Data Center Power & Policy in Guatemala

Every government action on data centers and power in Guatemala that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.

In short

As of 20 October 2026, DC Market Insights tracks 8 government actions on data centers and power in Guatemala, 6 of them in force. We have found no moratorium or restriction on new data centers in force in Guatemala. 2 incentive schemes apply, including ZDEEP regime (Decreto 30-2008 amending ZOLIC Law, Decreto 22-73).

8Actions tracked
6In force
84.5 USD/MWhIndustrial power price
53.5%Renewable share of generation

Market snapshot

Guatemala power and policy: key facts

  • Industrial electricity price: 84.5 USD/MWh (2025). Rank 16 of 21 tracked countries, highest first.
  • Renewable share of electricity generation: 53.5% (2024). Rank 10 of 32 tracked countries, highest first.
  • Grid emission factor: 0.29 kgCO2/kWh (2024). Rank 11 of 26 tracked countries, highest first.
  • Latest change: Plan de Expansión Indicativo del Sistema de Generación 2026-2050 (with Política Energética 2013-2027 targets) (Ministerio de Energía y Minas (MEM), 1 Jan 2026).
  • By type: 3 regulation, 2 plan or strategy, 2 incentive and 1 power tariff.

Power indicators for Guatemala

Latest official figure for each indicator, with earlier years where we have them.

Industrial electricity price 84.5 USD/MWh 2025 · Average AMM wholesale spot (opportunity) energy price 2025, original unit USD/MWh, no FX conversion. Energy only: excludes capacity, transmission tolls and distribution; the price reference for Grandes Usuarios (above 100 kW) buying on the spot market. 20 CNEE – Compendio Estadístico 2025 (data from AMM)
Renewable share of electricity generation 53.5% 2024 · CNEE reports clean-energy generation of 53.48% in 2024, down from 57.63% in 2023 and 70.03% in 2022, because El Niño reduced hydro output. MEM's semester report shows a recovery to 61.42% renewable in H1 2025 (6,568.24 GWh generated; hydro 2,175.54 GWh, b CNEE – Compendio Estadístico 2024-2025
Grid emission factor 0.29 kgCO2/kWh 2024 · MEM's 2024 GHG monitoring report sets the national grid factor (GHG emitted per kWh used from the national grid) at 0.2945 kgCO2e/kWh for 2024; MEM's 2023 energy balance gave 0.2687. IPCC methodology, with biomass CO2 treated as biogenic. MEM – Informe de Gases de Efecto Invernadero 2024

In force now in Guatemala

Power tariff (1)

  • Power tariffIn force

    Reglamento de la LGE (Acuerdo Gubernativo 256-97): Gran Usuario threshold 100 kW

    A Gran Usuario is any consumer whose power demand exceeds 100 kW (or a lower limit MEM may set). Large users are not price-regulated and freely negotiate supply with the distributor or any other supplier (generator or marketer), paying network tolls; consumers at or below 100 kW pay CNEE-set tariffs. Art. 19 lets MEM lower the 100 kW limit, even to zero, with two years' notice. Practically every data center qualifies as a Gran Usuario.

    100 kW (Gran Usuario threshold)

    Presidencia / MEM; applied by CNEE and AMM · Effective 21 Mar 1997 · CNEE – Reglamento de la Ley General de Electricidad (RLGE.pdf)

Incentive (2)

  • IncentiveIn force

    ZDEEP regime (Decreto 30-2008 amending ZOLIC Law, Decreto 22-73)

    Public Special Economic Development Zones (ZDEEP) are extra-customs areas authorised by ZOLIC (the state free-zone entity) for industrial, commercial and service activities. Users receive a 10-year 100% income tax exemption, VAT exemption on foreign-trade transactions and exemption from import duties (DAI) on inputs, machinery and equipment. Named ZDEEPs include Zona Franca Quetzal, Puerta del Istmo and Michatoya Pacifico. No ZDEEP rule names data centers specifically.

    10 years 100% ISR exemption

    ZOLIC (Zona Libre de Industria y Comercio Santo Tomás de Castilla)

  • IncentiveIn force

    Ley de Incentivos para el Desarrollo de Proyectos de Energía Renovable (Decreto 52-2003)

    Renewable generation projects qualified by MEM get: exemption from import duties and VAT on generation machinery and equipment during pre-investment and construction (max 10 years); a 10-year income tax (ISR) exemption from the start of commercial operation; and a 10-year exemption from the Impuesto a las Empresas Mercantiles y Agropecuarias. Relevant to on-site or captive renewable plants built for data centers. Regulation: Acuerdo Gubernativo 211-2005.

