Data pack · Updated 12 November 2026
How much data center capacity Mexico has installed, how it compares with the rest of Latin America, and what our trackers show about its sites, operators, deals and rules.
Mexico data center capacity at a glance
Mexico had about 0.4 GW of installed data center capacity (IT load) at the end of 2025, by our estimate. That is about 17% of the capacity in Latin America and puts Mexico at number 27 of the 33 countries in our global model. Our Data Center Tracker holds 55 sites in Mexico run by 21 operators: 45 operational, 3 under construction and 7 planned. Our trackers also hold 1 verified deals and 14 government measures in force for the country.
Installed capacity is IT load, the power available to servers, storage and network. The country figure comes from the same model as the global and regional totals and is benchmarked against dated public figures. Site figures below are what each source states, often a campus’s full build-out, so they are not the same measure.
What our tracker holds for Mexico
Largest tracked sites
| Site | Operator | City | Status | MW |
|---|---|---|---|---|
| CloudHQ Querétaro campus | CloudHQ | Querétaro | Planned | 900 IT |
| DC QR03 | ODATA | El Marqués | Under construction | 300 IT |
| KIO QRO3 | KIO Networks | El Marqués | Planned | 100 |
| DC QR01 | ODATA | Querétaro | Operational | 32 |
| Querétaro 2 (QRO2) | Ascenty | Querétaro | Operational | 31 |
| DC QR02 | ODATA | Querétaro | Operational | 30 |
| Querétaro 1 (QRO1) | Ascenty | Colón | Operational | 25 |
| Querétaro 3 (QRO3) | Ascenty | Querétaro | Operational | 25 |
| DC QR04 | ODATA | San Miguel de Allende | Operational | 12 IT |
| KIO QRO2 | KIO Networks | El Marqués | Operational | 12 IT |
Where the sites are
| City | Sites | Operators | MW stated, live |
|---|---|---|---|
| Querétaro | 15 | 11 | 126 |
| Mexico City | 8 | 5 | n/a |
| Monterrey | 5 | 5 | n/a |
| El Marqués | 4 | 2 | 19 |
| Tepotzotlán | 2 | 1 | 5 |
| Huixquilucan | 2 | 2 | n/a |
| Atizapán de Zaragoza | 2 | 1 | n/a |
| Tultitlán | 2 | 2 | n/a |
Cities with the most tracked sites. MW only where a source states it.
Who runs them
| Operator | Sites | MW live | MW pipeline |
|---|---|---|---|
| CloudHQ | 1 | n/a | 900 |
| ODATA | 4 | 74 | 300 |
| KIO Networks | 14 | 19 | 104 |
| Ascenty | 3 | 81 | n/a |
| TERRANOVA | 1 | 8 | n/a |
| Scala Data Centers | 6 | 5 | 2 |
| Telmex | 7 | n/a | n/a |
| Equinix | 4 | n/a | n/a |
Operators ranked by MW stated at their tracked sites in Mexico.
Power context
- Grid emission factor, 20230.438 kgCO2/kWh · Gobierno de México, AVISO Factor de Emisión del Sistema Eléctrico Nacional 2023 (Aviso_FE-SEN23)
Rules in force
- TariffTarifas finales del Suministro Básico como tarifas máximas
- RegulationSENER Single Self-Supply Window (Ventanilla Única de Autoconsumo): fixed deadlines for 0.7 to 20 MW self-supply projects
- RegulationCogeneration rules: one study request; new plant and load centre studied on the larger of capacity or demand
- RegulationCNE rules for batteries at load centres (SAEE-CC): connection studies and demand limits
- GridCNE model interconnection and connection contract: load centres of 1 MW or more must sign; developer pays for works and posts guarantees
From government sources. Power and policy in Mexico
Recent deals
- Aug 2026 · Land / campusQRO3 data center complex expansion, El Marqués Industrial Park, Querétaro, 100 MW, USD 1.3 bn
Other countries in Latin America
Installed capacity, end 2025, DC Market Insights estimate. All countries and regions
Mexico in the full data pack
By year to 2035
Installed MW for Mexico from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases.
Leading hubs
Live and pipeline MW for the main metro markets, with the basis of each figure.
Every tracked site
The full site list with operator, location, status, MW and source, refreshed from our tracker.
Related research on Mexico
Frequently asked questions
How much data center capacity does Mexico have?
We estimate about 0.4 GW of installed data center capacity (IT load) in Mexico at the end of 2025, about 17% of Latin America and number 27 of the 33 countries in our model. This is a DC Market Insights estimate, benchmarked against dated public figures.
How many data centers are there in Mexico?
Our Data Center Tracker lists 55 sites in Mexico (45 operational, 3 under construction, 7 planned), run by 21 operators. Each site is verified from operator, planning or utility sources; the list grows as new sites are confirmed.
Which companies have the most tracked data center capacity in Mexico?
By capacity stated at their sites (operational plus pipeline), the largest in our tracker are CloudHQ, ODATA, KIO Networks. Site capacity is counted only where a source states it.
What rules apply to data centers in Mexico?
Our Power and Policy Tracker lists 14 government measures in force for Mexico, such as incentives, tariffs, grid rules and national plans, each linked to the official source.
How will Mexico data center capacity grow to 2035?
The full data pack gives installed capacity for Mexico by year from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases and the main metro hubs.