Australia Data Center Infrastructure Market Size, Share & Forecast to 2035
Market at a glance
The Australia Data Center Infrastructure market was worth USD 3,690.0 million in 2025 and is forecast to reach USD 12.48 billion by 2035, growing at a 12.96% CAGR.
Key findings
NEXTDC Triples Contracted Capacity to 740.1 MW and Plans A$5.25-5.75 Billion of FY2027 Capex
Liquid-Cooled AI Halls Take 55% of Spending by 2035
A 67 GW Pipeline Against 27% Grid Connection Use
Upgrading the Installed Base: USD 539.14 million to USD 3.19 billion
What is inside the report
- 01Introduction
- 02Executive Summary
- 03Market Dynamics
- 04Pricing Analysis
- 05Standards and Regulation
- 06Market Segmentation by Component
- 07Market Segmentation by Project Type
- 08Market Segmentation by Data Center Type
- 09Market Segmentation by Rack Density
- 10DC Exclusive: The Sydney and Melbourne Capacity Ledger
- 17chapters
- 2020-2024Historical period
- 2026-2035Forecast period
- —Companies profiled
Segmentation
Full analysis
The Australia Data Center Infrastructure Market is valued at USD 4.73 billion in 2026 and is projected to reach USD 12.48 billion by 2035, up from USD 3.69 billion in 2025, a CAGR of 12.96% from 2025 to 2035 (DC Market Insights estimate). Australia Data Center Infrastructure covers the switchgear, transformers, uninterruptible power supply (UPS) systems, generators, chillers, liquid cooling loops, buildings, racks and monitoring software installed in Australian data centers, but not the servers inside them. Spending here follows the grid queue around Sydney and Melbourne: the Australian Energy Market Operator (AEMO) counted about 5 terawatt-hours (TWh) of data center use in the National Electricity Market in FY2026, with 66% of that load in New South Wales and 30% in Victoria, and expects about 15 TWh by FY2030 in its Step Change case (Source: AEMO 2026 Electricity Statement of Opportunities). NEXTDC, the Sydney-based operator listed on the Australian Securities Exchange (ASX), alone lifted contracted capacity from 244.8 MW to 740.1 MW in FY2026 and guided capital spending of A$5.25 billion to A$5.75 billion for FY2027, so halls already sold are now being fitted out (Source: NEXTDC FY26 results, 27 August 2026). The 2025 receipt is 300 MW of new IT capacity × USD 10.50 million of infrastructure per MW = USD 3.15 billion of new build, plus 1,283.7 MW installed × USD 0.42 million per MW a year = USD 539.14 million of upgrades. Racks above 40 kilowatts (kW) are the fastest segment at 26.31% a year, and Queensland is the fastest region at 18.40% a year because Brisbane sites sit outside the Sydney and Melbourne connection queues.
Australian Data Center Infrastructure in Numbers: How Much Will Australian Sites Spend in 2026?
DC Market Insights values Australia data center infrastructure spending at USD 4.73 billion in 2026, 28.25% above USD 3.69 billion in 2025.
- Market size 2025: USD 3.69 billion; 2026: USD 4.73 billion; 2030: USD 8.66 billion; 2035: USD 12.48 billion.
- CAGR 2025-2035: 12.96% in the base case; the 2035 range runs from USD 9.23 billion (low case, 9.60%) to USD 15.96 billion (high case, 15.78%).
- Infrastructure per new MW in 2025: USD 10.50 million, about A$16.15 million at A$1 = USD 0.65 (DC Market Insights estimate).
- Largest component: electrical infrastructure, USD 1.20 billion or 32.53% of 2025 spending.
- Fastest segment: racks above 40 kW, from USD 664.05 million to USD 6.86 billion, 26.31% a year.
- Largest data center type: hyperscale and cloud campuses, USD 1.77 billion (48.00%).
- Leading region: New South Wales, USD 2.29 billion (62.00%); fastest region: Queensland at 18.40% a year.
- Largest location: Western Sydney (Eastern Creek and Kemps Creek), USD 1.11 billion in 2025.
- Installed IT capacity: about 1,571 MW at the end of 2025, about 3,999 MW in 2030 and about 7,226 MW by 2035 (DC Market Insights estimate).
- Market leaders: Schneider Electric, Vertiv, ABB, Eaton and Siemens supply about 41% of the electrical and cooling equipment value (DC Market Insights estimate).
Executive Summary: How Did Australian Data Center Infrastructure Spending Reach USD 3.69 billion in 2025?
