Data Center Power & Policy in Mexico

Every government action on data centers and power in Mexico that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.

In short

As of 15 November 2026, DC Market Insights tracks 17 government actions on data centers and power in Mexico, 14 of them in force. We have found no moratorium or restriction on new data centers in force in Mexico.

17Actions tracked
14In force
—Industrial power price
—Renewable share of generation

Market snapshot

Mexico power and policy: key facts

  • Grid emission factor: 0.44 kgCO2/kWh (2023). Rank 14 of 42 tracked countries, highest first.
  • Latest change: Initiative to reform the Querétaro State Environmental Code on the installation of data centres (Congress of the State of Querétaro (LXI Legislatura), 5 Nov 2026).
  • By type: 8 regulation, 7 power tariff, 1 grid access and 1 renewable energy.

Power indicators for Mexico

Latest official figure for each indicator, with earlier years where we have them.

Grid emission factor 0.44 kgCO2/kWh 2023 · Factor de Emisión del Sistema Eléctrico Nacional 2023: 0.438 tCO2e/MWh (= 0.438 kgCO2e/kWh), official notice for emission reporting (RENE), published on gob.mx (CRE electricity unit). Same value as 2022. A 2024 factor of 0.444 tCO2/MWh is reported by cons Gobierno de México, AVISO Factor de Emisión del Sistema Eléctrico Nacional 2023 (Aviso_FE-SEN23)

In force now in Mexico

Grid access (1)

  • Grid accessIn force

    CNE model interconnection and connection contract: load centres of 1 MW or more must sign; developer pays for works and posts guarantees

    CNE agreement issuing the model contract for interconnection, connection or both to the National Transmission Grid or the General Distribution Networks for power plants, storage systems and load centres (centros de carga), replacing the CRE models. It applies to load centres on the transmission grid that take part in the wholesale market (qualified users, registered self-supply users) and to distribution-connected load centres with contracted load of 1 MW or more. The applicant bears the cost of metering and specific works and must post guarantees; CENACE instructs signing (within 10 business days) and physical connection follows within 72 hours of the order. Signed 2 March 2026 (Comité Técnico agreement CT/2.SE/2-2026); published in the DOF on 17 March 2026 and in force from the next business day, per Greenberg Traurig.

    1 MW Contracted load threshold for distribution-connected load centres. DOF date and entry into force from Greenberg Traurig (17 Mar 2026, next business day); the official text read gives only the signing date (2 Mar 2026).

    Comisión Nacional de Energía (CNE); CENACE · Effective 18 Mar 2026 · DOF (SIDOF), ACUERDO por el que la Comisión Nacional de Energía expide el modelo de contrato para la interconexión, conexión o ambas

Power tariff (6)

  • Power tariffIn force

    Tarifas finales del Suministro Básico como tarifas máximas

    The final Basic Supply tariffs notified by the CNE are maximums. CFE may agree conventional arrangements or tariff discounts with its customers under criteria set by the CNE and validated by the Energy Ministry (SENER) through general administrative provisions. Such agreements must follow principles of generality and accessibility, and the contracts or discounts must be registered with the CNE.

    Comisión Nacional de Energía (CNE); Secretaría de Energía (SENER) · Effective 1 Sep 2026 · Diario Oficial de la Federación (SIDOF) – CNE oficio F00.06.UE/2433/2026

  • Power tariffIn force

    Saldo del diferencial de costos de generación por acreditar a la CFE

    The CNE recognised a balance of generation cost differentials that CFE has reported for January 2021 to October 2025 and still has to recover. Under the 2026 agreement, this balance and any differentials arising in 2026 can be spread over up to 24 months in the final tariffs to keep tariffs stable. Any balance left at the end of 2026 may be carried into the 2027 tariffs.

    34,428,541,687.45 $ (MXN pesos) Can be spread over up to 24 months, per the same agreement.