    10 years ISR exemption

    Congreso de la Republica; MEM (qualification), SAT (import exemption) · Effective 11 Nov 2003 · CNEE – Ley de incentivos para el desarrollo de Energía Renovable

Regulation (2)

  • RegulationIn force

    Reglamento de Evaluación, Control y Seguimiento Ambiental (Acuerdo Gubernativo 137-2016)

    All projects, works, industries or activities are classified through MARN's Listado Taxativo into category A (highest impact, incl. megaprojects), B1/B2 (moderate) or C (low impact, register only), which sets the environmental instrument required before construction. Projects not in the list are categorised by MARN on technical criteria; the list was issued as Acuerdo Ministerial 204-2019. Applies to data center construction and to associated generation or substations.

    Ministerio de Ambiente y Recursos Naturales (MARN) · Effective 11 Jul 2016

  • RegulationIn force

    Ley General de Electricidad (Decreto 93-96)

    Framework electricity law. Generation is free and needs no prior State authorisation (beyond constitutional/legal requirements); transport not using public-domain assets and private distribution are also free. Creates CNEE as regulator and MEM as policy body, sets up the Wholesale Market (run by AMM) and defines Gran Usuario by reference to the threshold in the regulation. A data center can build its own generation or buy power without a concession.

    Congreso de la Republica; text hosted by CNEE · Effective 15 Nov 1996 · CNEE – Ley General de Electricidad (LGE.pdf)

Plan or strategy (1)

  • Plan or strategyIn force

    Plan de Expansión Indicativo del Sistema de Generación 2026-2050 (with Política Energética 2013-2027 targets)

    MEM's January 2026 indicative generation expansion plan restates national targets: 80% of electricity from renewables, 500 MW of new renewable investment and 1,500 km of new transmission lines (Política Energética 2013-2027). It finds all scenarios below the 80% target in 2026-2029, with several reaching it from 2032, and warns that load-flow studies for 2025-2026 show nodes outside operating limits, so grid reinforcement is urgent.

    80 % renewable generation target

    Ministerio de Energía y Minas (MEM) · Effective 1 Jan 2026 · MEM – PEIG 2026-2050

Announced and proposed

Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.

  • RegulationProposed

    Iniciativa 6347 – Ley de Ciberseguridad (bill)

    Cybersecurity bill in Congress. Proposes a national cyber-incident response centre, new computer crimes (illicit access to or interception of data, computer fraud) and protection of critical infrastructure such as banking systems and telecom networks. Favourable opinion from the Comisión de Asuntos de Seguridad Nacional on 26 Aug 2025; still under review in Congress in mid-2026 per press. Not enacted; no data-center-specific provisions verified.

    Congreso de la Republica (Comisión de Asuntos de Seguridad Nacional)

  • Plan or strategyAnnounced

    Licitación Abierta PEG-5-2025 (generation tender, 1,400 MW firm)

    Largest generation tender in Guatemala's history, run by the distributors under CNEE terms of reference (CNEE-270-2024; bases CNEE-108-2025 with Addendum 1 CNEE-287-2025). Seeks 1,400 MW of guaranteed capacity plus up to 150 MW of installed capacity, with supply starting 1 May 2030-2033 and contracts of up to 15 years. Offers were received 12 Feb 2026 (per press); the final award was not verified on an official page.

    1,400 MW guaranteed capacity

    CNEE; tendering distributors EEGSA, DEOCSA, DEORSA · Effective 1 May 2030

Timeline of data center and power policy in Guatemala

DateActionTypeStatusAuthority
1 Jan 2026Plan de Expansión Indicativo del Sistema de Generación 2026-2050 (with Política Energética 2013-2027 targets)Plan or strategyIn forceMinisterio de Energía y Minas (MEM)
26 Aug 2025Iniciativa 6347 – Ley de Ciberseguridad (bill)RegulationProposedCongreso de la Republica (Comisión de Asuntos de Seguridad Nacional)
1 May 2025Licitación Abierta PEG-5-2025 (generation tender, 1,400 MW firm)Plan or strategyAnnouncedCNEE; tendering distributors EEGSA, DEOCSA, DEORSA
11 Jul 2016Reglamento de Evaluación, Control y Seguimiento Ambiental (Acuerdo Gubernativo 137-2016)RegulationIn forceMinisterio de Ambiente y Recursos Naturales (MARN)
1 Jan 2008ZDEEP regime (Decreto 30-2008 amending ZOLIC Law, Decreto 22-73)IncentiveIn forceZOLIC (Zona Libre de Industria y Comercio Santo Tomás de Castilla)
28 Oct 2003Ley de Incentivos para el Desarrollo de Proyectos de Energía Renovable (Decreto 52-2003)IncentiveIn forceCongreso de la Republica; MEM (qualification), SAT (import exemption)
21 Mar 1997Reglamento de la LGE (Acuerdo Gubernativo 256-97): Gran Usuario threshold 100 kWPower tariffIn forcePresidencia / MEM; applied by CNEE and AMM
16 Oct 1996Ley General de Electricidad (Decreto 93-96)RegulationIn forceCongreso de la Republica; text hosted by CNEE

How Guatemala compares

Latest official figures for the countries we track.

