Every data center in Taiwan that we have verified: operator, location, status and capacity, each checked against its source.
By Amit JainReviewed by Deepti AgrawalUpdated 25 Nov 2026
In short
As of 25 November 2026, DC Market Insights tracks 43 data centers in Taiwan run by 16 operators: 32 operational, 5 under construction and 6 planned. Stated operational capacity is 107 MW, with a further 45 MW under construction and 151 MW planned. Chunghwa Telecom holds the largest share of tracked operational capacity (34%).
43Facilities tracked
16Operators
107 MWOperational (32 sites)
45 MWUnder construction (5 sites)
151 MWPlanned (6 sites)
MW = IT capacity where the source states it, otherwise total capacity. 13 of 43 facilities have a stated capacity; the others are counted as sites only.
OperationalUnder constructionPlannedPin = exact site location; dot = city (approximate)
Market snapshot
Taiwan data center market: key facts
Capacity under construction or planned (196 MW) is 1.8 times the operational base of 107 MW.
The three largest operators by operational capacity, Chunghwa Telecom, Chief Telecom and Vantage Data Centers, hold 67% of tracked operational MW.
NCHC (NARLabs) has the largest development pipeline in Taiwan: 120 MW under construction or planned.
The largest operational facility we track is Chunghwa Telecom Lunping AI Data Center (Chunghwa Telecom, Taoyuan) at 36 MW.
The largest project in the pipeline is Shalun Smart Innovation Computing Center (沙崙智慧創新算力中心) by NCHC (NARLabs) (120 MW, planned).
Tainan is the largest cluster: 4 of 43 facilities and 45% of tracked capacity.
By type, the tracker lists 30 colocation, 5 enterprise and 4 hyperscale facilities.
13 of 43 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational107 MW
Under construction45 MW
Planned151 MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Capacity by year opened or expected, MW
OperationalUnder construction or planned Facilities with a stated year and capacity only.
Largest operators in Taiwan by tracked capacity, MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Market context
What shapes the Taiwan data center market
Policy, power, land and demand, each statement checked against its source. Reviewed 29 October 2026. Government sources are linked; the full source list comes with the Excel data.
Taiwan's data-centre siting is set by power. Since September 2023 Taipower has paused new data-centre supply above 5 MW in northern Taiwan (Taoyuan and north) and steers large sites to central and southern Taiwan. New 5 MW+ sites face MOEA energy-use review with PUE caps of 1.3 to 1.4. Users above 5,000 kW must source renewables equal to 10% of contract capacity, and large IDCs paid 15-25% tariff rises in 2024.
Power and grid
Taipower has paused new supply applications from data centres of 5 MW and above in northern Taiwan since September 2023, a temporary measure until grid bottlenecks are fixed. It is drafting supply-approval rules for transmission-level data centres in tight-supply areas.
Northern Taiwan used 93.1 TWh in 2023 but generated 75.0 TWh, relying on power sent from central and southern Taiwan. Taipower steers 5 MW+ data centres to the central-south.
Taipower expects new demand from semiconductors and AI to exceed 5 GW by 2030, with average annual growth over 2026-2035 more than double the past decade. It warns that AI data centres in cities create very high local load density.
The NT$564.5bn Strengthening Grid Resilience Plan decentralises the grid and feeds science and industrial parks directly from nearby plants. The government wants it finished by 2028. Executive Yuan news
The last nuclear unit (Maanshan 2) was retired in May 2025. Taipower submitted a Maanshan restart plan to the Nuclear Safety Commission on 27 Mar 2026, but any restart needs 18-24 months of safety inspection and licence renewal.
Power prices
From April 2024, internet data centres using more than 50 GWh a year faced tariff rises of 15-25% by consumption scale, above the 7-14% for other industries.
After the October 2024 review, the average industrial price is NT$4.27/kWh. Taipower's 2025 average unit price for the power-service category was NT$4.2289/kWh.
Policy and incentives
The Executive Yuan's AI New Ten Major Construction programme commits over NT$130bn over four years to compute, sovereign AI, applications and talent. The AI Basic Act took effect in January 2026. Executive Yuan news
State compute is going south: the 15 MW NCHC cloud compute centre in Southern Taiwan Science Park opened in December 2025, and a 120 MW Shalun centre in Tainan is planned for 2029. NSTC news
Sustainability, efficiency and climate
New or expanded hyperscale and colocation data centres of 5 MW and above must use best available techniques and pass an energy-use review. PUE must not exceed 1.3 for hyperscale and 1.4 for colocation (effective 5 Nov 2025).
Users with contract capacity of 5,000 kW or more must cover 10% of contract capacity with renewables, storage, green power and certificates, or a fee in lieu, within 5 years (in force since 2021). Taiwan Renewable Energy Certificate Center
Renewables were 12.7% of Taipower-system generation in 2025. The grid emission factor fell from 0.530 kg/kWh in 2016 to 0.474 kg/kWh in 2024.
A carbon fee of NT$300/tCO2e has applied to designated large emitters since 1 Jan 2025. MOENV news release
Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
A second analyst re-opens each source before a facility is published.
Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.
Questions
How many data centers are there in Taiwan?
DC Market Insights tracks 43 data centers in Taiwan as of November 2026: 32 operational, 5 under construction and 6 planned, run by 16 operators. The count grows as we verify more sites.
What is the data center capacity of Taiwan?
Tracked operational capacity in Taiwan is 107 MW, with 45 MW under construction and 151 MW planned. These totals use the capacity each source states (IT load where given) and cover 13 of 43 tracked facilities.
Which companies operate the most data center capacity in Taiwan?
By tracked operational capacity, the largest operators in Taiwan are Chunghwa Telecom (36 MW), Chief Telecom (20 MW) and Vantage Data Centers (16 MW).
Where are the data centers in Taiwan located?
The largest clusters by tracked capacity are Tainan (4 facilities), Taipei (16 facilities) and Miaoli (3 facilities). The map above shows every site.
Which new data centers are being built in Taiwan?
We track 45 MW under construction and 151 MW planned. The largest projects are Shalun Smart Innovation Computing Center (沙崙智慧創新算力中心) by NCHC (NARLabs) (120 MW), Epoch Digital Taipei (22 MW) and Chief Telecom Huwei AI Data Center (16 MW).
Where does this data come from?
Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.
What does the MW figure mean?
We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.
How exact are the map locations?
When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.
How often is it updated?
The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.
Can I get the data in Excel?
Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.
Global capacity
How much data center capacity is installed worldwide?
Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.