TeraWulf Data Centers

Data centers operated by TeraWulf that we have verified: location, status and capacity, each checked against its source.

In short

As of 21 November 2026, DC Market Insights tracks 9 data centers operated by TeraWulf in 1 country, of which 4 are operational. Stated operational capacity is 102 MW, with a further 336 MW under construction and 1,721 MW planned. The pipeline is 20.2 times the capacity already operating.

9Facilities tracked
1Countries
102 MWOperational (4 sites)
336 MWUnder construction (2 sites)
1,721 MWPlanned (3 sites)

MW = IT capacity where the source states it, otherwise total capacity. 9 of 9 facilities have a stated capacity; the others are counted as sites only.

Lake Mariner CB-1 · TeraWulf · Barker (approximate location)Lake Mariner CB-2 · TeraWulf · Barker (approximate location)Lake Mariner CB-3 · TeraWulf · Barker (approximate location)Lake Mariner CB-4 · TeraWulf · Barker (approximate location) · Cooling: Direct liquidLake Mariner CB-5 · TeraWulf · Barker (approximate location) · Cooling: Direct liquid · Owned: TeraWulf-built and operated building leased to Fluidstack (same terms as CB-3/CB-4 Fluidstack leases)TeraWulf Lake Hawkeye (Cayuga site) · TeraWulf · Lansing (approximate location)TeraWulf Justified Data Campus · TeraWulf · Hawesville (approximate location)TeraWulf Muskie Data Campus · TeraWulf · Grayson (approximate location)Lake Mariner WULF Den · TeraWulf · Barker (exact location) · Owned: TeraWulf owns and operates the Lake Mariner campus (land held under long-term lease from Somerset Operating Co.)
Operational Under construction Planned Pin = exact site location; dot = city (approximate) Select a country on the map to open its page.

Market snapshot

TeraWulf data centers: key facts

About TeraWulf

TeraWulf (Nasdaq: WULF) develops, owns and operates power-backed data center campuses in the United States for AI and HPC tenants. Its Lake Mariner Data Campus in Barker, New York had 102 MW of energized critical IT HPC capacity at 30 September 2026, with 336 MW more under construction in CB-4 and CB-5 and 438 MW contracted in total. It is developing the Justified (Hawesville, about 401 MW IT leased to Anthropic) and Muskie (Grayson, up to 1 GW contracted power) campuses in Kentucky, plus the Lake Hawkeye site in Lansing, New York (about 320 MW IT potential).

Headquarters
Easton, Maryland, United States
Ownership
Publicly listed on Nasdaq (ticker WULF)
Tracked footprint
9 facilities in 1 country
Website
terawulf.com

Data center business

  • Lake Mariner Data Campus, Barker, New York, sits on the site of a retired coal-fired power plant; operations began in March 2022. At 30 September 2026 it had 102 MW of energized critical IT HPC capacity and 145 MW of legacy bitcoin mining capacity. About 500 MW of aggregate gross capacity is expected to be energized by early 2027, with a planned expansion to about 750 MW backed by an approved NYISO System Impact Study. 90 MW of the campus power comes under a ten-year NYPA agreement signed in February 2022.
  • Lake Mariner capacity is contracted to two tenants through subsidiaries: La Lupa Data LLC delivers 60 MW of critical IT to Core42 under leases signed in December 2024 (fully in service by 30 September 2026); Akela Data LLC provides 378 MW of critical IT to Fluidstack under three leases signed in August 2025, backed by Google credit support. Together they total 438 MW of contracted critical IT HPC capacity.
  • Building-level critical IT capacity at Lake Mariner (company table): WULF Den 2 MW, CB1 16 MW, CB2 42 MW, CB3 42 MW, CB4 168 MW and CB5 168 MW.
  • Justified Data Campus, Hawesville (Hancock County), Kentucky: a brownfield former industrial site with more than 250 buildable acres, an energized on-site substation and high-voltage transmission. TeraWulf signed a 20-year lease with Anthropic for about 401 MW of critical IT, about USD 19 billion of contracted revenue over the initial term. The Kentucky PSC approved a Retail Electric Service Agreement for up to 482 MW through Kenergy and Big Rivers on 21 August 2026.
  • Muskie Data Campus, Grayson, Kentucky: about 308 acres acquired in May 2026 through the purchase of Industrial Equity Partners LLC. Contracted electric service with Kentucky Power was raised from 500 MW to 1,000 MW (subject to PSC approval); the first 500 MW is expected to ramp from Q4 2028 and the second 500 MW in 2029. Kentucky Power will build a 345 kV substation tied to the 765 kV network.
  • Lake Hawkeye (Cayuga site), Lansing, New York: about 183 acres under an 80-year ground lease signed 12 August 2025. Subject to permitting and site development it could support up to 400 MW of gross capacity, about 320 MW of critical IT load; operations are not contemplated until about 2029.
  • Chesapeake Data Campus, Morgantown, Maryland: TeraWulf agreed to buy the Morgantown generating station (about 210 MW of operating generation). FERC authorized the pending acquisition on 29 July 2026; subject to the remaining closing conditions the site could scale to up to 1 GW, with first data center operations contemplated for 2030.