CountryIndustrial power priceRenewable shareGrid emission factorRestrictions in forceIncentives in force
Argentina—19.6% (2025)0.28 kgCO2/kWh (2022)02
Australia—39% (2025)—02
Bangladesh—2% (2025)—00
Belgium183 USD/MWh (2025)34.3% (2025)0.19 kgCO2/kWh (2024)00
Brazil—86.8% (2025)0.07 kgCO2/kWh (2025)01
Canada—63.9% (2024)0.10 kgCO2/kWh (2022)20
Chile—66% (2025)0.24 kgCO2/kWh (2023)00
Colombia——0.22 kgCO2/kWh (2024)02
Denmark134 USD/MWh (2025)81.5% (2024)0.11 kgCO2/kWh (2024)10
Ecuador——0.16 kgCO2/kWh (2024)10
Finland58.4 USD/MWh (2025)57% (2024)0.03 kgCO2/kWh (2025)00
France104 USD/MWh (2025)27% (2025)0.02 kgCO2/kWh (2025)01
Germany180 USD/MWh (2025)58.8% (2025)0.34 kgCO2/kWh (2025)10
Guatemala84.5 USD/MWh (2025)53.5% (2024)0.29 kgCO2/kWh (2024)02
India82.1 USD/MWh (2025)28.7% (2026)0.68 kgCO2/kWh (2025)05
Indonesia62.9 USD/MWh (2024)16.3% (2025)0.68 kgCO2/kWh (2024)01
Ireland234 USD/MWh (2025)41.3% (2024)0.20 kgCO2/kWh (2025)20
Italy184 USD/MWh (2025)48% (2025)0.20 kgCO2/kWh (2025)00
Japan—23.1% (2024)0.45 kgCO2/kWh (2024)00
Kazakhstan—14.6% (2025)0.81 kgCO2/kWh (2025)00
Luxembourg165 USD/MWh (2025)23.3% (2025)—00
Malaysia105 USD/MWh (2026)21% (2025)0.74 kgCO2/kWh (2024)11
Mexico——0.44 kgCO2/kWh (2023)00
Nepal———00
Netherlands148 USD/MWh (2025)49% (2025)0.20 kgCO2/kWh (2024)40
Pakistan97.5 USD/MWh (2026)34.7% (2025)—01
Peru—62.6% (2025)—01
Russia—17.6% (2025)—20
Singapore189 USD/MWh (2025)2.1% (2024)0.40 kgCO2/kWh (2024)00
South Korea—9.8% (2025)—00
Spain113 USD/MWh (2025)55.5% (2025)—00
Sri Lanka—60.2% (2025)—00
Sweden78.5 USD/MWh (2025)—0.06 kgCO2/kWh (2023)00
United Arab Emirates120 USD/MWh (2026)8.8% (2024)0.47 kgCO2/kWh (2024)00
United Kingdom234 USD/MWh (2026)52.1% (2025)0.15 kgCO2/kWh (2026)11
United States86.2 USD/MWh (2025)24% (2025)0.35 kgCO2/kWh (2023)01
Uzbekistan83.3 USD/MWh (2026)19.4% (2025)—10

Questions

Is there a data center moratorium in Guatemala?

We have found no moratorium or restriction on new data centers in force in Guatemala as of 20 October 2026. Proposed or announced measures, if any, are listed in the timeline.

What incentives does Guatemala offer data centers?

In force: ZDEEP regime (Decreto 30-2008 amending ZOLIC Law, Decreto 22-73) and Ley de Incentivos para el Desarrollo de Proyectos de Energía Renovable (Decreto 52-2003). Each is listed with its authority and dates on this page.

What does electricity cost for data centers in Guatemala?

The industrial electricity price in Guatemala was 84.5 USD/MWh in 2025 (Average AMM wholesale spot (opportunity) energy price 2025, original unit USD/MWh, no FX conversion. Energy only: excludes capacity, transmission tolls and distribution; the price reference for Grandes Usuarios (above 100 kW) buying on the spot market. 20). Data center contracts can differ by voltage level, contract length and location.

How much of Guatemala’s electricity is renewable?

Renewables supplied 53.5% of electricity generation in Guatemala in 2024.

Where does this data come from?

Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.

What counts as a restriction or moratorium?

A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.

How are power prices compared?

We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.

How often is it updated?

Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.

Global capacity

How much data center capacity is installed worldwide?

Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.

Open the Global Capacity Tracker

Choosing a market or a site?

Our analysts prepare country briefings on power, grid access, incentives and permits, with every source, in Excel.