Proprietary data

Meta Data Centers

Data centers operated by Meta that we have verified: location, status and capacity, each checked against its source.

In short

As of 21 October 2026, DC Market Insights tracks 36 data centers operated by Meta in 6 countries, of which 20 are operational. Stated operational capacity is 1,000 MW, with a further 8,000 MW under construction and — planned. The pipeline is 8.0 times the capacity already operating.

36Facilities tracked
6Countries
1,000 MWOperational (20 sites)
8,000 MWUnder construction (13 sites)
—Planned (3 sites)

MW = IT capacity where the source states it, otherwise total capacity. 5 of 36 facilities have a stated capacity; the others are counted as sites only.

Singapore Data Center (Tanjong Kling) · Meta · Singapore (approximate location)Meta Odense Data Center · Meta · Odense (approximate location)Meta Fort Worth Data Center · Meta · Fort Worth (approximate location)Meta Temple Data Center · Meta · Temple (approximate location)Meta El Paso Data Center · Meta · El Paso (approximate location)Meta Mesa Data Center · Meta · Mesa (approximate location) · Owned: (self-build): Meta data center, $1.2B investment in ArizonaMeta Los Lunas Data Center · Meta · Los Lunas (approximate location) · Cooling: Evaporative or adiabatic · Owned: (self-build): Meta's own data center campusMeta Los Lunas expansion (Greater Kudu) · Meta · Los Lunas (approximate location) · Owned: (self-build)Meta Eagle Mountain Data Center · Meta · Eagle Mountain (approximate location) · Cooling: Direct liquid · Owned: (self-build): Meta's own Eagle Mountain campusMeta Prineville · Meta · Prineville (approximate location) · Cooling: Evaporative or adiabatic · Owned: Meta custom-built campus, first building broke ground 2010Meta Kuna · Meta · Kuna (approximate location) · Cooling: HybridGallatin Data Center · Meta · Gallatin (approximate location) · Owned: (self-build): Meta seeks city approval to build another data center on its own 800-acre siteAiken Data Center · Meta · Aiken (approximate location) · Cooling: Chilled water, dry coolers · Owned: Meta self-buildForest City Data Center · Meta · Forest City (approximate location) · Owned: (self-build): Meta broke ground on the Forest City Data Center in 2010Huntsville Data Center · Meta · Huntsville (approximate location) · Owned: council approved purchase by Facebook project entity Starbelt LLCMontgomery Data Center · Meta · Montgomery (approximate location)Richland Parish Data Center (Hyperion) · Meta · Holly Ridge (approximate location) · Joint venture: Blue Owl funds 80% / Meta 20%; Meta leases all campus facilities from the JVMeta DeKalb Data Center · Meta · DeKalb (approximate location) · Owned: Meta data center (article calls it its DeKalb Data Center; Mortensen is the construction lead)Meta New Albany Data Center · Meta · New Albany (approximate location) · Cooling: Hybrid · Owned (self-build): (Meta's own buildings) plus leased capacity from strategic partners; Meta does not name the partnersMeta Bowling Green Data Center · Meta · Bowling Green (approximate location)Meta Jeffersonville Data Center · Meta · Jeffersonville (approximate location) · Owned: (self-build): Meta data center campusMeta Lebanon Data Center · Meta · Lebanon (approximate location) · Cooling: Direct liquid · Owned (self-build): (Meta states in general terms that it designs and builds its own infrastructure; the page does not state site ownership)Meta Rosemount Data Center · Meta · Rosemount (approximate location) · Owned: Meta self-build data center (Meta's 19th U.S. data center)Meta Beaver Dam Data Center · Meta · Beaver Dam (approximate location) · Cooling: Chilled water, dry coolers · Owned: (self-build)Meta Kansas City Data Center · Meta · Kansas City (approximate location) · Owned: Meta-built and operated data centerMeta Cheyenne Data Center · Meta · Cheyenne (approximate location) · Owned (self-build): Meta says it custom designs and builds its own infrastructure; the page calls Cheyenne 'our newest Meta data center'Meta Luleå Data Center · Meta · Luleå (approximate location)Meta Sturgeon County Data Center · Meta · Sturgeon County (approximate location)Meta Tulsa Data Center · Meta · Tulsa (approximate location)Meta Maysville hyperscale data center campus · Meta · Maysville (approximate location) · Cooling: Chilled water, dry coolersMeta Altoona Data Center · Meta · Altoona (exact location) · Owned (self-build): Meta with general contractor Turner Construction CompanyMeta Sarpy Data Center · Meta · Papillion (exact location) · Owned: self-build; permit holder Raven Northbrook LLC, tied to Facebook in 2017 reportingMeta Clonee Data Center · Meta · Clonee (exact location) · Owned: Runways Information Services Ltd owns and operates the campus
Operational Under construction Planned Pin = exact site location; dot = city (approximate) Select a country on the map to open its page.

