Data Center Power & Policy in Guatemala
Every government action on data centers and power in Guatemala that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.
In short
As of 20 October 2026, DC Market Insights tracks 8 government actions on data centers and power in Guatemala, 6 of them in force. We have found no moratorium or restriction on new data centers in force in Guatemala. 2 incentive schemes apply, including ZDEEP regime (Decreto 30-2008 amending ZOLIC Law, Decreto 22-73).
Market snapshot
Guatemala power and policy: key facts
- Industrial electricity price: 84.5 USD/MWh (2025). Rank 16 of 21 tracked countries, highest first.
- Renewable share of electricity generation: 53.5% (2024). Rank 10 of 32 tracked countries, highest first.
- Grid emission factor: 0.29 kgCO2/kWh (2024). Rank 11 of 26 tracked countries, highest first.
- Latest change: Plan de Expansión Indicativo del Sistema de Generación 2026-2050 (with Política Energética 2013-2027 targets) (Ministerio de Energía y Minas (MEM), 1 Jan 2026).
- By type: 3 regulation, 2 plan or strategy, 2 incentive and 1 power tariff.
Power indicators for Guatemala
Latest official figure for each indicator, with earlier years where we have them.
In force now in Guatemala
Power tariff (1)
Reglamento de la LGE (Acuerdo Gubernativo 256-97): Gran Usuario threshold 100 kW
A Gran Usuario is any consumer whose power demand exceeds 100 kW (or a lower limit MEM may set). Large users are not price-regulated and freely negotiate supply with the distributor or any other supplier (generator or marketer), paying network tolls; consumers at or below 100 kW pay CNEE-set tariffs. Art. 19 lets MEM lower the 100 kW limit, even to zero, with two years' notice. Practically every data center qualifies as a Gran Usuario.
100 kW (Gran Usuario threshold)
Incentive (2)
ZDEEP regime (Decreto 30-2008 amending ZOLIC Law, Decreto 22-73)
Public Special Economic Development Zones (ZDEEP) are extra-customs areas authorised by ZOLIC (the state free-zone entity) for industrial, commercial and service activities. Users receive a 10-year 100% income tax exemption, VAT exemption on foreign-trade transactions and exemption from import duties (DAI) on inputs, machinery and equipment. Named ZDEEPs include Zona Franca Quetzal, Puerta del Istmo and Michatoya Pacifico. No ZDEEP rule names data centers specifically.
10 years 100% ISR exemption
Ley de Incentivos para el Desarrollo de Proyectos de Energía Renovable (Decreto 52-2003)
Renewable generation projects qualified by MEM get: exemption from import duties and VAT on generation machinery and equipment during pre-investment and construction (max 10 years); a 10-year income tax (ISR) exemption from the start of commercial operation; and a 10-year exemption from the Impuesto a las Empresas Mercantiles y Agropecuarias. Relevant to on-site or captive renewable plants built for data centers. Regulation: Acuerdo Gubernativo 211-2005.
10 years ISR exemption
Regulation (2)
Reglamento de Evaluación, Control y Seguimiento Ambiental (Acuerdo Gubernativo 137-2016)
All projects, works, industries or activities are classified through MARN's Listado Taxativo into category A (highest impact, incl. megaprojects), B1/B2 (moderate) or C (low impact, register only), which sets the environmental instrument required before construction. Projects not in the list are categorised by MARN on technical criteria; the list was issued as Acuerdo Ministerial 204-2019. Applies to data center construction and to associated generation or substations.
Ley General de Electricidad (Decreto 93-96)
Framework electricity law. Generation is free and needs no prior State authorisation (beyond constitutional/legal requirements); transport not using public-domain assets and private distribution are also free. Creates CNEE as regulator and MEM as policy body, sets up the Wholesale Market (run by AMM) and defines Gran Usuario by reference to the threshold in the regulation. A data center can build its own generation or buy power without a concession.
Plan or strategy (1)
Plan de Expansión Indicativo del Sistema de Generación 2026-2050 (with Política Energética 2013-2027 targets)
MEM's January 2026 indicative generation expansion plan restates national targets: 80% of electricity from renewables, 500 MW of new renewable investment and 1,500 km of new transmission lines (Política Energética 2013-2027). It finds all scenarios below the 80% target in 2026-2029, with several reaching it from 2032, and warns that load-flow studies for 2025-2026 show nodes outside operating limits, so grid reinforcement is urgent.
