Every data center in Thailand that we have verified: operator, location, status and capacity, each checked against its source.
By Amit JainReviewed by Deepti AgrawalUpdated 25 Nov 2026
In short
As of 25 November 2026, DC Market Insights tracks 30 data centers in Thailand run by 20 operators: 22 operational, 4 under construction and 4 planned. Stated operational capacity is 51.6 MW, with a further 307 MW under construction and 157 MW planned. ST Telemedia Global Data Centres holds the largest share of tracked operational capacity (48%).
30Facilities tracked
20Operators
51.6 MWOperational (22 sites)
307 MWUnder construction (4 sites)
157 MWPlanned (4 sites)
MW = IT capacity where the source states it, otherwise total capacity. 11 of 30 facilities have a stated capacity; the others are counted as sites only.
OperationalUnder constructionPlannedPin = exact site location; dot = city (approximate)
Market snapshot
Thailand data center market: key facts
Capacity under construction or planned (464 MW) is 9.0 times the operational base of 51.6 MW.
The three largest operators by operational capacity, ST Telemedia Global Data Centres, SUPERNAP Thailand and NTT DATA, hold 100% of tracked operational MW.
Bridge Data Centres has the largest development pipeline in Thailand: 193 MW under construction or planned.
The largest operational facility we track is STTGDC BKK1 (ST Telemedia Global Data Centres, Bangkok) at 23 MW.
The largest project in the pipeline is Bridge Data Centres QHI01 and QHI02 (193 MW, under construction).
Bangkok is the largest cluster: 22 of 30 facilities and 55% of tracked capacity.
By type, the tracker lists 20 colocation, 6 hyperscale and 3 enterprise facilities.
11 of 30 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational51.6 MW
Under construction307 MW
Planned157 MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Largest operators in Thailand by tracked capacity, MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Market context
What shapes the Thailand data center market
Policy, power, land and demand, each statement checked against its source. Reviewed 21 November 2026. Government sources are linked; the full source list comes with the Excel data.
Thailand promotes data centers through the Board of Investment: since July 2025 sites with PUE of 1.3 or lower and at least 2 MW IT load get the higher incentive group (8-year CIT exemption, 5 years in the EEC). Power prices are set nationally by the ERC (average 3.95 THB/kWh in Sep-Dec 2026), and new rules for data center grid deposits, a dedicated electricity licence and Direct PPA are in preparation. BOI Announcement Sor. 5/2568
Policy and incentives
BOI Announcement Sor. 5/2568 (5 Jun 2025, applications from 1 Jul 2025) splits data center promotion by efficiency: PUE not above 1.3 = activity 8.2.1.1 (group A2), other data centers = 8.2.1.2 (A3); both need at least 2 MW IT load, and ISO/IEC 27001 is required before the CIT exemption can be used. BOI
BOI's 2026 presentation gives the CIT exemption as 8 years for PUE of 1.3 or lower and 5 years above 1.3, each one level lower inside the EEC, and asks for a utility certificate of power supply capacity before applying. BOI
A Prime Minister's Office regulation approved by Cabinet on 5 Aug 2026 set up a Data Center Business Policy Committee chaired by a Deputy PM, covering energy prices, water, zoning, fire safety and data security.
Power and grid
The ERC kept the Sep-Dec 2026 Ft at 16.23 satang per unit, leaving the national average at 3.95 THB per unit excluding VAT; for Jan-Apr 2027 a two-tier option of 103.34 satang for medium and large users is out for comment (18-24 Nov 2026).
EGAT and the Ministry of Energy are upgrading EEC substations to serve 1,150 MW of urgent data center demand, with new PEA delivery points at Rayong 2, Phanthong and Phanthong 2. EGAT
Large users on MEA and PEA Type 4.2.1 time-of-use tariffs at 69 kV and above pay 4.1025 THB/kWh on-peak and 2.5849 THB/kWh off-peak plus 74.14 THB/kW-month on-peak demand, before Ft and VAT. PEA
Land, zoning and sites
No national data center moratorium is in place; BOI lowers the incentive group by one level for data centers located in the Eastern Economic Corridor. BOI
Sustainability, water and climate
Green power routes are the Utility Green Tariff (UGT1 2026 premium proposed at 0.0375 THB/unit) and a 2,000 MW Direct PPA pilot aimed at data center companies whose parents require renewable power. ERC
The Thailand Greenhouse Gas Management Organization set the grid electricity emission factor at 0.4750 kgCO2e/kWh (combustion plus T&D losses).
Our Deal Tracker lists 10 deals in Thailand since January 2026, with $4.74B in disclosed value.
Aether Holdings, Inc. (Aether Compute); Advance Capital Partners Limited → Proposed AI data center joint venture on Cho Thavee's ~14-acre factory site, Khon Kaen, Thailand JV / partnership
Thai bank (not named) → Haoyang Data Centre 1 (Thailand) Ltd (HYDC1) hyperscale AI data center, Eastern Economic Corridor, ~140,302 sq m site Financing$590.0M
Unnamed tier 1 global hyperscaler → TH01 phase 1, Bang Na, Bangkok (12MW) Land / campus · 12 MW
Bangkok Bank, Bank of Ayudhya, HSBC, KASIKORNBANK, Mizuho, Natixis CIB, Siam Commercial Bank, SMBC, Standard Chartered (MLAs) → Digital Edge / B.Grimm Power JV – BKK Campus, Chonburi (100 MW)
Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
A second analyst re-opens each source before a facility is published.
Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.
Questions
How many data centers are there in Thailand?
DC Market Insights tracks 30 data centers in Thailand as of November 2026: 22 operational, 4 under construction and 4 planned, run by 20 operators. The count grows as we verify more sites.
What is the data center capacity of Thailand?
Tracked operational capacity in Thailand is 51.6 MW, with 307 MW under construction and 157 MW planned. These totals use the capacity each source states (IT load where given) and cover 11 of 30 tracked facilities.
Which companies operate the most data center capacity in Thailand?
By tracked operational capacity, the largest operators in Thailand are ST Telemedia Global Data Centres (25 MW), SUPERNAP Thailand (20 MW) and NTT DATA (6.6 MW).
Where are the data centers in Thailand located?
The largest clusters by tracked capacity are Bangkok (22 facilities), Chonburi (6 facilities) and Greater Bangkok (1 facilities). The map above shows every site.
Which new data centers are being built in Thailand?
We track 307 MW under construction and 157 MW planned. The largest projects are Bridge Data Centres QHI01 and QHI02 (193 MW), BKK Campus by CloudHQ (108 MW) and BKK1 (BKK Campus) by Digital Edge (100 MW).
Where does this data come from?
Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.
What does the MW figure mean?
We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.
How exact are the map locations?
When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.
How often is it updated?
The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.
Can I get the data in Excel?
Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.
Global capacity
How much data center capacity is installed worldwide?
Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.