Market snapshot

Meta data centers: key facts

About Meta

Meta Platforms owns and operates its own data center fleet to run Facebook, Instagram, WhatsApp and its AI models. In April 2026 Meta said it had 32 owned and operated data centers; the Sturgeon County, Alberta campus announced in July 2026 became the 33rd in its global fleet. Its locations page lists 28 US sites plus Sturgeon County (Canada), Odense (Denmark), Clonee (Ireland), Luleå (Sweden) and Singapore. Richland Parish (5GW), El Paso, Lebanon and New Albany are each planned at 1GW or more.

Headquarters
Menlo Park, United States
Founded
2004
Ownership
Listed on Nasdaq (META)
Tracked footprint
36 facilities in 6 countries
Website
datacenters.atmeta.com

Data center business

  • Meta says the electricity use of its data centers is matched with 100% clean and renewable energy, and its Eagle Mountain (Utah) and Sturgeon County (Alberta) sites are designed with no operational water use in the cooling system. In Utah alone it reports more than 1.7GW of clean energy across 13 sites supporting the Eagle Mountain data center.
  • Meta funds the build-out from its own capital spending: capital expenditures, including principal payments on finance leases, were $31.08 billion in Q2 2026, and Meta expects full-year 2026 capital expenditures of $130-145 billion.
  • Meta says it has spent more than 15 years developing, constructing and operating data center facilities.
  • Meta describes its fleet as owned and operated: "Meta has 32 owned and operated data centers that support our apps and technologies." It says it broke ground on ten data centers in the 24 months to April 2026, and that its Richland Parish, El Paso, Lebanon and New Albany, Ohio facilities will each have 1GW or more of capacity once construction is complete.
  • Meta designs and builds its own data centers and key parts of its technical infrastructure, and third parties also provide a substantial portion of that infrastructure.
  • The Meta data center locations page (viewed October 2026) lists 33 sites: 28 in the United States, Sturgeon County in Canada, Odense in Denmark, Clonee in Ireland, Luleå in Sweden and Singapore. For each it gives the investment, the year construction began and the number of operational jobs, but no megawatt capacity per site.
  • Europe: Luleå, Sweden was Meta's first European data center and began serving live user traffic in June 2013 (investment 8.7B+ SEK). Clonee, County Meath, announced in January 2016, was its first in Ireland and second in Europe (€1.4B). Odense, Denmark (10B+ DKK) delivers 165,000 MWh of surplus heat a year from its server halls to the local district heating system.

Recent updates

  • Eagle Mountain, Utah data center expansion announced, taking Meta's investment in Utah to more than $3 billion.
  • Kuna, Idaho data center announced online and operational. Construction began in 2022 and the site represents an investment of more than $1.2 billion.
  • Q2 2026 results: capital expenditures of $31.08 billion in the quarter; full-year 2026 outlook narrowed to $130-145 billion.
  • Meta and funds managed by BlackRock form a venture (BlackRock 80%, Meta 20%) to develop and own the 1GW El Paso, Texas campus; total development costs are about $14 billion and the campus is expected to start coming online in 2028.
  • Richland Parish, Louisiana data center expanded to 5GW of compute capacity, an investment of more than $50 billion in the region plus over $1 billion in local infrastructure.
  • Ground broken on a 1GW, AI-optimized data center in Sturgeon County, Alberta: Meta's first in Canada and 33rd in its global fleet, an investment of more than CAD $13 billion.
  • Ground broken on an AI-optimized data center in Tulsa, Oklahoma, Meta's first in the state, 28th in the US and 32nd globally; more than $1 billion investment once completed.

Company details checked against company and official sources, 12 Nov 2026.

  • Capacity under construction or planned (8,000 MW) is 8.0 times the operational base of 1,000 MW.
  • Its largest operational site is Meta New Albany Data Center in New Albany, United States at 1,000 MW.
  • The largest project in the pipeline is Richland Parish Data Center (Hyperion) by Meta (5,000 MW, under construction).
  • United States accounts for 89% of tracked capacity (31 facilities).
  • 5 of 36 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational1,000 MW
Under construction8,000 MW

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Capacity by country, MW
Canada1,000 MW

OperationalUnder construction or planned

Meta development pipeline

Under construction and planned facilities with a stated capacity, largest first. 8,000 MW under construction and — planned in total.

