Proprietary data
Meta Data Centers
Data centers operated by Meta that we have verified: location, status and capacity, each checked against its source.
In short
As of 21 October 2026, DC Market Insights tracks 36 data centers operated by Meta in 6 countries, of which 20 are operational. Stated operational capacity is 1,000 MW, with a further 8,000 MW under construction and — planned. The pipeline is 8.0 times the capacity already operating.
MW = IT capacity where the source states it, otherwise total capacity. 5 of 36 facilities have a stated capacity; the others are counted as sites only.
Market snapshot
Meta data centers: key facts
About Meta
Meta Platforms owns and operates its own data center fleet to run Facebook, Instagram, WhatsApp and its AI models. In April 2026 Meta said it had 32 owned and operated data centers; the Sturgeon County, Alberta campus announced in July 2026 became the 33rd in its global fleet. Its locations page lists 28 US sites plus Sturgeon County (Canada), Odense (Denmark), Clonee (Ireland), Luleå (Sweden) and Singapore. Richland Parish (5GW), El Paso, Lebanon and New Albany are each planned at 1GW or more.
- Headquarters
- Menlo Park, United States
- Founded
- 2004
- Ownership
- Listed on Nasdaq (META)
- Tracked footprint
- 36 facilities in 6 countries
- Website
- datacenters.atmeta.com
Data center business
- Meta says the electricity use of its data centers is matched with 100% clean and renewable energy, and its Eagle Mountain (Utah) and Sturgeon County (Alberta) sites are designed with no operational water use in the cooling system. In Utah alone it reports more than 1.7GW of clean energy across 13 sites supporting the Eagle Mountain data center.
- Meta funds the build-out from its own capital spending: capital expenditures, including principal payments on finance leases, were $31.08 billion in Q2 2026, and Meta expects full-year 2026 capital expenditures of $130-145 billion.
- Meta says it has spent more than 15 years developing, constructing and operating data center facilities.
- Meta describes its fleet as owned and operated: "Meta has 32 owned and operated data centers that support our apps and technologies." It says it broke ground on ten data centers in the 24 months to April 2026, and that its Richland Parish, El Paso, Lebanon and New Albany, Ohio facilities will each have 1GW or more of capacity once construction is complete.
- Meta designs and builds its own data centers and key parts of its technical infrastructure, and third parties also provide a substantial portion of that infrastructure.
- The Meta data center locations page (viewed October 2026) lists 33 sites: 28 in the United States, Sturgeon County in Canada, Odense in Denmark, Clonee in Ireland, Luleå in Sweden and Singapore. For each it gives the investment, the year construction began and the number of operational jobs, but no megawatt capacity per site.
- Europe: Luleå, Sweden was Meta's first European data center and began serving live user traffic in June 2013 (investment 8.7B+ SEK). Clonee, County Meath, announced in January 2016, was its first in Ireland and second in Europe (€1.4B). Odense, Denmark (10B+ DKK) delivers 165,000 MWh of surplus heat a year from its server halls to the local district heating system.
Recent updates
- Eagle Mountain, Utah data center expansion announced, taking Meta's investment in Utah to more than $3 billion.
- Kuna, Idaho data center announced online and operational. Construction began in 2022 and the site represents an investment of more than $1.2 billion.
- Q2 2026 results: capital expenditures of $31.08 billion in the quarter; full-year 2026 outlook narrowed to $130-145 billion.
- Meta and funds managed by BlackRock form a venture (BlackRock 80%, Meta 20%) to develop and own the 1GW El Paso, Texas campus; total development costs are about $14 billion and the campus is expected to start coming online in 2028.
- Richland Parish, Louisiana data center expanded to 5GW of compute capacity, an investment of more than $50 billion in the region plus over $1 billion in local infrastructure.
- Ground broken on a 1GW, AI-optimized data center in Sturgeon County, Alberta: Meta's first in Canada and 33rd in its global fleet, an investment of more than CAD $13 billion.
- Ground broken on an AI-optimized data center in Tulsa, Oklahoma, Meta's first in the state, 28th in the US and 32nd globally; more than $1 billion investment once completed.
Company details checked against company and official sources, 12 Nov 2026.
- Capacity under construction or planned (8,000 MW) is 8.0 times the operational base of 1,000 MW.
- Its largest operational site is Meta New Albany Data Center in New Albany, United States at 1,000 MW.
- The largest project in the pipeline is Richland Parish Data Center (Hyperion) by Meta (5,000 MW, under construction).
- United States accounts for 89% of tracked capacity (31 facilities).
- 5 of 36 facilities have a capacity stated by their source; the totals above count only those.