Recent updates

  • Q3 2026 results: revenue USD 76.2 million, of which USD 63.0 million HPC lease revenue (about 83%). CB-4 remains on track for phased delivery in Q4 2026 and CB-5 for early 2027. Cash, cash equivalents and restricted cash about USD 2.4 billion at quarter end.
  • Google signed credit support agreements for project debt backing the Anthropic leases at Justified, and TeraWulf signed a definitive GMP-basis EPC agreement with Fluor for three data center buildings there; phased ready-for-service is expected from late 2027 to Q2 2028.
  • TeraWulf raised contracted power at the Muskie Data Campus from 500 MW to 1 GW under an amended agreement with Kentucky Power, moving the second 500 MW phase from 2030 to 2029, subject to PSC approval.
  • The Kentucky Public Service Commission approved the Retail Electric Service Agreement for up to 482 MW at the Justified Data Campus in Hancock County (order of 21 August 2026).
  • CB-3 at Lake Mariner was delivered in early July 2026, lifting revenue-generating critical IT capacity from 81 MW to 102 MW and making USD 600 million of Google credit support for Fluidstack's lease obligations effective.
  • TeraWulf signed a 20-year lease with Anthropic at Justified (about USD 19 billion over the initial term) and agreed to sell its 50.1% interest in the Abernathy Joint Venture (168 MW critical IT campus in Texas) to an investor group led by Fluidstack for about USD 530 million.
  • TeraWulf acquired the Muskie Data Campus in Eastern Kentucky from Industrial Equity Partners, a site expected to support more than 1 GW of data center capacity over time.

Company details checked against company and official sources, 21 Nov 2026.

  • Capacity under construction or planned (2,057 MW) is 20.2 times the operational base of 102 MW.
  • Its largest operational site is Lake Mariner CB-2 in Barker, United States at 42 MW.
  • The largest project in the pipeline is TeraWulf Muskie Data Campus (1,000 MW, planned).
Capacity by status, MW
Operational102 MW
Under construction336 MW
Planned1,721 MW

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

TeraWulf development pipeline

Under construction and planned facilities with a stated capacity, largest first. 336 MW under construction and 1,721 MW planned in total.

ProjectLocationStatusTypeCapacity
TeraWulf Muskie Data CampusTeraWulf Grayson, United States Planned Hyperscale 1,000 MW
TeraWulf Justified Data CampusTeraWulf Hawesville, United States Planned Hyperscale 401 MW
TeraWulf Lake Hawkeye (Cayuga site)TeraWulf Lansing, United States Planned Hyperscale 320 MW
Lake Mariner CB-4TeraWulf Barker, United States Under construction Hyperscale 168 MW
Lake Mariner CB-5TeraWulf Barker, United States Under construction Hyperscale 168 MW