80 % renewable generation target
Announced and proposed
Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.
Iniciativa 6347 – Ley de Ciberseguridad (bill)
Cybersecurity bill in Congress. Proposes a national cyber-incident response centre, new computer crimes (illicit access to or interception of data, computer fraud) and protection of critical infrastructure such as banking systems and telecom networks. Favourable opinion from the Comisión de Asuntos de Seguridad Nacional on 26 Aug 2025; still under review in Congress in mid-2026 per press. Not enacted; no data-center-specific provisions verified.
Licitación Abierta PEG-5-2025 (generation tender, 1,400 MW firm)
Largest generation tender in Guatemala's history, run by the distributors under CNEE terms of reference (CNEE-270-2024; bases CNEE-108-2025 with Addendum 1 CNEE-287-2025). Seeks 1,400 MW of guaranteed capacity plus up to 150 MW of installed capacity, with supply starting 1 May 2030-2033 and contracts of up to 15 years. Offers were received 12 Feb 2026 (per press); the final award was not verified on an official page.
1,400 MW guaranteed capacity
Timeline of data center and power policy in Guatemala
| Date | Action | Type | Status | Authority |
|---|---|---|---|---|
| 1 Jan 2026 | Plan de Expansión Indicativo del Sistema de Generación 2026-2050 (with Política Energética 2013-2027 targets) | Plan or strategy | In force | Ministerio de Energía y Minas (MEM) |
| 26 Aug 2025 | Iniciativa 6347 – Ley de Ciberseguridad (bill) | Regulation | Proposed | Congreso de la Republica (Comisión de Asuntos de Seguridad Nacional) |
| 1 May 2025 | Licitación Abierta PEG-5-2025 (generation tender, 1,400 MW firm) | Plan or strategy | Announced | CNEE; tendering distributors EEGSA, DEOCSA, DEORSA |
| 11 Jul 2016 | Reglamento de Evaluación, Control y Seguimiento Ambiental (Acuerdo Gubernativo 137-2016) | Regulation | In force | Ministerio de Ambiente y Recursos Naturales (MARN) |
| 1 Jan 2008 | ZDEEP regime (Decreto 30-2008 amending ZOLIC Law, Decreto 22-73) | Incentive | In force | ZOLIC (Zona Libre de Industria y Comercio Santo Tomás de Castilla) |
| 28 Oct 2003 | Ley de Incentivos para el Desarrollo de Proyectos de Energía Renovable (Decreto 52-2003) | Incentive | In force | Congreso de la Republica; MEM (qualification), SAT (import exemption) |
| 21 Mar 1997 | Reglamento de la LGE (Acuerdo Gubernativo 256-97): Gran Usuario threshold 100 kW | Power tariff | In force | Presidencia / MEM; applied by CNEE and AMM |
| 16 Oct 1996 | Ley General de Electricidad (Decreto 93-96) | Regulation | In force | Congreso de la Republica; text hosted by CNEE |
How Guatemala compares
Latest official figures for the countries we track.
| Country | Industrial power price | Renewable share | Grid emission factor | Restrictions in force | Incentives in force |
|---|---|---|---|---|---|
| Argentina | — | 19.6% (2025) | 0.28 kgCO2/kWh (2022) | 0 | 2 |
| Australia | — | 39% (2025) | — | 0 | 2 |
| Bangladesh | — | 2% (2025) | — | 0 | 0 |
| Belgium | 183 USD/MWh (2025) | 34.3% (2025) | 0.19 kgCO2/kWh (2024) | 0 | 0 |
| Brazil | — | 86.8% (2025) | 0.07 kgCO2/kWh (2025) | 0 | 1 |
| Canada | — | 63.9% (2024) | 0.10 kgCO2/kWh (2022) | 2 | 0 |
| Chile | — | 66% (2025) | 0.24 kgCO2/kWh (2023) | 0 | 0 |
| Colombia | — | — | 0.22 kgCO2/kWh (2024) | 0 | 2 |
| Denmark | 134 USD/MWh (2025) | 81.5% (2024) | 0.11 kgCO2/kWh (2024) | 1 | 0 |
| Ecuador | — | — | 0.16 kgCO2/kWh (2024) | 1 | 0 |
