Proprietary data
IXcellerate Data Centers
Data centers operated by IXcellerate that we have verified: location, status and capacity, each checked against its source.
In short
As of 15 November 2026, DC Market Insights tracks 10 data centers operated by IXcellerate in 1 country, of which 5 are operational. Stated operational capacity is 128 MW, with a further 74 MW under construction and — planned. The pipeline is 0.6 times the capacity already operating.
MW = IT capacity where the source states it, otherwise total capacity. 7 of 10 facilities have a stated capacity; the others are counted as sites only.
Market snapshot
IXcellerate data centers: key facts
About IXcellerate
IXcellerate is a Moscow-based operator of commercial colocation data centres. In October 2025 it said its ecosystem had 5 operating data centres and about 10,329 rack spaces by the end of 2025, which it said made it Russia's second-largest commercial operator by capacity. Its sites sit on three campuses: Moscow North in Altufyevo (MOS1-MOS4), Moscow South in Biryulyovo (MOS5 operating, MOS6-MOS8 planned or in build) and Vёshki in Mytishchi (MOS11 and MOS12, 130+ MW planned).
- Headquarters
- Moscow, Russia
- Founded
- 2012
- Tracked footprint
- 10 facilities in 1 country
- Website
- ixcellerate.ru
Data center business
- IXcellerate describes itself as a leading operator of commercial data centres and one of the three largest players in Russia. It offers colocation of server and telecom equipment, with capacity that clients can grow as they need. Its legal entities are IXcellerate LLC (registered 17 Feb 2012, Altufyevskoye shosse 33G, Moscow), IXcellerate 3 LLC and IXcellerate 4 LLC.
- All IXcellerate data centres are designed to meet Tier III reliability. The company says its sites have one of the highest connectivity levels in Russia, with more than 50 telecom operators and several IX platforms, including Eurasia Peering and MSK-IX.
- Moscow North campus (Altufyevo, north Moscow) is where IXcellerate started in 2012. It holds four data centres: MOS1 (6,000 m2, 1,835 racks, 13.7 MW), MOS2 (3,300 m2, 1,580 racks, 13 MW), MOS3 (7,367 m2, 2,400 racks, 30 MW) and MOS4 (1,861 m2, 512 racks, 7 MW design power, technical launch 2022).
- Moscow South campus is IXcellerate's largest project: a site of more than 15 ha on a former brewery in south Moscow, about 30 km from Moscow North. Its data centres together are designed for 300+ MW of power and more than 19,300 racks, with a target PUE of 1.3. MOS5 is live with 18,500 m2, 5,002 rack spaces and 64 MW; MOS7 is designed for 1,720 racks and 34 MW; MOS6 and MOS8 are planned.
- Vёshki is IXcellerate's third campus: 5.5 ha next to Vёshki village (Mytishchi urban district, Moscow Oblast), 6 km in a straight line from Moscow North. It is planned for 7,500 rack spaces and 130+ MW in two data centres. MOS11 is a brownfield conversion of an existing building: 13,037 m2, 2,500 racks, 40 MW, design PUE 1.33, racks of 12 kW and up to 44 kW. MOS12 construction is planned for 2027.
- IXcellerate runs a telehouse inside MOS5 on the South campus: two operator halls with 140 rack spaces and up to 10 kW per rack, three independent cable entries, and a direct link to the MMTS-9 traffic hub 9 km away. Residents named include MSK-IX, CDN-Video, RETN and Rascom; peering is available via MSK-IX, Eurasia Peering IX and Data-IX at up to 400 Gbit/s ports.
- The CEO said average load per rack has passed 12 kW and exceeds 20 kW in some contracts, partly from AI services. IXcellerate designs its next data centres on a hybrid scheme with both air and water-air cooling. In 2025 it passed recertification to ISO 9001, ISO 45001 and ISO 27001, and its staff grew by about a third (about 80 people).
Recent updates
- Cloud provider mt cloud (Movetel) added servers and geo-distributed clusters across IXcellerate's South and North campuses, renting racks of 10-12 kW and above, including GPU configurations, in Tier III data centres.
- ATOL moved its server capacity to MOS5 on the South campus, renting racks of 13 kW each and reserving capacity for growth.
- NETRACK, a client for more than 10 years, put a new batch of equipment into service in MOS3, taking its installation to more than one hundred racks of 10 kW and above, including GPU clusters; NETRACK uses three North campus data centres and has a presence on the South campus.
- Cloud provider Beget opened its first Moscow point of presence in MOS5, renting four racks of up to 15 kW each for a high-performance computing cluster, with options to extend.
- A time capsule was laid on 16 Dec 2025 in MOS7, the data centre under construction on the South campus. In 2025 IXcellerate had launched the last phase of MOS5, whose capacity passed 5,000 rack spaces.
- IXcellerate completed the purchase of a 5.5 ha plot near Vёshki (Mytishchi) and began its third campus, 7,500 racks and 130+ MW, funded by reinvested profit and debt. The first phase of MOS11 (2,500 racks, 40 MW) was planned for summer 2026; MOS12 construction is set for 2027, with phased capacity by 2029-2030. The CEO said the company adds about 2,000 rack spaces a year.
- IXcellerate opened MOS3 on the North campus: 2,400 rack spaces and 30 MW, the fourth and last data centre within the campus's current borders. At launch 1,400 racks were live and 1,000 more were contracted for January 2026; all racks were reserved during construction. Power comes over six 10 kV city feeds; the annual average PUE at full load is below 1.3.
- IXcellerate upgraded its South campus telehouse in MOS5 and raised its capacity to two operator halls with 140 rack spaces, aimed at telecom operators, CDN providers and content companies.