The Australia Data Center Infrastructure Market size was valued at USD 1.33 billion in 2020, reached USD 3.69 billion in 2025, and is anticipated to reach USD 12.48 billion by 2035, at a CAGR of 12.96% during the forecast period.
| Report attribute | Details |
|---|---|
| Historical period | 2020-2024 |
| Base year | 2025 |
| Forecast period | 2026-2035 |
| Market size 2025 | USD 3.69 billion |
| Market size 2026 | USD 4.73 billion |
| CAGR 2025-2035 | 12.96% |
| Market size 2035 | USD 12.48 billion |
Spending rose 22.67% a year from 2020 to 2025 because new IT capacity commissioned each year grew from 120 MW to 300 MW as hyperscale campuses in Western Sydney and Melbourne’s west took most of the new halls. Growth slows to 12.96% a year after 2025 even though additions reach 620 MW a year by 2030, because the base is larger and AEMO’s connection process paces how fast load can arrive: at the end of March 2026, 11 projects with 5.4 gigawatts (GW) of maximum demand were waiting in the transmission connection process (Source: AEMO, 1 June 2026).

What Does Australia Data Center Infrastructure Include, and Where Does It Stop?
Australia Data Center Infrastructure counts USD 3.69 billion of 2025 spending on the physical systems that power, cool, house and monitor IT equipment in Australian data centers.
Included
- Electrical infrastructure: high-voltage connections and on-site substations, transformers, switchgear, UPS systems, batteries, busway, power distribution units and diesel or gas generators.
- Mechanical and cooling infrastructure: chillers, cooling towers, computer room air handlers, coolant distribution units and direct-to-chip piping.
- Building shell and civil works: structure, fire protection, physical security and site works for the data hall.
- Racks, cabling and white-space fit-out; DCIM, monitoring and lifecycle upgrades on the installed base.
Excluded
- Servers, storage and network switches, land, electricity bills, colocation rent and cloud revenue. Data center infrastructure management software sold as a stand-alone product is counted separately in the Australia Data Center Infrastructure Management (DCIM) Market; this edition counts only the monitoring layer installed with each hall.
Five Splits of One Australian Total
Each split (component, project type, data center type, rack density and region) adds up to the same USD 3.69 billion in 2025 and USD 12.48 billion in 2035. The Australia Data Center Market adds IT equipment and services on top of these facility systems.
Why Do Australia Data Center Infrastructure Market Estimates Reach Two or Three Times This Figure?
Published figures for Australian data center infrastructure run from about USD 3 billion to above USD 10 billion a year; DC Market Insights puts 2026 at USD 4.73 billion because it counts facility systems only.
Broader definitions add servers and storage, which can double the total once GPU clusters arrive; they add land and power connection charges paid to network businesses; and some count the full value of a campus in the year it is announced rather than as halls are fitted out. The earlier DC Market Insights edition also counted IT and network hardware and put 2025 at USD 5.81 billion; this edition moves IT equipment out and builds the total from megawatts.
| Element | In this edition | Why |
|---|---|---|
| Power, cooling, shell, racks | Yes: USD 3.15 billion new build 2025 | Installed per MW of new IT capacity |
| Lifecycle upgrades and monitoring | Yes: USD 539.14 million | Recurring spend on the installed base |
| Servers, storage, network gear | No | IT layer, counted in the Australia Data Center Market |
| Land and grid connection charges | No | Paid to landowners and network businesses |
| Electricity and rent | No | Operating costs, not infrastructure |
Small and mid-size enterprises, universities and state agencies are in scope as buyers of enterprise and edge halls; their 2025 spending is USD 737.83 million. Integrated IT and network infrastructure, software-defined systems and managed services sit outside the scope for the reasons above.
Market Drivers: Which Australian Projects and Rules Push Infrastructure Orders Up?
Three forces specific to the Australia data center infrastructure market lift spending from USD 3.69 billion in 2025 to USD 8.66 billion in 2030.
NEXTDC Triples Contracted Capacity to 740.1 MW and Plans A$5.25-5.75 Billion of FY2027 Capex
NEXTDC reported pro forma contracted utilisation of 740.1 MW at the end of FY2026, up from 244.8 MW, against built capacity of 287.9 MW and billing utilisation of 175.0 MW; S4 Sydney was upgraded to 365 MW and M5 Melbourne is planned for up to 1.2 GW (Source: NEXTDC FY26 results, ASX, 27 August 2026). The gap of about 452 MW between contracted and built capacity is infrastructure that still has to be bought: at USD 10.69 million per MW in 2026 it equals about USD 4.83 billion of electrical, cooling and shell work (DC Market Insights estimate). The figures are in the NEXTDC FY26 results release.
CDC’s 555 MW Contract Doubles Its Order Book Above 1 GW
CDC Data Centres, majority-owned by Infratil, reported 671 MW operating, 572 MW under construction and a 2.9 GW pipeline, and signed a 555 MW contract with a US investment-grade customer for delivery in FY2028-29 that takes contracted capacity above 1 GW (Source: Infratil, 5 May 2026). The 572 MW under construction alone represents about USD 6.11 billion of infrastructure at 2026 content per MW (DC Market Insights estimate).