    Comisión Nacional de Energía (CNE) · Effective 1 Jan 2026 · Diario Oficial de la Federación (SIDOF) – Acuerdo CT/11.SE/8-2025, Comisión Nacional de Energía

  • Power tariffIn force

    Cargo por Servicios Conexos no incluidos en el MEM 2026

    For 2026 the CNE set a per-kWh charge for ancillary services not included in the wholesale electricity market. It applies to all tariff categories and divisions, and stays in place until the general administrative provisions under article 158 of the Electricity Sector Law are issued.

    0.01 $/kWh (MXN) Applies until provisions under art. 158 fr. V of the LSE are issued.

    Comisión Nacional de Energía (CNE) · Effective 1 Jan 2026 · Diario Oficial de la Federación (SIDOF) – Acuerdo CT/11.SE/8-2025, Comisión Nacional de Energía

  • Power tariffIn force

    Cargo de transmisión para la categoría DIT (Demanda Industrial en Transmisión)

    The DIT category (industrial demand at transmission level) pays the regulated transmission charge for voltages of 220 kV or more. All other categories, including GDMTH and DIST (sub-transmission), pay the charge for voltages below 220 kV. DIT and DIST are billed on hourly energy charges and a capacity charge on demand.

    220 kV

    Comisión Nacional de Energía (CNE) · Effective 1 Jan 2026 · Ends 31 Dec 2026 · Diario Oficial de la Federación (SIDOF) – Acuerdo CT/11.SE/8-2025, Comisión Nacional de Energía

  • Power tariffIn force

    Categoría tarifaria GDMTH – Gran Demanda en Media Tensión Horaria

    Under the 2026 tariff structure, the GDMTH category covers medium-voltage customers with hourly metering and demand of 100 kW-month or more. It replaces the former CFE categories HM and HMC. Energy is charged by time-of-use period (base, intermediate, peak), and capacity and distribution are charged on demand.

    100 kW-mes Threshold as written in Table 1 of the agreement.

    Comisión Nacional de Energía (CNE) · Effective 1 Jan 2026 · Ends 31 Dec 2026 · Diario Oficial de la Federación (SIDOF) – Acuerdo CT/11.SE/8-2025, Comisión Nacional de Energía

  • Power tariffIn force

    Acuerdo por el que la CNE autoriza el cálculo y ajuste de las tarifas finales del Suministro Básico de la CFE, 1 enero – 31 diciembre 2026

    The National Energy Commission (CNE) set the methodology for CFE's regulated final Basic Supply tariffs (TFSB) for 2026. The tariffs are built from regulated transmission, distribution, CFE supplier operation and CENACE operation tariffs, plus a non-MEM ancillary services charge and generation charges (energy and capacity). The CNE sets the generation charges every month from CFE's reported generation costs, using a constant relative-price scheme. The agreement covers the industrial categories GDMTH, DIST and DIT.

    Comisión Nacional de Energía (CNE) · Effective 1 Jan 2026 · Ends 31 Dec 2026 · Diario Oficial de la Federación (SIDOF) – Acuerdo CT/11.SE/8-2025, Comisión Nacional de Energía

Renewable energy (1)

  • Renewable energyIn force

    Energy Sector Programme 2025-2030 (PROSENER): clean energy to reach 38% of power generation by 2030

    The Programa Sectorial de Energía 2025-2030, published in the DOF on 22 December 2025, sets the goal that clean energy reaches 38% of national power generation by 2030 (the National Development Plan gives a 38% to 45% range). It records that clean energy made only 24.32% of generation in 2024, short of the earlier 35% goal. Clean energy in Mexico includes renewables plus nuclear and efficient cogeneration.

    38 % of generation (clean energy, 2030 goal 2024 baseline 24.32% clean energy (not renewables only).

