zori, Russia Planned — — Operator / official
Atomdata StoreDataColocation Moscow, Russia Operational — — Operator / official
Atomdata Xelent-2Colocation Saint Petersburg, Russia Planned — — Operator / official

Market position

How Atomdata (Rosatom) compares

Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.

  • In Russia, Atomdata (Rosatom) ranks #3 of 21 tracked operators by capacity, with 12% of the country’s tracked MW.
  • Russia has 111 tracked data centers from 21 operators: 466 MW operational and 375 MW under construction or planned.
  • Moscow also hosts 10 other tracked data center(s), run by MonArch group of companies, IXcellerate, Rostelecom-DPC (RTK-DPC) and Sber.

Data center operators in Russia

Tracked facilities11121 operators
Operational capacity466 MW375 MW in the pipeline
Atomdata (Rosatom) rank by capacity#3of 21 operators · 12%
Renewable share of generation17.6%2025
OperatorFacilitiesOperational MWPipeline MW
IXcellerate10128 MW74 MW
Yandex563 MW40 MW
MonArch group of companies1—100 MW
Sber329.9 MW60 MW
MTS Web Services (MWS)632 MW20 MW
Rostelecom-DPC (RTK-DPC)2450.2 MW—
Selectel711 MW20 MW
Key Point Group610 MW20 MW

All data centers in Russia Power and policy in Russia

Other data centers in Moscow

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
  • Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers does Atomdata (Rosatom) operate?

DC Market Insights tracks 7 Atomdata (Rosatom) data center(s) in 1 country as of November 2026: 5 operational, 0 under construction and 2 planned.

Where is Atomdata (Rosatom) headquartered?

Atomdata (Rosatom) is headquartered in Moscow, Russia. Ownership: Rosatom State Corporation group (within JSC RoKIT).

Which other companies operate data centers in Russia?

Besides Atomdata (Rosatom), the largest operators we track in Russia by capacity are IXcellerate, Yandex, MonArch group of companies, Sber and MTS Web Services (MWS). The Russia page lists all 21 operators.

What rules apply to data centers in Russia?

Our Power & Policy Tracker lists 10 government actions on data centers and power in Russia, including 2 restriction(s) and 0 incentive scheme(s) in force.

Which other data centers are in Moscow?

Other tracked data centers in Moscow include MonArch Saltykovskaya data center complex (MonArch group of companies), IXcellerate MOS5 (IXcellerate), RTK-DPC Medvedkovo (Rostelecom-DPC (RTK-DPC)) and IXcellerate MOS7 (IXcellerate).

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Global capacity

How much data center capacity is installed worldwide?

Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.