Hyperscaler Programmes: AWS A$20 Billion to 2029 and OpenAI at Eastern Creek
Amazon said on 14 June 2025 that it would invest A$20 billion from 2025 to 2029 to expand Australian data center infrastructure, and NEXTDC and OpenAI signed a non-binding memorandum on 5 December 2025 for an AI campus at S7 Eastern Creek (NEXTDC’s seventh Sydney site) with a first phase expected in the second half of 2027 (Source: Amazon; NEXTDC ASX release). Hyperscale and cloud campuses grow from USD 1.77 billion to USD 7.24 billion, 15.12% a year.
Market Trends: How Are Australian Data Halls Changing Between 2025 and 2035?
Australia data center infrastructure is moving to higher rack density, own-clean-energy commitments and Melbourne capacity, which together lift infrastructure per MW from USD 10.50 million in 2025 to USD 12.55 million in 2035.
Liquid-Cooled AI Halls Take 55% of Spending by 2035
Racks above 40 kW rise from 18.00% of 2025 spending to 55.00% in 2035, 26.31% a year, because GPU clusters such as the planned S7 campus need direct-to-chip cooling and higher-rated power trains (DC Market Insights estimate).
Melbourne’s West Gains Share
AEMO’s Quarterly Energy Dynamics for Q1 2026 reported Victorian data center demand averaging 187 MW, up 94% from 96 MW a year earlier, against 398 MW in New South Wales, up 18% (Source: AEMO, April 2026). Victoria’s share of infrastructure spending rises from 27.00% to 32.80% by 2035.
New Clean Generation as a Condition of Approval
The Commonwealth’s National Expectations for Data Centres and AI Infrastructure of 23 March 2026 ask new facilities to secure new and additional clean generation or storage and minimise water use, which pushes on-site batteries and closed-loop cooling into the 2026-2030 build of USD 28.38 billion (Source: Department of Industry, Science and Resources).
Market Challenges: What Could Slow Australian Data Center Infrastructure Orders?
Grid connection and electricity cost are the two limits on Australian data center infrastructure spending, which DC Market Insights keeps at 620 MW of new IT capacity in 2030 rather than the 67 GW development pipeline.
A 67 GW Pipeline Against 27% Grid Connection Use
AEMO counts 225 data center projects with 67 GW of combined capacity in development, while connection capacity already granted was used at an average of about 27% in FY2026 (Source: AEMO 2026 Electricity Statement of Opportunities). Only a fraction of the pipeline will be built: the model’s 6,040 MW of additions from 2026 to 2035 equal about 9.0% of it.
Wholesale Price Swings
The National Electricity Market average wholesale spot price was A$87 per megawatt-hour (MWh) in Q3 2025 and A$73/MWh in Q1 2026 (Source: AEMO Quarterly Energy Dynamics). A 20 MW hall at 60% load uses about 105 gigawatt-hours a year, so each A$10/MWh move changes its power bill by about A$1.05 million, which tilts design choices toward lower power usage effectiveness (PUE) cooling.
Market Opportunities: Where Can Suppliers Win Australian Data Center Infrastructure Contracts?
The two largest openings for suppliers of Australia data center infrastructure are lifecycle work on the installed base and high-density fit-outs, worth USD 3.19 billion and USD 6.86 billion in 2035.
Upgrading the Installed Base: USD 539.14 million to USD 3.19 billion
Retrofit and lifecycle spending grows 19.47% a year as installed IT capacity rises from about 1,571 MW to about 7,226 MW and halls built in 2015-2020 reach their first UPS and chiller replacement cycle.
Fit-Out of Contracted but Unbuilt Halls
NEXTDC’s 537 MW of development in progress and CDC’s 572 MW under construction add up to about 1,109 MW, close to the 1,350 MW the model adds in 2026-2028; that three-year window is worth USD 14.72 billion of new build.
What Does Data Center Infrastructure Cost per MW in Australia?
Australia data center infrastructure cost USD 10.50 million of power, cooling, shell and fit-out per MW of new IT capacity in 2025, a DC Market Insights model price that rises to USD 12.55 million per MW by 2035.
| Line | 2020 | 2025 | 2030 | 2035 |
|---|---|---|---|---|
| Infrastructure per new MW (USD million) | 9.60 | 10.50 | 11.48 | 12.55 |
| Lifecycle per installed MW a year (USD million) | 0.39 | 0.42 | 0.45 | 0.49 |
| New IT capacity (MW) | 120 | 300 | 620 | 740 |
The 2025 content per MW splits into electrical USD 4.00 million, mechanical and cooling USD 2.90 million, shell and civil USD 2.50 million and racks and fit-out USD 1.10 million. A public anchor: NEXTDC’s FY2026 capital spending of A$3.40 billion (about USD 2.21 billion) equals 54% of the model’s 2026 new-build spending of USD 4.06 billion for the whole country, and it includes land and powered shells that this edition counts only when halls are fitted out (Source: NEXTDC FY26 results).