    Secretaría de Energía (SENER) · Ends 31 Dec 2030 · DOF (SIDOF), Programa Sectorial de Energía 2025-2030 (22-12-2025)

Regulation (6)

  • RegulationIn force

    SENER Single Self-Supply Window (Ventanilla Única de Autoconsumo): fixed deadlines for 0.7 to 20 MW self-supply projects

    SENER guidelines (signed 4 May 2026) create the Ventanilla Única de Autoconsumo inside the Ventanilla Energía platform for priority, fast and parallel handling of self-supply procedures by SENER, CENACE, CFE and CNE, with one shared file. Deadlines in business days: SENER resolves the MISSE in 20; CENACE self-supply studies in 30 (rapid study 10); CNE generation permit in 30; CFE signs the interconnection and connection contract 10 days after CENACE's instruction; CENACE commissioning tests within 60. It covers isolated or interconnected projects of 0.7 to 20 MW; larger projects follow the ordinary process. In force the day after DOF publication. The SENER/CNE study on integrating data centres (May 2026) points to this route for data centres.

    20 MW Upper capacity limit for the single window (lower limit 0.7 MW). Date = signing date; DOF publication date not read.

    Secretaría de Energía (SENER) · DOF (SIDOF), ACUERDO por el que se emiten los Lineamientos para la implementación de la Ventanilla Única de Autoconsumo

  • RegulationIn force

    Cogeneration rules: one study request; new plant and load centre studied on the larger of capacity or demand

    These rules apply until the Interconnection and Connection Manual is amended. For wholesale-market cogeneration, the applicant files a single study request with CENACE. Existing load centres or plants get a Rapid Study first. Where both the plant and the load centre are new, study scope, timing and fees are set using the larger of the plant's net capacity and the load centre's electrical demand. CENACE studies cover the load at maximum demand together with the plant at maximum net capacity, and each running without the other.

    Comisión Nacional de Energía (CNE) · Diario Oficial de la Federación, 16 April 2026: Acuerdo CNE, DACG para la generación de energía eléctrica en la modalidad de Cogeneración (copy on CENACE site)

  • RegulationIn force

    CNE rules for batteries at load centres (SAEE-CC): connection studies and demand limits

    Storage installed at a load centre counts as part of the load centre and needs no storage permit. Its power counts toward the contracted or maximum demand, and the power drawn from the grid may not exceed that value. Stored energy is for on-site use only and may not be injected into the grid or sold. New load centres with storage need an Impact Study and a Facilities Study. For existing load centres, adding storage is a technical modification handled by CENACE through a Rapid Study. The rules replace Acuerdo A/113/2024.

    Comisión Nacional de Energía (CNE) · Diario Oficial de la Federación, 16 April 2026: Acuerdo CNE, DACG para la integración de SAEE al SEN (copy on CENACE site)

  • RegulationIn force

    New Federal Law on Protection of Personal Data held by Private Parties (2025): transfers allowed, no data localisation

    A new LFPDPPP was published in the DOF on 20 March 2025 and took effect on 21 March 2025, replacing the 2010 law. Supervision, verification and sanctions moved from the dissolved INAI to the Secretaría Anticorrupción y Buen Gobierno. Chapter V (Art. 36 onward) allows national and international transfers of personal data, in some cases without the data subject's consent; the law sets no requirement to store data inside Mexico.

    Congress of the Union; Secretaría Anticorrupción y Buen Gobierno · Effective 21 Mar 2025 · Cámara de Diputados, Ley Federal de Protección de Datos Personales en Posesión de los Particulares (DOF 20-03-2025)

  • RegulationIn force

    Self-supply (autoconsumo) regime: own power plants of 0.7 MW or more, simplified permit for 0.7 to 20 MW interconnected plants

    Articles 30 to 32 of the Ley del Sector Eléctrico define self-supply as production from a power plant of 0.7 MW or more used on site. It can be isolated (no grid connection, all output used in a private network) or interconnected (grid-connected; surplus can be delivered free or sold only to the state utility, with a generation permit and interconnection contract, and intermittent plants need their own storage or must pay for backup). Interconnected plants of 0.7 to 20 MW get a simplified CNE permit procedure; renewables are preferred. This is the main legal route for data centres that want on-site generation while grid connections are delayed.

