Every data center in Canada that we have verified: operator, location, status and capacity, each checked against its source.
By Amit JainReviewed by Deepti AgrawalUpdated 26 Nov 2026
In short
As of 26 November 2026, DC Market Insights tracks 100 data centers in Canada run by 22 operators: 85 operational, 8 under construction and 7 planned. Stated operational capacity is 508 MW, with a further 1,367 MW under construction and 8,510 MW planned. eStruxture holds the largest share of tracked operational capacity (29%).
100Facilities tracked
22Operators
508 MWOperational (85 sites)
1,367 MWUnder construction (8 sites)
8,510 MWPlanned (7 sites)
MW = IT capacity where the source states it, otherwise total capacity. 38 of 100 facilities have a stated capacity; the others are counted as sites only.
OperationalUnder constructionPlannedPin = exact site location; dot = city (approximate)
Market snapshot
Canada data center market: key facts
Capacity under construction or planned (9,877 MW) is 19.4 times the operational base of 508 MW.
The three largest operators by operational capacity, eStruxture, Vantage Data Centers and Cologix, hold 71% of tracked operational MW.
O'Leary Ventures has the largest development pipeline in Canada: 7,500 MW under construction or planned.
The largest operational facility we track is Vantage Quebec City (QC2) campus (Vantage Data Centers, Quebec City) at 86 MW.
The largest project in the pipeline is Wonder Valley AI data centre industrial park by O'Leary Ventures (7,500 MW, planned).
Grande Prairie is the largest cluster: 1 of 100 facilities and 72% of tracked capacity.
By type, the tracker lists 77 colocation, 15 hyperscale and 7 other facilities.
38 of 100 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational508 MW
Under construction1,367 MW
Planned8,510 MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Largest operators in Canada by tracked capacity, MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Market context
What shapes the Canada data center market
Policy, power, land and demand, each statement checked against its source. Reviewed 17 October 2026. Government sources are linked; the full source list comes with the Excel data.
Canada has no national data centre law; where data centres can connect and what they pay is set province by province. Alberta limits grid access (1,200 MW interim cap, priority for projects with their own generation) and has legislated a levy on large sites; British Columbia allocates up to 400 MW to AI and data centres by competition; Québec requires government authorization for loads of 5 MW or more and Hydro-Québec has asked for a dedicated data centre rate; Ontario has proposed ministerial approval for grid connections. Federally, a $2 billion Sovereign AI Compute Strategy funds AI data centre capacity. About 64% of power is renewable. ISED – Canadian Sovereign AI Compute Strategy
Policy and incentives
The federal Canadian Sovereign AI Compute Strategy commits $2 billion over five years, including an AI Compute Challenge of up to $700 million to build or expand commercial AI-specific data centres in Canada. ISED – Canadian Sovereign AI Compute Strategy
Alberta's Bill 12 (2025) introduces a levy of up to 2% on the value of computer equipment in data centres of 75 MW or more, deductible from provincial corporate income tax, with a lower rate for sites that bring their own power. Alberta – Bill 12 fact sheet
Ontario proposed (Aug 2026) an economic and strategic assessment for new data centres covering jobs and investment, data sovereignty with a preference for Canadian-owned facilities, and community benefits. Environmental Registry of Ontario 026-0853
Power and grid
Alberta's AESO set an interim 1,200 MW limit for large-load connections that is now fully taken, against about 19,565 MW of data centre requests (30 Jul 2026); the Data Centre Regulation (June 2026) prioritizes projects tethered to new generation or storage. Government of Alberta – Is Alberta's grid ready?
British Columbia requires AI and data centre projects to win a competitive BC Hydro process for clean power, with allocation targets of up to 400 MW in the first two years (opened 30 Jan 2026). BC Gov News
In Québec, new projects or load additions of 5 MW or more need government authorization before connection; Hydro-Québec asked the Régie de l'énergie in Feb 2026 for a dedicated data centre rate (tarif CD) from 1 Nov 2026. Gouvernement du Québec – Autorisation d'un projet électrique
Ontario proposed (Sep 2025) that covered data centres obtain approval from the Minister of Energy and Mines before connecting to the grid. Environmental Registry of Ontario 025-1001
Sustainability, water and climate
Hydro, wind and solar supplied 63.9% of Canada's 622.2 million MWh of electricity in 2024 (preliminary). Statistics Canada – The Daily
Canada's electricity generation intensity was 100 g CO2e/kWh in 2022, 55% below the 2005 level of 220 g CO2e/kWh. Canada Energy Regulator
Our Deal Tracker lists 10 deals in Canada since January 2026, with $12.00B in disclosed value.
Nocera, Inc. → BitRock Ltd. (Calgary AI data center developer, ~44% stake) M&A$22.0M · 10 MW
Genius Group Limited, FingerMotion, Inc. → BlueFlare Energy Solutions Brooks Corridor Campus Program (up to 100 MW powered land and colocation campuses), first site Brooks Campus No. 1 JV / partnership · 100 MW
PowerBank Corporation joint development partner (Toronto energy developer, not named) → Site for 2 MW modular AI data center (about 1.77 MW IT), Ontario Land / campus · 2 MW
Unnamed frontier AI developer (tenant) → EverWind Point Tupper data centre campus, Nova Scotia (95 MW initial, 420 MW full) Land / campus · 420 MW
Bell Canada (BCE) – Bell AI Fabric → Bell AI data centre project, Regina area, Saskatchewan (expanded to pathway to 1.2 GW) Land / campus · 1,200 MW
Every facility with operator, city, status, capacity, year and source, plus summaries and the status history. Built from the live tracker.
Data Centers in Canada: Capacity Sheet
100 facilities
Every tracked data center in Canada with operator, city, status, MW, year and source, plus summaries by city and operator and the status history. Excel, updated weekly.
Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
A second analyst re-opens each source before a facility is published.
Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.
Questions
How many data centers are there in Canada?
DC Market Insights tracks 100 data centers in Canada as of November 2026: 85 operational, 8 under construction and 7 planned, run by 22 operators. The count grows as we verify more sites.
What is the data center capacity of Canada?
Tracked operational capacity in Canada is 508 MW, with 1,367 MW under construction and 8,510 MW planned. These totals use the capacity each source states (IT load where given) and cover 38 of 100 tracked facilities.
Which companies operate the most data center capacity in Canada?
By tracked operational capacity, the largest operators in Canada are eStruxture (148 MW), Vantage Data Centers (127 MW) and Cologix (86.4 MW).
Where are the data centers in Canada located?
The largest clusters by tracked capacity are Grande Prairie (1 facilities), Edmonton (2 facilities) and Regina (1 facilities). The map above shows every site.
Which new data centers are being built in Canada?
We track 1,367 MW under construction and 8,510 MW planned. The largest projects are Wonder Valley AI data centre industrial park by O'Leary Ventures (7,500 MW), Meta Sturgeon County Data Center (1,000 MW) and Beacon AI Centers Heartland data centre (920 MW).
Where does this data come from?
Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.
What does the MW figure mean?
We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.
How exact are the map locations?
When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.
How often is it updated?
The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.
Can I get the data in Excel?
Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.
Global capacity
How much data center capacity does Canada have?
Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.