ProjectLocationStatusTypeCapacity
Richland Parish Data Center (Hyperion)Meta Holly Ridge, United States Under construction Hyperscale 5,000 MW
Meta Sturgeon County Data CenterMeta Sturgeon County, Canada Under construction Hyperscale 1,000 MW
Meta El Paso Data CenterMeta El Paso, United States Under construction Hyperscale 1,000 MW
Meta Lebanon Data CenterMeta Lebanon, United States Under construction Hyperscale 1,000 MW

Facilities

36 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
Richland Parish Data Center (Hyperion)Hyperscale Joint venture: Blue Owl funds 80% / Meta 20%; Meta leases all campus facilities from the JV
History
  1. Announced
  2. Under construction
  3. Under construction
  4. Under construction
Holly Ridge, United States Under construction 5,000 MW IT — Operator / official
Meta El Paso Data CenterHyperscale
History
  1. Under construction
  2. Under construction
  3. Under construction
El Paso, United States Under construction 1,000 MW IT — Operator / official
Meta Lebanon Data CenterHyperscale Cooling: Direct liquid · Owned (self-build): (Meta states in general terms that it designs and builds its own infrastructure; the page does not state site ownership)
History
  1. Under construction
  2. Under construction
Lebanon, United States Under construction 1,000 MW — Operator / official
Meta New Albany Data CenterHyperscale Cooling: Hybrid · Owned (self-build): (Meta's own buildings) plus leased capacity from strategic partners; Meta does not name the partners
History
  1. Operational
  2. Operational
New Albany, United States Operational 1,000 MW — Operator / official
Meta Sturgeon County Data CenterHyperscale
1 deal
Sturgeon County, Canada Under construction 1,000 MW total — Operator / official
Aiken Data CenterHyperscale Cooling: Chilled water, dry coolers · Owned: Meta self-build Aiken, United States Under construction — — Operator / official
Forest City Data CenterHyperscale Owned: (self-build): Meta broke ground on the Forest City Data Center in 2010 Forest City, United States Operational — — Operator / official
Gallatin Data CenterHyperscale Owned: (self-build): Meta seeks city approval to build another data center on its own 800-acre site Gallatin, United States Operational — — Operator / official
Henrico Data CenterHyperscale United States Operational — 2020 Trade press
Huntsville Data CenterHyperscale Owned: council approved purchase by Facebook project entity Starbelt LLC Huntsville, United States Operational — — Operator / official
Meta Altoona Data CenterHyperscale Owned (self-build): Meta with general contractor Turner Construction Company Altoona, United States Operational — 2014 Operator / official
Meta Beaver Dam Data CenterHyperscale Cooling: Chilled water, dry coolers · Owned: (self-build) Beaver Dam, United States Under construction — — Operator / official
Meta Bowling Green Data CenterHyperscale Bowling Green, United States Under construction — — Operator / official
Meta Cheyenne Data CenterHyperscale Owned (self-build): Meta says it custom designs and builds its own infrastructure; the page calls Cheyenne 'our newest Meta data center' Cheyenne, United States Under construction — — Operator / official
Meta Clonee Data CenterHyperscale Owned: Runways Information Services Ltd owns and operates the campus
History
  1. Announced
  2. Operational
Clonee, Ireland Operational — — Operator / official
Meta DeKalb Data CenterHyperscale Owned: Meta data center (article calls it its DeKalb Data Center; Mortensen is the construction lead) DeKalb, United States Operational — 2023 Trade press
Meta Eagle Mountain Data CenterHyperscale Cooling: Direct liquid · Owned: (self-build): Meta's own Eagle Mountain campus Eagle Mountain, United States Operational — 2021 Operator / official
Meta Fort Worth Data CenterHyperscale Fort Worth, United States Operational — — Operator / official
Meta Jeffersonville Data CenterHyperscale Owned: (self-build): Meta data center campus Jeffersonville, United States Under construction — — Operator / official
Meta Kansas City Data CenterHyperscale Owned: Meta-built and operated data center Kansas City, United States Operational — 2025 Trade press
Meta KunaHyperscale Cooling: Hybrid
History
  1. Under construction
  2. Announced
  3. Operational
  4. Operational
Kuna, United States Operational — 2026 Operator / official
Meta Los Lunas Data CenterHyperscale Cooling: Evaporative or adiabatic · Owned: (self-build): Meta's own data center campus Los Lunas, United States Operational — — Trade press
Meta Los Lunas expansion (Greater Kudu)Hyperscale Owned: (self-build) Los Lunas, United States Planned — — Trade press
Meta Luleå Data CenterHyperscale Luleå, Sweden Operational — 2013 Operator / official
Meta Maysville hyperscale data center campusHyperscale Cooling: Chilled water, dry coolers
History
  1. Planned
  2. Planned
Maysville, United States Planned — — Trade press
Meta Mesa Data CenterHyperscale Owned: (self-build): Meta data center, $1.2B investment in Arizona Mesa, United States Operational — — Trade press
Meta Odense Data CenterHyperscale
History
  1. Under construction
  2. Operational
Odense, Denmark Operational — — Operator / official
Meta PrinevilleHyperscale Cooling: Evaporative or adiabatic · Owned: Meta custom-built campus, first building broke ground 2010 Prineville, United States Operational — — Trade press
Meta Rosemount Data CenterHyperscale Owned: Meta self-build data center (Meta's 19th U.S. data center)
History
  1. Under construction
  2. Under construction
Rosemount, United States Under construction — — Trade press
Meta Sarpy Data CenterHyperscale Owned: self-build; permit holder Raven Northbrook LLC, tied to Facebook in 2017 reporting Papillion, United States Operational — 2019 Trade press
Meta Temple Data CenterHyperscale Temple, United States Under construction — — Operator / official
Meta Tulsa Data CenterHyperscale Tulsa, United States Under construction — — Operator / official
Montgomery Data CenterHyperscale Montgomery, United States Under construction — — Operator / official
Project Tropical (Meta Henrico expansion)Hyperscale United States Planned — — Trade press
Singapore Data Center (Tanjong Kling)Hyperscale Singapore, Singapore Operational — 2022 Trade press
Stanton Springs Data CenterHyperscale Cooling: Air or free cooling United States Operational — — Operator / official