| Finland | 58.4 USD/MWh (2025) | 57% (2024) | 0.03 kgCO2/kWh (2025) | 0 | 0 |
| France | 104 USD/MWh (2025) | 27% (2025) | 0.02 kgCO2/kWh (2025) | 0 | 1 |
| Germany | 180 USD/MWh (2025) | 58.8% (2025) | 0.34 kgCO2/kWh (2025) | 1 | 0 |
| Guatemala | 84.5 USD/MWh (2025) | 53.5% (2024) | 0.29 kgCO2/kWh (2024) | 0 | 2 |
| India | 82.1 USD/MWh (2025) | 28.7% (2026) | 0.68 kgCO2/kWh (2025) | 0 | 5 |
| Indonesia | 62.9 USD/MWh (2024) | 16.3% (2025) | 0.68 kgCO2/kWh (2024) | 0 | 1 |
| Ireland | 234 USD/MWh (2025) | 41.3% (2024) | 0.20 kgCO2/kWh (2025) | 2 | 0 |
| Italy | 184 USD/MWh (2025) | 48% (2025) | 0.20 kgCO2/kWh (2025) | 0 | 0 |
| Japan | — | 23.1% (2024) | 0.45 kgCO2/kWh (2024) | 0 | 0 |
| Kazakhstan | — | 14.6% (2025) | 0.81 kgCO2/kWh (2025) | 0 | 0 |
| Luxembourg | 165 USD/MWh (2025) | 23.3% (2025) | — | 0 | 0 |
| Malaysia | 105 USD/MWh (2026) | 21% (2025) | 0.74 kgCO2/kWh (2024) | 1 | 1 |
| Mexico | — | — | 0.44 kgCO2/kWh (2023) | 0 | 0 |
| Nepal | — | — | — | 0 | 0 |
| Netherlands | 148 USD/MWh (2025) | 49% (2025) | 0.20 kgCO2/kWh (2024) | 4 | 0 |
| Pakistan | 97.5 USD/MWh (2026) | 34.7% (2025) | — | 0 | 1 |
| Peru | — | 62.6% (2025) | — | 0 | 1 |
| Russia | — | 17.6% (2025) | — | 2 | 0 |
| Singapore | 189 USD/MWh (2025) | 2.1% (2024) | 0.40 kgCO2/kWh (2024) | 0 | 0 |
| South Korea | — | 9.8% (2025) | — | 0 | 0 |
| Spain | 113 USD/MWh (2025) | 55.5% (2025) | — | 0 | 0 |
| Sri Lanka | — | 60.2% (2025) | — | 0 | 0 |
| Sweden | 78.5 USD/MWh (2025) | — | 0.06 kgCO2/kWh (2023) | 0 | 0 |
| United Arab Emirates | 120 USD/MWh (2026) | 8.8% (2024) | 0.47 kgCO2/kWh (2024) | 0 | 0 |
| United Kingdom | 234 USD/MWh (2026) | 52.1% (2025) | 0.15 kgCO2/kWh (2026) | 1 | 1 |
| United States | 86.2 USD/MWh (2025) | 24% (2025) | 0.35 kgCO2/kWh (2023) | 0 | 1 |
| Uzbekistan | 83.3 USD/MWh (2026) | 19.4% (2025) | — | 1 | 0 |
Questions
Is there a data center moratorium in Guatemala?
We have found no moratorium or restriction on new data centers in force in Guatemala as of 20 October 2026. Proposed or announced measures, if any, are listed in the timeline.
What incentives does Guatemala offer data centers?
In force: ZDEEP regime (Decreto 30-2008 amending ZOLIC Law, Decreto 22-73) and Ley de Incentivos para el Desarrollo de Proyectos de Energía Renovable (Decreto 52-2003). Each is listed with its authority and dates on this page.
What does electricity cost for data centers in Guatemala?
The industrial electricity price in Guatemala was 84.5 USD/MWh in 2025 (Average AMM wholesale spot (opportunity) energy price 2025, original unit USD/MWh, no FX conversion. Energy only: excludes capacity, transmission tolls and distribution; the price reference for Grandes Usuarios (above 100 kW) buying on the spot market. 20). Data center contracts can differ by voltage level, contract length and location.
How much of Guatemala’s electricity is renewable?
Renewables supplied 53.5% of electricity generation in Guatemala in 2024.
Where does this data come from?
Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.
What counts as a restriction or moratorium?
A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.
How are power prices compared?
We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.
How often is it updated?
Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.
Global capacity
How much data center capacity is installed worldwide?
Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.