Which Australian Rules Shape Data Center Infrastructure Design?
Five rule sets shape how Australia’s USD 4.73 billion of 2026 data center infrastructure spending is designed and approved.
- National Expectations for Data Centres and AI Infrastructure (23 March 2026): no upward pressure on energy prices, new clean generation or storage, low water use (Source: Department of Industry, Science and Resources).
- New South Wales (NSW) Data Centre Policy Framework (draft, consultation 17 August to 14 September 2026): projects that meet its energy and water measures are assessed within 75 days; the State Significant Development pipeline holds 19 projects worth A$50.3 billion (Source: Infrastructure NSW).
- National Electricity Rules connection process run by AEMO and the transmission network businesses, which sets when high-voltage switchgear and substations are ordered.
- The Digital Transformation Agency’s Hosting Certification Framework for sites holding government data, which drives security zoning and sovereign-owned enterprise and government halls.
- National Construction Code and AS/NZS 3000 wiring rules for building and electrical work, plus NABERS ratings for data centre energy performance.
Which Australia Data Center Infrastructure Segment Carries the Most Value?
Electrical infrastructure carries the most value in Australia data center infrastructure at USD 1.20 billion in 2025, 32.53% of the market, while racks above 40 kW grow fastest at 26.31% a year.
By Component
Electrical systems lead because every Australian campus above 50 MW needs its own high-voltage substation; DCIM, monitoring and lifecycle grows fastest at 19.47% as the installed base grows.
| Component | 2025 (USD million) | Share 2025 | 2035 (USD million) | CAGR 2025-2035 |
|---|---|---|---|---|
| Electrical Infrastructure | 1,200.00 | 32.53% | 3,538.10 | 11.42% |
| Mechanical and Cooling Infrastructure | 870.00 | 23.58% | 2,565.12 | 11.42% |
| Building Shell and Civil Works | 750.00 | 20.33% | 2,211.31 | 11.42% |
| Racks Cabling and White-Space Fit-Out | 330.00 | 8.95% | 972.98 | 11.42% |
| DCIM Monitoring and Lifecycle Upgrades | 539.14 | 14.61% | 3,193.59 | 19.47% |
By Project Type
New build is 85.39% of 2025 spending; retrofit and lifecycle grows faster at 19.47% a year.
| Project type | 2025 (USD million) | Share 2025 | 2035 (USD million) | CAGR 2025-2035 |
|---|---|---|---|---|
| New Build | 3,150.00 | 85.39% | 9,287.50 | 11.42% |
| Retrofit and Lifecycle | 539.14 | 14.61% | 3,193.59 | 19.47% |
By Data Center Type
Hyperscale and cloud campuses grow 15.12% a year; enterprise and government halls grow only 5.40% as agencies and firms move to colocation and cloud.
| Data center type | 2025 (USD million) | Share 2025 | 2035 (USD million) | CAGR 2025-2035 |
|---|---|---|---|---|
| Hyperscale and Cloud Campuses | 1,770.79 | 48.00% | 7,239.03 | 15.12% |
| Colocation and Wholesale | 1,180.52 | 32.00% | 3,744.33 | 12.24% |
| Enterprise and Government | 516.48 | 14.00% | 873.68 | 5.40% |
| Edge and Telecom | 221.35 | 6.00% | 624.05 | 10.92% |
By Rack Density
Spending on halls below 15 kW per rack stays near USD 1.66 billion a year, while halls above 40 kW reach USD 6.86 billion in 2035.
| Rack density | 2025 (USD million) | Share 2025 | 2035 (USD million) | CAGR 2025-2035 |
|---|---|---|---|---|
| Below 15 kW per Rack | 1,660.11 | 45.00% | 1,747.35 | 0.51% |
| 15 to 40 kW per Rack | 1,364.98 | 37.00% | 3,869.14 | 10.98% |
| Above 40 kW per Rack | 664.05 | 18.00% | 6,864.60 | 26.31% |
DC Exclusive: The Sydney and Melbourne Capacity Ledger, 2,089 MW Built or Building at Three Listed Operators
For Australia data center infrastructure suppliers, DC Market Insights tracks 2,089 MW of capacity that NEXTDC, CDC and Macquarie Technology report as built or under construction, a DC Market Insights model built on 9 inputs from their 2026 filings, and prices the unbuilt part at 2026 infrastructure content per MW.