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
OperationalUnder construction or planned
Meta development pipeline
Under construction and planned facilities with a stated capacity, largest first. 8,000 MW under construction and — planned in total.
| Project | Location | Status | Type | Capacity |
|---|---|---|---|---|
| Richland Parish Data Center (Hyperion)Meta | Holly Ridge, United States | Under construction | Hyperscale | 5,000 MW |
| Meta Sturgeon County Data CenterMeta | Sturgeon County, Canada | Under construction | Hyperscale | 1,000 MW |
| Meta El Paso Data CenterMeta | El Paso, United States | Under construction | Hyperscale | 1,000 MW |
| Meta Lebanon Data CenterMeta | Lebanon, United States | Under construction | Hyperscale | 1,000 MW |
Facilities
36 facilities match. Each is checked against its source; source links come with the Excel data.
| Facility | Location | Status | Capacity | Year | Source |
|---|---|---|---|---|---|
Richland Parish Data Center (Hyperion)Hyperscale
Joint venture: Blue Owl funds 80% / Meta 20%; Meta leases all campus facilities from the JV
History
|
Holly Ridge, United States | Under construction | 5,000 MW IT | — | Operator / official |
Meta El Paso Data CenterHyperscale
History
|
El Paso, United States | Under construction | 1,000 MW IT | — | Operator / official |
Meta Lebanon Data CenterHyperscale
Cooling: Direct liquid · Owned (self-build): (Meta states in general terms that it designs and builds its own infrastructure; the page does not state site ownership)
History
|
Lebanon, United States | Under construction | 1,000 MW | — | Operator / official |
Meta New Albany Data CenterHyperscale
Cooling: Hybrid · Owned (self-build): (Meta's own buildings) plus leased capacity from strategic partners; Meta does not name the partners
History
|
New Albany, United States | Operational | 1,000 MW | — | Operator / official |
Meta Sturgeon County Data CenterHyperscale
1 deal
|
Sturgeon County, Canada | Under construction | 1,000 MW total | — | Operator / official |
| Aiken Data CenterHyperscale Cooling: Chilled water, dry coolers · Owned: Meta self-build | Aiken, United States | Under construction | — | — | Operator / official |
| Forest City Data CenterHyperscale Owned: (self-build): Meta broke ground on the Forest City Data Center in 2010 | Forest City, United States | Operational | — | — | Operator / official |
| Gallatin Data CenterHyperscale Owned: (self-build): Meta seeks city approval to build another data center on its own 800-acre site | Gallatin, United States | Operational | — | — | Operator / official |
| Henrico Data CenterHyperscale | United States | Operational | — | 2020 | Trade press |
| Huntsville Data CenterHyperscale Owned: council approved purchase by Facebook project entity Starbelt LLC | Huntsville, United States | Operational | — | — | Operator / official |
| Meta Altoona Data CenterHyperscale Owned (self-build): Meta with general contractor Turner Construction Company | Altoona, United States | Operational | — | 2014 | Operator / official |
| Meta Beaver Dam Data CenterHyperscale Cooling: Chilled water, dry coolers · Owned: (self-build) | Beaver Dam, United States | Under construction | — | — | Operator / official |
| Meta Bowling Green Data CenterHyperscale | Bowling Green, United States | Under construction | — | — | Operator / official |
| Meta Cheyenne Data CenterHyperscale Owned (self-build): Meta says it custom designs and builds its own infrastructure; the page calls Cheyenne 'our newest Meta data center' | Cheyenne, United States | Under construction | — | — | Operator / official |
Meta Clonee Data CenterHyperscale
Owned: Runways Information Services Ltd owns and operates the campus
History
|
Clonee, Ireland | Operational | — | — | Operator / official |
| Meta DeKalb Data CenterHyperscale Owned: Meta data center (article calls it its DeKalb Data Center; Mortensen is the construction lead) | DeKalb, United States | Operational | — | 2023 | Trade press |
| Meta Eagle Mountain Data CenterHyperscale Cooling: Direct liquid · Owned: (self-build): Meta's own Eagle Mountain campus | Eagle Mountain, United States | Operational | — | 2021 | Operator / official |
| Meta Fort Worth Data CenterHyperscale | Fort Worth, United States | Operational | — | — | Operator / official |
| Meta Jeffersonville Data CenterHyperscale Owned: (self-build): Meta data center campus | Jeffersonville, United States | Under construction | — | — | Operator / official |
| Meta Kansas City Data CenterHyperscale Owned: Meta-built and operated data center | Kansas City, United States | Operational | — | 2025 | Trade press |
Meta KunaHyperscale
Cooling: Hybrid
History
|
Kuna, United States | Operational | — | 2026 | Operator / official |
| Meta Los Lunas Data CenterHyperscale Cooling: Evaporative or adiabatic · Owned: (self-build): Meta's own data center campus | Los Lunas, United States | Operational | — | — | Trade press |
| Meta Los Lunas expansion (Greater Kudu)Hyperscale Owned: (self-build) | Los Lunas, United States | Planned | — | — | Trade press |
| Meta Luleå Data CenterHyperscale | Luleå, Sweden | Operational | — | 2013 | Operator / official |
Meta Maysville hyperscale data center campusHyperscale
Cooling: Chilled water, dry coolers
History
|
Maysville, United States | Planned | — | — | Trade press |
| Meta Mesa Data CenterHyperscale Owned: (self-build): Meta data center, $1.2B investment in Arizona | Mesa, United States | Operational | — | — | Trade press |
Meta Odense Data CenterHyperscale
History
|
Odense, Denmark | Operational | — | — | Operator / official |
| Meta PrinevilleHyperscale Cooling: Evaporative or adiabatic · Owned: Meta custom-built campus, first building broke ground 2010 | Prineville, United States | Operational | — | — | Trade press |
Meta Rosemount Data CenterHyperscale
Owned: Meta self-build data center (Meta's 19th U.S. data center)
History
|
Rosemount, United States | Under construction | — | — | Trade press |
| Meta Sarpy Data CenterHyperscale Owned: self-build; permit holder Raven Northbrook LLC, tied to Facebook in 2017 reporting | Papillion, United States | Operational | — | 2019 | Trade press |
| Meta Temple Data CenterHyperscale | Temple, United States | Under construction | — | — | Operator / official |
| Meta Tulsa Data CenterHyperscale | Tulsa, United States | Under construction | — | — | Operator / official |
| Montgomery Data CenterHyperscale | Montgomery, United States | Under construction | — | — | Operator / official |
| Project Tropical (Meta Henrico expansion)Hyperscale | United States | Planned | — | — | Trade press |
| Singapore Data Center (Tanjong Kling)Hyperscale | Singapore, Singapore | Operational | — | 2022 | Trade press |
| Stanton Springs Data CenterHyperscale Cooling: Air or free cooling | United States | Operational | — | — | Operator / official |
Market position
How Meta compares
Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.