Company details checked against company and official sources, 15 Nov 2026.
- Capacity under construction or planned (74 MW) is 0.6 times the operational base of 128 MW.
- Its largest operational site is IXcellerate MOS5 in Moscow, Russia at 64 MW.
- The largest project in the pipeline is IXcellerate MOS11 (Vёshki) (40 MW, under construction).
- 7 of 10 facilities have a capacity stated by their source; the totals above count only those.
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
IXcellerate development pipeline
Under construction and planned facilities with a stated capacity, largest first. 74 MW under construction and — planned in total.
| Project | Location | Status | Type | Capacity |
|---|---|---|---|---|
| IXcellerate MOS11 (Vёshki)IXcellerate | Mytishchi, Russia | Under construction | Colocation | 40 MW |
| IXcellerate MOS7IXcellerate | Moscow, Russia | Under construction | Colocation | 34 MW |
Facilities
10 facilities match. Each is checked against its source; source links come with the Excel data.
| Facility | Location | Status | Capacity | Year | Source |
|---|---|---|---|---|---|
IXcellerate MOS5Colocation
History
|
Moscow, Russia | Operational | 64 MW total | — | Operator / official |
IXcellerate MOS11 (Vёshki)Colocation
History
|
Mytishchi, Russia | Under construction | 40 MW total | — | Operator / official |
IXcellerate MOS7Colocation
History
|
Moscow, Russia | Under construction | 34 MW total | — | Operator / official |
IXcellerate MOS3Colocation
History
|
Moscow, Russia | Operational | 30 MW total | 2025 | Operator / official |
| IXcellerate MOS1Colocation | Moscow, Russia | Operational | 13.7 MW total | — | Operator / official |
| IXcellerate MOS2Colocation | Moscow, Russia | Operational | 13 MW total | — | Operator / official |
| IXcellerate MOS4Colocation | Moscow, Russia | Operational | 7 MW total | 2022 | Operator / official |
IXcellerate MOS12 (Vёshki)Colocation
History
|
Mytishchi, Russia | Planned | — | — | Operator / official |
| IXcellerate MOS6Colocation | Moscow, Russia | Planned | — | — | Operator / official |
| IXcellerate MOS8Colocation | Moscow, Russia | Planned | — | — | Operator / official |
Market position
How IXcellerate compares
Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.
- In Russia, IXcellerate ranks #1 of 21 tracked operators by capacity, with 24% of the country’s tracked MW.
- Russia has 111 tracked data centers from 21 operators: 466 MW operational and 375 MW under construction or planned.
- Moscow also hosts 10 other tracked data center(s), run by MonArch group of companies, Atomdata (Rosatom), Rostelecom-DPC (RTK-DPC) and Sber.
Data center operators in Russia
| Operator | Facilities | Operational MW | Pipeline MW |
|---|---|---|---|
| Yandex | 5 | 63 MW | 40 MW |
| Atomdata (Rosatom) | 7 | 102 MW | — |
| MonArch group of companies | 1 | — | 100 MW |
| Sber | 3 | 29.9 MW | 60 MW |
| MTS Web Services (MWS) | 6 | 32 MW | 20 MW |
| Rostelecom-DPC (RTK-DPC) | 24 | 50.2 MW | — |
| Selectel | 7 | 11 MW | 20 MW |
| Key Point Group | 6 | 10 MW | 20 MW |
All data centers in Russia Power and policy in Russia
Other data centers in Moscow
- MonArch Saltykovskaya data center complex · MonArch group of companies · Planned · 100 MW
- Atomdata Moscow-2 · Atomdata (Rosatom) · Operational · 36 MW
- RTK-DPC Medvedkovo · Rostelecom-DPC (RTK-DPC) · Operational · 36 MW
- Sber Skolkovo data center · Sber · Operational · 29.9 MW
- Selectel Yurlovsky · Selectel · Under construction · 20 MW
- Selectel Berzarina · Selectel · Operational · 11 MW
- Linx Moscow · Linxdatacenter (Linx) · Operational · 5 MW
- 3data 8 Marta · 3data · Operational
- 3data Altufyevskoye · 3data · Operational
- 3data Bolshaya Polyanka · 3data · Operational
How we build the tracker
- Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
- A second analyst re-opens each source before a facility is published.
- Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
- Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
- Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
- Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
- Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.
Questions
How many data centers does IXcellerate operate?
DC Market Insights tracks 10 IXcellerate data center(s) in 1 country as of November 2026: 5 operational, 2 under construction and 3 planned.
Where is IXcellerate headquartered?
IXcellerate is headquartered in Moscow, Russia.
Which other companies operate data centers in Russia?
Besides IXcellerate, the largest operators we track in Russia by capacity are Yandex, Atomdata (Rosatom), MonArch group of companies, Sber and MTS Web Services (MWS). The Russia page lists all 21 operators.
What rules apply to data centers in Russia?
Our Power & Policy Tracker lists 10 government actions on data centers and power in Russia, including 2 restriction(s) and 0 incentive scheme(s) in force.
Which other data centers are in Moscow?
Other tracked data centers in Moscow include MonArch Saltykovskaya data center complex (MonArch group of companies), Atomdata Moscow-2 (Atomdata (Rosatom)), RTK-DPC Medvedkovo (Rostelecom-DPC (RTK-DPC)) and Sber Skolkovo data center (Sber).
Where does this data come from?
Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.
What does the MW figure mean?
We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.
How exact are the map locations?
When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.
How often is it updated?
The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.
Can I get the data in Excel?
Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.
Global capacity
How much data center capacity is installed worldwide?
Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.
Need the full list, or a capacity view of one market?
Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.