| Operator and site | Built or operating (MW) | Under construction or in progress (MW) | Infrastructure still to buy (USD million, DC Market Insights estimate) | Source |
|---|---|---|---|---|
| NEXTDC (all sites; S4 Sydney 365 MW, M5 Melbourne up to 1.2 GW planned) | 287.9 | 537.0 | 5,739.99 | NEXTDC FY26 results, 27 Aug 2026 |
| CDC Data Centres (Canberra, Sydney, Melbourne; group totals include New Zealand) | 671.0 | 572.0 | 6,114.11 | Infratil, 5 May 2026 |
| Macquarie Technology (Macquarie Park, IC3 SuperWest 47 MW) | 21.0 | 47.0 | 502.38 | Macquarie Technology ASX, 26 Aug 2026 |
| Total, three operators | 979.9 | 1,156.0 | 12,356.48 | DC Market Insights |
The three operators’ 1,156 MW in progress equals about 86% of the 1,350 MW of new IT capacity the model adds nationally in 2026-2028; the rest comes from AirTrunk, Equinix, Amazon Web Services, Microsoft and smaller operators. Their combined built base (CDC’s group figure includes its Auckland sites) of about 980 MW is about 62% of the 1,571 MW the model counts as installed at the end of 2025. The order book that matters for suppliers is therefore the 1,156 MW in progress, worth about USD 12.36 billion of power, cooling, shell and fit-out.
How Is Data Center Infrastructure Spending Split Across Australia’s States?
New South Wales leads Australia data center infrastructure with USD 2.29 billion in 2025, 62.00% of spending, and Queensland grows fastest at 18.40% a year.
| Region | 2025 (USD million) | Share 2025 | 2035 (USD million) | CAGR 2025-2035 |
|---|---|---|---|---|
| New South Wales | 2,287.27 | 62.00% | 6,365.36 | 10.78% |
| Victoria | 996.07 | 27.00% | 4,093.80 | 15.18% |
| Queensland | 184.46 | 5.00% | 998.49 | 18.40% |
| Western Australia | 166.01 | 4.50% | 748.87 | 16.26% |
| South Australia ACT Tasmania and Northern Territory | 55.34 | 1.50% | 274.58 | 17.37% |
New South Wales
New South Wales spends USD 2.29 billion in 2025 and USD 6.37 billion in 2035, 10.78% a year. Western Sydney holds the largest campuses, NEXTDC S4 at 365 MW and the S7 Eastern Creek AI site among them, and NSW took 66% of FY2026 National Electricity Market data center demand (Source: AEMO). Its share falls from 62.00% to 51.00% because connection queues are longest here.
Victoria
Victoria spends USD 996.07 million in 2025 and USD 4.09 billion in 2035, 15.18% a year. Victorian data center demand averaged 187 MW in Q1 2026, up 94% in a year (Source: AEMO), and NEXTDC plans M5 Melbourne at up to 1.2 GW; Melbourne West becomes the second-largest location.
Queensland
Queensland spends USD 184.46 million in 2025 and USD 998.49 million in 2035, 18.40% a year. Brisbane grows fastest because land and connection points are available outside the Sydney and Melbourne queues; its share rises from 5.00% to 8.00%.
Western Australia
Western Australia spends USD 166.01 million in 2025 and USD 748.87 million in 2035, 16.26% a year. Perth sites run on the separate South West Interconnected System, where AEMO counts 15 more data centers beyond the 162 national total it reported in June 2026 (Source: AEMO).
South Australia ACT Tasmania and Northern Territory
South Australia ACT Tasmania and Northern Territory spends USD 55.34 million in 2025 and USD 274.58 million in 2035, 17.37% a year. Canberra’s sovereign and government halls lead this group; Adelaide, Hobart and Darwin add small edge and subsea-cable landing sites.
Which Australian Locations Lead Data Center Infrastructure Spending?
Western Sydney (Eastern Creek and Kemps Creek) leads Australia data center infrastructure spending with USD 1.11 billion in 2025, and Brisbane is the fastest large location at 18.40% a year.
| Rank | Location | State group | 2025 (USD million) | 2035 (USD million) | CAGR 2025-2035 |
|---|---|---|---|---|---|
| 1 | Western Sydney (Eastern Creek and Kemps Creek) | New South Wales | 1,106.74 | 3,744.33 | 12.96% |
| 2 | Melbourne West (Derrimut and Truganina) | Victoria | 627.15 | 2,970.50 | 16.83% |
| 3 | Macquarie Park | New South Wales | 442.70 | 998.49 | 8.47% |
| 4 | Rest of New South Wales | New South Wales | 405.81 | 998.49 | 9.42% |
| 5 | Sydney Inner South (Alexandria and Mascot) | New South Wales | 332.02 | 624.05 | 6.51% |
| 6 | Melbourne Docklands and Port Melbourne | Victoria | 258.24 | 748.87 | 11.23% |
| 7 | Brisbane | Queensland | 184.46 | 998.49 | 18.40% |
| 8 | Perth | Western Australia | 166.01 | 748.87 | 16.26% |
| 9 | Rest of Victoria | Victoria | 110.67 | 374.43 | 12.96% |
| 10 | Canberra | South Australia ACT Tasmania and Northern Territory | 33.20 | 162.25 | 17.19% |
| 11 | Adelaide | South Australia ACT Tasmania and Northern Territory | 14.76 | 74.89 | 17.63% |
| 12 | Hobart and Darwin | South Australia ACT Tasmania and Northern Territory | 7.38 | 37.44 | 17.63% |
Melbourne West grows 16.83% a year to USD 2.97 billion by 2035, while Sydney Inner South grows only 6.51% because its older urban sites have little room for new high-voltage supply.