    0.7 MW Minimum plant capacity for autoconsumo (generation permit required); simplified permit for interconnected plants of 0.7 to 20 MW.

    Comisión Nacional de Energía (CNE); Secretaría de Energía (SENER) · Cámara de Diputados, Ley del Sector Eléctrico (DOF 18-03-2025), Arts. 30-32

  • RegulationIn force

    Electricity Sector Law (LSE): the State must keep at least 54% of the energy injected into the grid

    The Ley del Sector Eléctrico, published in the DOF on 18 March 2025, replaced the 2014 Electricity Industry Law. Article 12 sets the 'prevalence' of the State: state-owned CFE must keep at least 54% of the average energy injected into the national grid over a calendar year, with private generation allowed for the rest under planning set by the Energy Ministry (SENER). The law also created the self-supply (autoconsumo) regime used by data centres that build their own plants (see PP-MX-002) and moved permits to the new Comisión Nacional de Energía (CNE), which replaced the CRE.

    54 % of energy injected into the grid (Stat Annual average; measurement rules set by the regulations. Entry-into-force date not read from the transitory articles.

    Congress of the Union; Secretaría de Energía (SENER); Comisión Nacional de Energía (CNE) · Cámara de Diputados, Ley del Sector Eléctrico (DOF 18-03-2025), Art. 12

Announced and proposed

Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.

  • RegulationProposed

    Initiative to reform the Querétaro State Environmental Code on the installation of data centres

    A citizen initiative drafted by the Colectivo Voceras de la Madre Tierra. It was presented with local deputies Eric Silva Hernández and Claudia Díaz Gayou. It would give data centres a legal status in the State Environmental Code and require an environmental impact assessment for each one, because Sedesu does not currently demand one. It would also require an early, mandatory public consultation before investments are approved, a public inventory of data centres listing the water and electricity they use, and a mandatory annual report. Under the current law the annual operating report (cédula de operación anual) is voluntary.

    Congress of the State of Querétaro (LXI Legislatura) · LXI Legislatura Querétaro

  • RegulationAnnounced

    Mandatory water consumption reporting for data centres in Querétaro

    The Querétaro Secretaría de Desarrollo Sustentable (Sedesu) said data centres will have to report their water use from 2027. Procedures are being changed during the current year, with a test measurement and preliminary work with the Mexican data centre association. Data centres are classed as service companies and so currently have no duty to report water use, unlike manufacturers. Sedesu said water volumes are allocated by Conagua, not by the state.

    Secretaría de Desarrollo Sustentable del Estado de Querétaro (Sedesu)