Facilities

9 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
TeraWulf Muskie Data CampusHyperscale
History · 2 deals
  1. Announced
  2. Planned
  3. Planned
  • TeraWulf → Muskie Data Campus, eastern Kentucky (~285 acres, up to 1 GW over time)
  • TeraWulf → Muskie Data Campus, eastern Kentucky (contracted power raised from 500MW to 1GW)
  • All deals in the Deal Tracker
Grayson, United States Planned 1,000 MW total — Operator / official
TeraWulf Justified Data CampusHyperscale
History · 2 deals
  1. Announced
  2. Planned
  3. Planned
  4. Planned
  • Anthropic → Justified Data campus, Hawesville, Kentucky (~401 MW critical IT)
  • Google LLC (credit support provider) → TeraWulf Justified Data Campus project financing, Hawesville, Kentucky (Anthropic lease)
  • All deals in the Deal Tracker
Hawesville, United States Planned 401 MW IT — Operator / official
TeraWulf Lake Hawkeye (Cayuga site)Hyperscale
History
  1. Planned
  2. Planned
Lansing, United States Planned 320 MW IT — Operator / official
Lake Mariner CB-4Hyperscale Cooling: Direct liquid Barker, United States Under construction 168 MW IT — Operator / official
Lake Mariner CB-5Hyperscale Cooling: Direct liquid · Owned: TeraWulf-built and operated building leased to Fluidstack (same terms as CB-3/CB-4 Fluidstack leases) Barker, United States Under construction 168 MW IT — Operator / official
Lake Mariner CB-2Hyperscale Barker, United States Operational 42 MW IT — Operator / official
Lake Mariner CB-3Hyperscale
History
  1. Under construction
  2. Operational
  3. Operational
Barker, United States Operational 42 MW IT — Operator / official
Lake Mariner CB-1Hyperscale Barker, United States Operational 16 MW IT — Operator / official
Lake Mariner WULF DenHyperscale Owned: TeraWulf owns and operates the Lake Mariner campus (land held under long-term lease from Somerset Operating Co.) Barker, United States Operational 2 MW IT — Operator / official

Market position

How TeraWulf compares

Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.

  • In United States, TeraWulf ranks #10 of 171 tracked operators by capacity, with 2.8% of the country’s tracked MW.
  • United States has 1,315 tracked data centers from 171 operators: 11,392 MW operational and 66,365 MW under construction or planned.
  • Industrial electricity in United States costs 86.2 USD/MWh (2025, latest official figure).
  • Our Deal Tracker lists 2 deal(s) naming TeraWulf, the latest on 4 November 2026.

Data center operators in United States

Tracked facilities1,315171 operators
Operational capacity11,392 MW66,365 MW in the pipeline
TeraWulf rank by capacity#10of 171 operators · 2.8%
Industrial power price86.2 USD/MWh2025
OperatorFacilitiesOperational MWPipeline MW
Tract19—17,275 MW
PowerHouse Data Centers1760 MW8,807 MW
Meta311,000 MW7,000 MW
Vantage Data Centers22194 MW3,804 MW
Beale Infrastructure6—3,650 MW
OpenAI1—3,200 MW
Aligned Data Centers29154 MW2,648 MW
STACK Infrastructure20480 MW1,848 MW

All data centers in United States Power and policy in United States

Deals naming TeraWulf

  • Google LLC (credit support provider) → TeraWulf Justified Data Campus project financing, Hawesville, Kentucky (Anthropic lease) Financing
  • TeraWulf → Muskie Data Campus, eastern Kentucky (contracted power raised from 500MW to 1GW) Power deal

Open in the Deal Tracker

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
  • Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers does TeraWulf operate?

DC Market Insights tracks 9 TeraWulf data center(s) in 1 country as of November 2026: 4 operational, 2 under construction and 3 planned.

Where is TeraWulf headquartered?

TeraWulf is headquartered in Easton, Maryland, United States. Ownership: Publicly listed on Nasdaq (ticker WULF).

Which other companies operate data centers in United States?

Besides TeraWulf, the largest operators we track in United States by capacity are Tract, PowerHouse Data Centers, Meta, Vantage Data Centers and Beale Infrastructure. The United States page lists all 171 operators.

What rules apply to data centers in United States?

Our Power & Policy Tracker lists 15 government actions on data centers and power in United States, including 0 restriction(s) and 1 incentive scheme(s) in force.

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Global capacity

How much data center capacity is installed worldwide?

Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.