Forecast Scenarios: How Far Could Australian Data Center Infrastructure Spending Go by 2035?
DC Market Insights expects Australia data center infrastructure spending of USD 12.48 billion in 2035 in the base case, within a range of USD 9.23 billion to USD 15.96 billion.
| Scenario | New IT MW a year from 2027 | 2035 (USD million) | CAGR 2025-2035 | What has to happen |
|---|---|---|---|---|
| Low | 72% of base | 9,230.09 | 9.60% | Connection queues and the NSW framework slow approvals; fewer AI campuses |
| Base | 450 (2027) to 740 (2035) | 12,481.09 | 12.96% | Contracted NEXTDC and CDC capacity built on time; AEMO Step Change load |
| High | 130% of base | 15,964.31 | 15.78% | S7-class AI campuses multiply and new clean generation keeps pace |
Which Companies Lead the Australia Data Center Infrastructure Market?
Schneider Electric, Vertiv, ABB, Eaton and Siemens supply about 41% of the electrical and cooling equipment value in the Australia data center infrastructure market, a DC Market Insights estimate based on USD 2.07 billion of 2025 electrical and mechanical spending.
- Schneider Electric: switchgear, UPS systems, busway and EcoStruxure monitoring.
- Vertiv: UPS systems, thermal management and coolant distribution units.
- ABB: medium-voltage switchgear and UPS systems.
- Eaton: UPS systems and power distribution.
- Siemens: medium-voltage switchgear and building automation.
- Hitachi Energy: transformers and grid connection equipment.
- Legrand: racks, cabling and power distribution units.
- Cummins: diesel generators.
- Caterpillar: diesel and gas generators.
- Rolls-Royce Power Systems (mtu): standby generators.
- Johnson Controls: chillers and building controls.
- Carrier: chillers and air handlers.
- Trane Technologies: chillers and liquid cooling through LiquidStack.
- Stulz: computer room air conditioning.
- Multiplex: data hall construction.
- Built: data hall construction and fit-out.
On the buyer side, the three listed operators in the DC Exclusive ledger report about 980 MW built, roughly 62% of the national installed base (DC Market Insights estimate).
Which Australian Data Center Projects Moved in 2025 and 2026?
Seven dated events from June 2025 to August 2026 shape the USD 4.73 billion DC Market Insights expects for Australia data center infrastructure in 2026.
- In June 2025, Amazon announced A$20 billion of investment from 2025 to 2029 to expand its Australian data center infrastructure (Source: Amazon).
- In December 2025, NEXTDC and OpenAI signed a non-binding memorandum for an AI campus at S7 Eastern Creek, first phase expected in the second half of 2027 (Source: NEXTDC ASX release).
- In March 2026, the Commonwealth published its National Expectations for Data Centres and AI Infrastructure (Source: Department of Industry, Science and Resources).
- In May 2026, CDC signed a 555 MW contract with a US customer, taking contracted capacity above 1 GW (Source: Infratil).
- In June 2026, AEMO reported 11 large data center projects with 5.4 GW of maximum demand in the connection process (Source: AEMO).
- In August 2026, NEXTDC reported 740.1 MW of contracted utilisation and Macquarie Technology set IC3 SuperWest at 47 MW (Source: NEXTDC; Macquarie Technology ASX releases).
- In August 2026, the NSW Government released its draft Data Centre Policy Framework with a 75-day assessment commitment (Source: Infrastructure NSW).
Key Takeaways: Four Australian Data Center Infrastructure Numbers to Watch Through 2035
- Australia data center infrastructure reaches USD 4.73 billion in 2026, up 28.25%, because NEXTDC and CDC are fitting out capacity they have already contracted.
- Racks above 40 kW reach 55.00% of spending by 2035 because AI campuses such as S7 Eastern Creek need liquid cooling.
- Queensland grows fastest at 18.40% a year because Brisbane avoids the Sydney and Melbourne connection queues.
- Lifecycle spending rises to USD 3.19 billion by 2035 because the installed base grows to about 7,226 MW.
Methodology: How the Model Builds Australian Data Center Infrastructure From Megawatts
DC Market Insights built the Australia Data Center Infrastructure Market bottom up from new and installed IT capacity, reaching USD 3.69 billion for 2025 from 12 model inputs.