Timeline of data center and power policy in Mexico

DateActionTypeStatusAuthority
5 Nov 2026Initiative to reform the Querétaro State Environmental Code on the installation of data centresRegulationProposedCongress of the State of Querétaro (LXI Legislatura)
15 Oct 2026Mandatory water consumption reporting for data centres in QuerétaroRegulationAnnouncedSecretaría de Desarrollo Sustentable del Estado de Querétaro (Sedesu)
31 Aug 2026Tarifas finales del Suministro Básico como tarifas máximasPower tariffIn forceComisión Nacional de Energía (CNE); Secretaría de Energía (SENER)
4 May 2026SENER Single Self-Supply Window (Ventanilla Única de Autoconsumo): fixed deadlines for 0.7 to 20 MW self-supply projectsRegulationIn forceSecretaría de Energía (SENER)
16 Apr 2026Cogeneration rules: one study request; new plant and load centre studied on the larger of capacity or demandRegulationIn forceComisión Nacional de Energía (CNE)
16 Apr 2026CNE rules for batteries at load centres (SAEE-CC): connection studies and demand limitsRegulationIn forceComisión Nacional de Energía (CNE)
17 Mar 2026CNE model interconnection and connection contract: load centres of 1 MW or more must sign; developer pays for works and posts guaranteesGrid accessIn forceComisión Nacional de Energía (CNE); CENACE
29 Dec 2025Saldo del diferencial de costos de generación por acreditar a la CFEPower tariffIn forceComisión Nacional de Energía (CNE)
29 Dec 2025Cargo por Servicios Conexos no incluidos en el MEM 2026Power tariffIn forceComisión Nacional de Energía (CNE)
29 Dec 2025Cargo de transmisión para la categoría DIT (Demanda Industrial en Transmisión)Power tariffIn forceComisión Nacional de Energía (CNE)
29 Dec 2025Categoría tarifaria GDMTH – Gran Demanda en Media Tensión HorariaPower tariffIn forceComisión Nacional de Energía (CNE)
29 Dec 2025Acuerdo por el que la CNE autoriza el cálculo y ajuste de las tarifas finales del Suministro Básico de la CFE, 1 enero – 31 diciembre 2026Power tariffIn forceComisión Nacional de Energía (CNE)
22 Dec 2025Energy Sector Programme 2025-2030 (PROSENER): clean energy to reach 38% of power generation by 2030Renewable energyIn forceSecretaría de Energía (SENER)
20 Mar 2025New Federal Law on Protection of Personal Data held by Private Parties (2025): transfers allowed, no data localisationRegulationIn forceCongress of the Union; Secretaría Anticorrupción y Buen Gobierno
18 Mar 2025Self-supply (autoconsumo) regime: own power plants of 0.7 MW or more, simplified permit for 0.7 to 20 MW interconnected plantsRegulationIn forceComisión Nacional de Energía (CNE); Secretaría de Energía (SENER)
18 Mar 2025Electricity Sector Law (LSE): the State must keep at least 54% of the energy injected into the gridRegulationIn forceCongress of the Union; Secretaría de Energía (SENER); Comisión Nacional de Energía (CNE)
13 Dec 2024Acuerdo A/158/2024 de la extinta Comisión Reguladora de Energía (cálculo y ajuste de tarifas finales 2025)Power tariffExpiredComisión Reguladora de Energía (extinct); voided by Comisión Nacional de Energía

How Mexico compares

Latest official figures for the countries we track.

