How much data center capacity Canada has installed, how it compares with the rest of North America, and what our trackers show about its sites, operators, deals and rules.
Canada data center capacity at a glance
Canada had about 1.8 GW of installed data center capacity (IT load) at the end of 2025, by our estimate. That is about 4% of the capacity in North America and puts Canada at number 6 of the 26 countries in our global model. Our Data Center Tracker holds 1 sites in Canada run by 1 operators: 0 operational, 1 under construction and 0 planned. Our trackers also hold 5 verified deals and 0 government measures in force for the country.
Installed capacity is IT load, the power available to servers, storage and network. The country figure comes from the same model as the global and regional totals and is benchmarked against dated public figures. Site figures below are what each source states, often a campus’s full build-out, so they are not the same measure.
What our tracker holds for Canada
Largest tracked sites
| Site | Operator | City | Status | MW |
|---|---|---|---|---|
| Meta Sturgeon County Data Center | Meta | Sturgeon County | Under construction | 1,000 |
Where the sites are
| City | Sites | Operators | MW stated, live |
|---|---|---|---|
| Sturgeon County | 1 | 1 | n/a |
Cities with the most tracked sites. MW only where a source states it.
Who runs them
| Operator | Sites | MW live | MW pipeline |
|---|---|---|---|
| Meta | 1 | n/a | 1,000 |
Operators ranked by MW stated at their tracked sites in Canada.
Recent deals
- Sep 2026 · Land / campusBell AI data centre project, Regina area, Saskatchewan (expanded to pathway to 1.2 GW), 1,200 MW
- Jul 2026 · Land / campusMeta's first Canadian data center, Sturgeon County, Alberta (1 GW), 1,000 MW, USD 9.2 bn
- Jul 2026 · Power dealGreenlight Electricity Centre, 932 MW gas-fired plant, Sturgeon County, Alberta, powering an unnamed customer's data centre, 932 MW, USD 2.8 bn
- Jan 2026 · M&ASaint John data center (500kW, three halls), 1 MW
- Jan 2026 · Land / campusSynapse Olds Data Centre, Olds, Alberta, 1,000 MW
Other countries in North America
- United States50.4 GW
Installed capacity, end 2025, DC Market Insights estimate. All countries and regions
Canada in the full data pack
By year to 2035
Installed MW for Canada from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases.
Leading hubs
Live and pipeline MW for the main metro markets, with the basis of each figure.
Every tracked site
The full site list with operator, location, status, MW and source, refreshed from our tracker.
Related research on Canada
Frequently asked questions
How much data center capacity does Canada have?
We estimate about 1.8 GW of installed data center capacity (IT load) in Canada at the end of 2025, about 4% of North America and number 6 of the 26 countries in our model. This is a DC Market Insights estimate, benchmarked against dated public figures.
How many data centers are there in Canada?
Our Data Center Tracker lists 1 sites in Canada (0 operational, 1 under construction, 0 planned), run by 1 operators. Each site is verified from operator, planning or utility sources; the list grows as new sites are confirmed.
Which companies have the most tracked data center capacity in Canada?
By capacity stated at their sites (operational plus pipeline), the largest in our tracker are Meta. Site capacity is counted only where a source states it.
How will Canada data center capacity grow to 2035?
The full data pack gives installed capacity for Canada by year from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases and the main metro hubs.