New-build spending equals new IT capacity commissioned (120 MW in 2020, 300 MW in 2025, 620 MW in 2030, 740 MW in 2035) multiplied by infrastructure content of USD 10.50 million per MW in 2025, rising 1.8% a year: USD 3.15 billion. Lifecycle spending equals the prior-year installed base (1,283.7 MW for 2025, 1% retired each year) multiplied by USD 0.42 million per MW, rising 1.5% a year: USD 539.14 million. Shares by data center type, rack density, state and location move in straight lines from 2025 to 2035 and add up to the total in every year.
Three bound checks hold. First ceiling: about 3,999 MW installed in 2030 at 35% average load and a PUE of 1.33 uses about 16.3 TWh, close to AEMO’s 15 TWh for the National Electricity Market in FY2030 plus Western Australia; 7,226 MW in 2035 uses about 31.3 TWh, below AEMO’s 34 TWh for FY2036. Second ceiling: New South Wales new build from 2026 to 2030 totals about USD 16.6 billion, below the A$50.3 billion (about USD 32.7 billion) of the 19 projects in the NSW State Significant Development pipeline, which also include land and IT. Floor: NEXTDC, CDC and Macquarie Technology report about 1,156 MW in progress, below the model’s 1,350 MW of national additions in 2026-2028. Related reading: the Australia Data Center Cooling Market, the Australia AI Data Center Market and the DC Market Insights research methodology.
Table of contents
- 01Introduction
- 1.1Market Definition and Scope
- 1.2Included and Excluded Systems
- 1.3Why Estimates Differ
- 02Executive Summary
- 2.1Market Snapshot, 2025, 2026 and 2035
- 2.2Key Market Statistics
- 2.3Market Size 2020-2035 (Figure 1)
- 03Market Dynamics
- 3.1NEXTDC Contracted Capacity of 740.1 MW
- 3.2CDC 555 MW Contract
- 3.3AWS AU$20 Billion and OpenAI at Eastern Creek
- 3.4Liquid-Cooled AI Halls
- 3.5Melbourne's West Gains Share
- 3.6New Clean Generation as a Condition of Approval
- 3.7A 67 GW Pipeline Against 27% Grid Connection Use
- 3.8Wholesale Price Swings
- 3.9Upgrading the Installed Base
- 3.10Fit-Out of Contracted but Unbuilt Halls
- 04Pricing Analysis
- 4.1Infrastructure Cost per MW, 2020-2035
- 05Standards and Regulation
- 5.1National Expectations for Data Centres and AI Infrastructure
- 5.2NSW Data Centre Policy Framework
- 5.3AEMO Connection Process
- 5.4Hosting Certification Framework
- 5.5National Construction Code and NABERS
- 06Market Segmentation by Component
- 6.1Electrical Infrastructure
- 6.2Mechanical and Cooling Infrastructure
- 6.3Building Shell and Civil Works
- 6.4Racks Cabling and White-Space Fit-Out
- 6.5DCIM Monitoring and Lifecycle Upgrades
- 07Market Segmentation by Project Type
- 7.1New Build
- 7.2Retrofit and Lifecycle
- 08Market Segmentation by Data Center Type
- 8.1Hyperscale and Cloud Campuses
- 8.2Colocation and Wholesale
- 8.3Enterprise and Government
- 8.4Edge and Telecom
- 09Market Segmentation by Rack Density
- 9.1Below 15 kW per Rack
- 9.215 to 40 kW per Rack
- 9.3Above 40 kW per Rack
- 10DC Exclusive: The Sydney and Melbourne Capacity Ledger
- 10.1NEXTDC
- 10.2CDC Data Centres
- 10.3Macquarie Technology
- 11Regional Insights
- 11.1New South Wales
- 11.2Victoria
- 11.3Queensland
- 11.4Western Australia
- 11.5South Australia ACT Tasmania and Northern Territory
- 12Location Analysis
- 12.1Western Sydney (Eastern Creek and Kemps Creek)
- 12.2Melbourne West (Derrimut and Truganina)
- 12.3Macquarie Park
- 12.4Rest of New South Wales
- 12.5Sydney Inner South (Alexandria and Mascot)
- 12.6Melbourne Docklands and Port Melbourne
- 12.7Brisbane
- 12.8Perth
- 12.9Rest of Victoria
- 12.10Canberra
- 12.11Adelaide
- 12.12Hobart and Darwin
- 13Forecast Scenarios
- 13.1Low Case
- 13.2Base Case
- 13.3High Case
- 14Competitive Insights
- 14.1Schneider Electric
- 14.2Vertiv
- 14.3ABB
- 14.4Eaton
- 14.5Siemens
- 14.6Hitachi Energy
- 14.7Legrand
- 14.8Cummins
- 14.9Caterpillar
- 14.10Rolls-Royce Power Systems (mtu)
- 14.11Johnson Controls
- 14.12Carrier
- 14.13Trane Technologies
- 14.14Stulz
- 14.15Multiplex
- 14.16Built
- 15Recent Developments
- 15.1Amazon AU$20 Billion Plan (June 2025)
- 15.2NEXTDC and OpenAI S7 Memorandum (December 2025)
- 15.3National Expectations (March 2026)
- 15.4CDC 555 MW Contract (May 2026)
