Every data center in United States that we have verified: operator, location, status and capacity, each checked against its source.
By Amit JainReviewed by Deepti AgrawalUpdated 21 Nov 2026
In short
As of 21 November 2026, DC Market Insights tracks 1,315 data centers in United States run by 171 operators: 856 operational, 130 under construction and 329 planned. Stated operational capacity is 11,392 MW, with a further 20,715 MW under construction and 45,650 MW planned. QTS holds the largest share of tracked operational capacity (17%).
1,315Facilities tracked
171Operators
11,392 MWOperational (856 sites)
20,715 MWUnder construction (130 sites)
45,650 MWPlanned (329 sites)
MW = IT capacity where the source states it, otherwise total capacity. 492 of 1,315 facilities have a stated capacity; the others are counted as sites only.
OperationalUnder constructionPlannedPin = exact site location; dot = city (approximate)
Market snapshot
United States data center market: key facts
Capacity under construction or planned (66,365 MW) is 5.8 times the operational base of 11,392 MW.
The three largest operators by operational capacity, QTS, Centersquare and Crusoe, hold 38% of tracked operational MW.
Tract has the largest development pipeline in United States: 17,275 MW under construction or planned.
The largest operational facility we track is Crusoe Abilene Stargate Campus (Crusoe, Abilene) at 1,200 MW.
The largest project in the pipeline is Richland Parish Data Center (Hyperion) by Meta (5,000 MW, under construction).
Northeast Louisiana is the largest cluster: 1 of 1,315 facilities and 6.4% of tracked capacity.
By type, the tracker lists 760 colocation, 510 hyperscale and 19 edge facilities.
22 facilities publish a PUE figure; the lowest is 1.15 at Evocative DAL1 Plano (Evocative) and the median is 1.40.
492 of 1,315 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational11,392 MW
Under construction20,715 MW
Planned45,650 MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Capacity by year opened or expected, MW
OperationalUnder construction or planned Facilities with a stated year and capacity only.
Largest operators in United States by tracked capacity, MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Market context
What shapes the United States data center market
Policy, power, land and demand, each statement checked against its source. Reviewed 7 October 2026. Government sources are linked; the full source list comes with the Excel data.
Data centers consumed about 4.4% of total U.S. electricity in 2023, according to a Lawrence Berkeley National Laboratory report released by the U.S. Department of Energy on December 20, 2024. The same report found total data center electricity use rose from 58 TWh in 2014 to 176 TWh in 2023. U.S. Department of Energy
Policy and incentives
Virginia exempts computer equipment and enabling software bought or leased for data centers from state retail sales and use tax (Code of Virginia 58.1-609.3), for facilities with at least $150 million of new capital investment and 50 new jobs paying 1.5 times the local average wage; thresholds fall to $70 million and 10 jobs in distressed localities. Virginia Legislative Information System, Code of Virginia
Under the Code of Virginia 58.1-609.3, the base data center sales and use tax exemption runs from July 1, 2010 to June 30, 2035, with extensions to June 30, 2040 and June 30, 2050 tied to cumulative investment of $35 billion with 1,000 jobs and $100 billion with 2,500 jobs. Virginia Legislative Information System, Code of Virginia
The Texas Comptroller administers a state sales tax exemption for qualifying data centers of at least 100,000 square feet whose owners or occupants commit to at least 20 qualifying jobs in the county and a $200 million capital investment over five years; the exemption lasts 10 years, or 15 years for investment of at least $250 million. Texas Comptroller of Public Accounts
The Illinois Department of Commerce and Economic Opportunity (DCEO) states that, following a Governor's directive of June 5, 2026, it no longer processes applications for the state data center incentive program as of July 1, 2026. The program required at least $250 million of capital investment over 60 months and 20 new full-time jobs. Illinois Department of Commerce and Economic Opportunity
Executive Order 14318, signed July 23, 2025, defines data center projects as facilities requiring more than 100 MW of new load dedicated to AI inference, training, simulation or synthetic data generation, and directs expedited federal permitting for qualifying projects, including those with at least $500 million in committed capital expenditures. The White House
Power and grid
Texas Senate Bill 6 (89th Legislature, 2025) adds Section 37.0561 to the Utilities Code, requiring the Public Utility Commission of Texas to adopt standards for interconnecting large load customers in the ERCOT power region, with a demand threshold of 75 megawatts unless the commission determines a lower threshold is necessary. Texas Legislature Online
On December 18, 2025, the Federal Energy Regulatory Commission (FERC) directed PJM Interconnection, in Docket EL25-49-000 et al., to revise its tariff so that transmission customers serving load co-located with generating facilities can choose from several transmission service options. Federal Energy Regulatory Commission
On June 18, 2026, the Federal Energy Regulatory Commission issued show cause orders to six grid operators (PJM, MISO, SPP, CAISO, ISO-NE and NYISO), giving them 60 days to justify their tariffs as just and reasonable without large-load provisions or to file tariff changes. Federal Energy Regulatory Commission
Oregon House Bill 3546 (2025) requires the Public Utility Commission of Oregon to create a separate classification of service, with its own tariff schedule, for large energy use facilities using 20 MW or more and primarily providing services under NAICS code 518210, and requires their service contracts to run 10 years or longer. Oregon State Legislature (OLIS)