Market position

How Meta compares

Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.

  • In United States, Meta ranks #3 of 171 tracked operators by capacity, with 10% of the country’s tracked MW.
  • United States has 1,315 tracked data centers from 171 operators: 11,392 MW operational and 66,365 MW under construction or planned.
  • Industrial electricity in United States costs 86.2 USD/MWh (2025, latest official figure).
  • In Ireland, Meta is one of 15 operators we track.
  • In Sweden, Meta is one of 17 operators we track.
  • Our Deal Tracker lists 1 deal(s) naming Meta, the latest on 13 October 2026.

Data center operators in United States

Tracked facilities1,315171 operators
Operational capacity11,392 MW66,365 MW in the pipeline
Meta rank by capacity#3of 171 operators · 10%
Industrial power price86.2 USD/MWh2025
OperatorFacilitiesOperational MWPipeline MW
Tract19—17,275 MW
PowerHouse Data Centers1760 MW8,807 MW
Vantage Data Centers22194 MW3,804 MW
Beale Infrastructure6—3,650 MW
OpenAI1—3,200 MW
Aligned Data Centers29154 MW2,648 MW
STACK Infrastructure20480 MW1,848 MW
QTS471,977 MW283 MW

All data centers in United States Power and policy in United States

Data center operators in Ireland

Tracked facilities3915 operators
Operational capacity53 MW1,278 MW in the pipeline
Meta rank by capacity#15of 15 operators
Industrial power price234 USD/MWh2025
OperatorFacilitiesOperational MWPipeline MW
Red Admiral DC1—250 MW
Echelon Data Centres2—200 MW
Art Data Centres1—200 MW
Herbata1—180 MW
Amazon Web Services6—169 MW
Huntstown Power Company1—150 MW
EdgeConneX425 MW37 MW
Pure DC314 MW40 MW

All data centers in Ireland Power and policy in Ireland

Data center operators in Sweden

Tracked facilities4117 operators
Operational capacity172 MW1,510 MW in the pipeline
Meta rank by capacity#16of 17 operators
Industrial power price78.5 USD/MWh2025
OperatorFacilitiesOperational MWPipeline MW
Brookfield1—750 MW
EcoDataCenter380 MW400 MW
atNorth312 MW330 MW
Conapto439 MW—
Hydro66119.2 MW—
STACK Infrastructure118 MW—
evroc1—18 MW
Bahnhof6—12 MW

All data centers in Sweden Power and policy in Sweden

Deals naming Meta

  • Meta → Data center and technology campus, Mason County (Maysville), Kentucky Land / campus $10.00B

Open in the Deal Tracker

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
  • Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers does Meta operate?

DC Market Insights tracks 36 Meta data center(s) in 6 countries as of October 2026: 20 operational, 13 under construction and 3 planned.

Where is Meta headquartered?

Meta is headquartered in Menlo Park, United States. Ownership: Listed on Nasdaq (META).

Which other companies operate data centers in United States?

Besides Meta, the largest operators we track in United States by capacity are Tract, PowerHouse Data Centers, Vantage Data Centers, Beale Infrastructure and OpenAI. The United States page lists all 171 operators.

What rules apply to data centers in United States?

Our Power & Policy Tracker lists 15 government actions on data centers and power in United States, including 0 restriction(s) and 1 incentive scheme(s) in force.

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Global capacity

How much data center capacity is installed worldwide?

Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.

Open the Global Capacity Tracker

Need the full list, or a capacity view of one market?

Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.

Talk to an analyst