- 15.5AEMO Connection Pipeline (June 2026)
- 15.6NEXTDC and Macquarie Technology Results (August 2026)
- 15.7NSW Draft Data Centre Policy Framework (August 2026)
- 16Key Takeaways
- 16.1Four Numbers to Watch Through 2035
- 17Research Methodology
- 17.1Model Inputs and Build Receipt
- 17.2Bound Checks
- Fig. 1Australia Data Center Infrastructure Market Size, 2020-2035
- Table 1Report Attributes
- Table 2Scope Comparison
- Table 3Infrastructure Cost per MW, 2020-2035
- Table 4Segmentation by Component
- Table 5Segmentation by Project Type
- Table 6Segmentation by Data Center Type
- Table 7Segmentation by Rack Density
- Table 8Sydney and Melbourne Capacity Ledger
- Table 9Spending by Region
- Table 10Top 12 Locations
- Table 11Forecast Scenarios, 2035
About this report
Written by Amit Jain and reviewed by Deepti Agrawal, Senior Editor, Research. Figures are built top-down and bottom-up and reconciled before publication, with 2025 as the base year.
Read our methodologyHow we built this
- Historical period2020-2024
- Base year2025
- Forecast period2026-2035
- Sizing approachTop-down + bottom-up
Need more than the report?
Advisory on this market
Due diligence, site selection and market entry work, by the analysts who wrote this report.
See consulting servicesFrequently asked questions
USD 4.73 billion in 2026, up 28.25% from USD 3.69 billion in 2025, according to DC Market Insights estimates. The market is projected to reach USD 12.48 billion by 2035, a CAGR of 12.96% from 2025.
12.96% a year from 2025 to 2035, after 22.67% a year from 2020 to 2025. New IT capacity added each year rises from 300 MW in 2025 to 620 MW in 2030 and 740 MW in 2035.
USD 10.50 million per MW of new IT capacity in 2025, about A$16.15 million: electrical USD 4.00 million, mechanical and cooling USD 2.90 million, shell USD 2.50 million and racks and fit-out USD 1.10 million (DC Market Insights estimate).
Racks above 40 kW, at 26.31% a year, from USD 664.05 million in 2025 to USD 6.86 billion in 2035, because AI campuses need liquid cooling. Electrical infrastructure is the largest component at USD 1.20 billion.
New South Wales, with USD 2.29 billion or 62.00% of 2025 spending, led by Western Sydney. Queensland grows fastest at 18.40% a year and Victoria rises from 27.00% to 32.80% of spending by 2035.
About 1,571 MW of IT capacity at the end of 2025, rising to about 3,999 MW in 2030 and 7,226 MW by 2035 (DC Market Insights estimate). AEMO counted about 5 TWh of data center use in the National Electricity Market in FY2026.
About 1,156 MW at three listed operators: NEXTDC 537 MW in progress, CDC 572 MW under construction and Macquarie Technology 47 MW. At 2026 content per MW that is about USD 12.36 billion of infrastructure still to buy (DC Market Insights estimate).
Schneider Electric, Vertiv, ABB, Eaton and Siemens supply about 41% of electrical and cooling equipment value (DC Market Insights estimate). Hitachi Energy, Legrand, Cummins, Caterpillar, Johnson Controls, Carrier and Trane Technologies follow.
Four main sets: the National Expectations for Data Centres and AI Infrastructure of 23 March 2026, the draft NSW Data Centre Policy Framework of August 2026 with 75-day assessment, AEMO’s grid connection process and the Hosting Certification Framework for government data.
USD 4.73 billion in 2026 counts facility systems only: power, cooling, shell, racks and lifecycle work. Estimates that add servers, storage, land or grid connection charges, or count whole campuses when announced, come out two to three times higher.
Get this report
How do I get the full report?
Request a quote; we reply by email within one business day.
How and when will I receive the report?
By email, within 24-48 business hours of payment.
How can I pay?
Once you accept the quote, we email you a secure payment link.
Can I see a sample first?
Yes. Request a free sample and we will email it to you.
Can the report be tailored to my needs?
Yes. We can add countries, segments or data cuts. Talk to an analyst about the scope you need.
Can I get an invoice or pay against a purchase order?
Write to sales@dcmarketinsights.com and our team will help.