- In United States, Meta ranks #3 of 171 tracked operators by capacity, with 10% of the country’s tracked MW.
- United States has 1,315 tracked data centers from 171 operators: 11,392 MW operational and 66,365 MW under construction or planned.
- Industrial electricity in United States costs 86.2 USD/MWh (2025, latest official figure).
- In Ireland, Meta is one of 15 operators we track.
- In Sweden, Meta is one of 17 operators we track.
- Our Deal Tracker lists 1 deal(s) naming Meta, the latest on 13 October 2026.
Data center operators in United States
| Operator | Facilities | Operational MW | Pipeline MW |
|---|---|---|---|
| Tract | 19 | — | 17,275 MW |
| PowerHouse Data Centers | 17 | 60 MW | 8,807 MW |
| Vantage Data Centers | 22 | 194 MW | 3,804 MW |
| Beale Infrastructure | 6 | — | 3,650 MW |
| OpenAI | 1 | — | 3,200 MW |
| Aligned Data Centers | 29 | 154 MW | 2,648 MW |
| STACK Infrastructure | 20 | 480 MW | 1,848 MW |
| QTS | 47 | 1,977 MW | 283 MW |
All data centers in United States Power and policy in United States
Data center operators in Ireland
| Operator | Facilities | Operational MW | Pipeline MW |
|---|---|---|---|
| Red Admiral DC | 1 | — | 250 MW |
| Echelon Data Centres | 2 | — | 200 MW |
| Art Data Centres | 1 | — | 200 MW |
| Herbata | 1 | — | 180 MW |
| Amazon Web Services | 6 | — | 169 MW |
| Huntstown Power Company | 1 | — | 150 MW |
| EdgeConneX | 4 | 25 MW | 37 MW |
| Pure DC | 3 | 14 MW | 40 MW |
All data centers in Ireland Power and policy in Ireland
Data center operators in Sweden
| Operator | Facilities | Operational MW | Pipeline MW |
|---|---|---|---|
| Brookfield | 1 | — | 750 MW |
| EcoDataCenter | 3 | 80 MW | 400 MW |
| atNorth | 3 | 12 MW | 330 MW |
| Conapto | 4 | 39 MW | — |
| Hydro66 | 1 | 19.2 MW | — |
| STACK Infrastructure | 1 | 18 MW | — |
| evroc | 1 | — | 18 MW |
| Bahnhof | 6 | — | 12 MW |
All data centers in Sweden Power and policy in Sweden
Deals naming Meta
- Meta → Data center and technology campus, Mason County (Maysville), Kentucky Land / campus $10.00B
How we build the tracker
- Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
- A second analyst re-opens each source before a facility is published.
- Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
- Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
- Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
- Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
- Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.
Questions
How many data centers does Meta operate?
DC Market Insights tracks 36 Meta data center(s) in 6 countries as of October 2026: 20 operational, 13 under construction and 3 planned.
Where is Meta headquartered?
Meta is headquartered in Menlo Park, United States. Ownership: Listed on Nasdaq (META).
Which other companies operate data centers in United States?
Besides Meta, the largest operators we track in United States by capacity are Tract, PowerHouse Data Centers, Vantage Data Centers, Beale Infrastructure and OpenAI. The United States page lists all 171 operators.
What rules apply to data centers in United States?
Our Power & Policy Tracker lists 15 government actions on data centers and power in United States, including 0 restriction(s) and 1 incentive scheme(s) in force.
Where does this data come from?
Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.
What does the MW figure mean?
We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.
How exact are the map locations?
When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.
How often is it updated?
The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.
Can I get the data in Excel?
Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.
Global capacity
How much data center capacity is installed worldwide?
Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.
Need the full list, or a capacity view of one market?
Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.