CountryIndustrial power priceRenewable shareGrid emission factorRestrictions in forceIncentives in force
Argentina—19.6% (2025)0.28 kgCO2/kWh (2022)02
Australia—39% (2025)—02
Austria169 USD/MWh (2026)78% (2025)0.15 kgCO2/kWh (2023)00
Bangladesh—2% (2025)—00
Belgium183 USD/MWh (2025)34.3% (2025)0.19 kgCO2/kWh (2024)00
Brazil—86.8% (2025)0.07 kgCO2/kWh (2025)01
Canada—63.9% (2024)0.10 kgCO2/kWh (2022)60
Chile—66% (2025)0.24 kgCO2/kWh (2023)00
China—38% (2025)0.53 kgCO2/kWh (2023)20
Colombia——0.22 kgCO2/kWh (2024)02
Costa Rica—98.6% (2025)0.04 kgCO2/kWh (2025)11
Denmark134 USD/MWh (2025)81.5% (2024)0.11 kgCO2/kWh (2024)10
Ecuador——0.16 kgCO2/kWh (2024)10
Finland58.4 USD/MWh (2025)57% (2024)0.03 kgCO2/kWh (2025)00
France104 USD/MWh (2025)27% (2025)0.02 kgCO2/kWh (2025)01
Germany180 USD/MWh (2025)58.8% (2025)0.34 kgCO2/kWh (2025)10
Guatemala84.5 USD/MWh (2025)53.5% (2024)0.29 kgCO2/kWh (2024)02
Hong Kong180 USD/MWh (2026)—0.59 kgCO2/kWh (2025)02
Iceland42.9 USD/MWh (2022)100% (2026)—12
India82.1 USD/MWh (2025)28.7% (2026)0.68 kgCO2/kWh (2025)15
Indonesia62.9 USD/MWh (2024)16.3% (2025)0.68 kgCO2/kWh (2024)01
Ireland234 USD/MWh (2025)41.3% (2024)0.20 kgCO2/kWh (2025)20
Israel—14.6% (2024)0.41 kgCO2/kWh (2024)10
Italy184 USD/MWh (2025)48% (2025)0.20 kgCO2/kWh (2025)00
Japan—23.1% (2024)0.45 kgCO2/kWh (2024)00
Jordan—26.9% (2024)0.54 kgCO2/kWh (2023)01
Kazakhstan—14.6% (2025)0.81 kgCO2/kWh (2025)00
Kyrgyzstan41.7 USD/MWh (2026)88% (2024)0.16 kgCO2/kWh (2019)11
Luxembourg165 USD/MWh (2025)23.3% (2025)—00
Malaysia105 USD/MWh (2026)21% (2025)0.74 kgCO2/kWh (2024)11
Mexico——0.44 kgCO2/kWh (2023)00
Morocco—27% (2024)—00
Nepal———00
Netherlands148 USD/MWh (2025)49% (2025)0.20 kgCO2/kWh (2024)40
New Zealand—88.5% (2025)0.08 kgCO2/kWh (2025)00
Nigeria154 USD/MWh (2026)32.7% (2025)—01
Norway100 USD/MWh (2026)96% (2025)0.01 kgCO2/kWh (2025)10
Pakistan97.5 USD/MWh (2026)34.7% (2025)—01
Panama66.3 USD/MWh (2025)74.7% (2025)0.15 kgCO2/kWh (2024)01
Paraguay33.0 USD/MWh (2026)——12
Peru—62.6% (2025)—01
Philippines—22.2% (2024)0.71 kgCO2/kWh (2017)12
Poland197 USD/MWh (2026)31.4% (2025)—01
Russia—17.6% (2025)—20
Singapore189 USD/MWh (2025)2.1% (2024)0.40 kgCO2/kWh (2024)10
South Africa—9% (2024)—11
South Korea—9.8% (2025)—00
Spain113 USD/MWh (2025)55.5% (2025)—10
Sri Lanka—60.2% (2025)—00
Sweden78.5 USD/MWh (2025)—0.06 kgCO2/kWh (2023)00
Switzerland240 USD/MWh (2026)70.8% (2025)0.13 kgCO2/kWh (2022)00
Taiwan—12.7% (2025)0.47 kgCO2/kWh (2024)10
Thailand120 USD/MWh (2026)—0.48 kgCO2/kWh (2026)02
Türkiye70.3 USD/MWh (2026)—0.44 kgCO2/kWh (2022)11
United Arab Emirates120 USD/MWh (2026)8.8% (2024)0.47 kgCO2/kWh (2024)00
United Kingdom234 USD/MWh (2026)52.1% (2025)0.15 kgCO2/kWh (2026)11
United States86.2 USD/MWh (2025)24% (2025)0.35 kgCO2/kWh (2023)01
Uruguay101 USD/MWh (2026)98% (2025)0.01 kgCO2/kWh (2025)03
Uzbekistan83.3 USD/MWh (2026)19.4% (2025)—10
Venezuela—77% (2023)—01
Vietnam69.9 USD/MWh (2026)——11

Questions

Is there a data center moratorium in Mexico?

We have found no moratorium or restriction on new data centers in force in Mexico as of 15 November 2026. Proposed or announced measures, if any, are listed in the timeline.

Where does this data come from?

Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.

What counts as a restriction or moratorium?

A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.

How are power prices compared?

We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.

How often is it updated?

Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.

Global capacity

How much data center capacity does Mexico have?

Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.

See Mexico capacity