According to the U.S. Energy Information Administration, annual average U.S. retail electricity prices in 2025 were 8.62 cents per kWh for industrial customers and 13.41 cents per kWh for commercial customers; the overall 2025 average of 13.63 cents per kWh is cited to preliminary Electric Power Monthly data. U.S. Energy Information Administration
Land, zoning and sites
According to Loudoun County, Virginia, much data center development in the county was permitted by right until March 2025. The Board of Supervisors has approved changes to the Comprehensive Plan and zoning so that data centers now require an approved special exception application, eliminating data centers as a by-right use in the county. Loudoun County Government – Data Centers Land Use FAQ
On September 10, 2024, the Fairfax County, Virginia Board of Supervisors approved a data center zoning ordinance amendment requiring data center buildings to be at least 200 feet from adjacent residential lot lines and at least one mile from a Metro station. Fairfax County Government News
In July 2025 the U.S. Department of Energy selected four federal sites for AI data center and energy infrastructure development: Idaho National Laboratory, Oak Ridge Reservation, Paducah Gaseous Diffusion Plant and Savannah River Site. U.S. Department of Energy
Demand and connectivity
According to a U.S. Department of Energy release of December 20, 2024 on a Lawrence Berkeley National Laboratory report, total U.S. data center electricity usage rose from 58 TWh in 2014 to 176 TWh in 2023. U.S. Department of Energy
The U.S. Census Bureau reported in January 2025, citing Bureau of Labor Statistics data, that the number of people working in U.S. data centers grew from 306,000 in 2016 to 501,000 in 2023, an increase of more than 60%. U.S. Census Bureau – America Counts
In an August 7, 2025 release on new submarine cable rules, the Federal Communications Commission stated there are 90 FCC-licensed submarine cable systems and that submarine cable systems carry roughly 99% of global internet traffic. Federal Communications Commission
The Federal Communications Commission reported in August 2025 that U.S. cable landing licensees had reported more than 5.3 million Gbps of available submarine cable capacity as of December 2022. Federal Communications Commission
Sustainability, water and climate
The U.S. Energy Information Administration reports that renewable energy sources supplied about 24% of total U.S. utility-scale electricity generation in 2025, when total utility-scale generation was about 4.43 trillion kWh. U.S. Energy Information Administration – Electricity in the U.S.
The U.S. Energy Information Administration reports that natural gas was the largest source of U.S. utility-scale electricity generation in 2025 at about 41%, followed by nuclear at about 18% and coal at about 17%. U.S. Energy Information Administration – Electricity in the U.S.
The U.S. Environmental Protection Agency's eGRID database with 2023 data, released in January 2025 and revised in June 2025, gives a U.S. average CO2 output emission rate of 767.209 lb/MWh for electricity generation. U.S. Environmental Protection Agency – eGRID Summary Data
Minnesota's 2025 data center law (2025 First Special Session, Chapter 12, H.F. 16) provides that when a data center contacts the state Department of Natural Resources about a project likely to consume more than 100 million gallons of water annually, the DNR may request information from the data center to assess the consumption's impact. Minnesota House Research – Act Summary, Chapter 12
Meta Lebanon Data CenterMeta
Cooling: Direct liquid · Owned (self-build): (Meta states in general terms that it designs and builds its own infrastructure; the page does not state site ownership)
History
Under construction
Under construction
Lebanon
Under construction
1,000 MW
—
Operator / official
Meta New Albany Data CenterMeta
Cooling: Hybrid · Owned (self-build): (Meta's own buildings) plus leased capacity from strategic partners; Meta does not name the partners
History
The Barn (Stargate Michigan)Related Digital
Cooling: Chilled water, dry coolers · Leased in colocation: developed by Related Digital (developer and equity provider) purpose-built exclusively for Oracle and OpenAI; delivery to Oracle
History
Vantage Lighthouse (Port Washington)Vantage Data Centers
Cooling: Direct liquid · Leased in colocation: Vantage Port Washington (Lighthouse), for Oracle and OpenAI (Stargate)
History
Every facility with operator, city, status, capacity, year and source, plus summaries and the status history. Built from the live tracker.
Data Centers in United States: Capacity Sheet
1,315 facilities
Every tracked data center in United States with operator, city, status, MW, year and source, plus summaries by city and operator and the status history. Excel, updated weekly.
Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
A second analyst re-opens each source before a facility is published.
Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.
Questions
How many data centers are there in United States?
DC Market Insights tracks 1,315 data centers in United States as of November 2026: 856 operational, 130 under construction and 329 planned, run by 171 operators. The count grows as we verify more sites.
What is the data center capacity of United States?
Tracked operational capacity in United States is 11,392 MW, with 20,715 MW under construction and 45,650 MW planned. These totals use the capacity each source states (IT load where given) and cover 492 of 1,315 tracked facilities.
Which companies operate the most data center capacity in United States?
By tracked operational capacity, the largest operators in United States are QTS (1,977 MW), Centersquare (1,203 MW) and Crusoe (1,200 MW).
Where are the data centers in United States located?
The largest clusters by tracked capacity are Northeast Louisiana (1 facilities), Northern Virginia (118 facilities) and Richmond (25 facilities). The map above shows every site.
Which new data centers are being built in United States?
We track 20,715 MW under construction and 45,650 MW planned. The largest projects are Richland Parish Data Center (Hyperion) by Meta (5,000 MW), Tract Caldwell Valley Technology Park (4,000 MW) and Project Camelia by OpenAI (3,200 MW).
Where does this data come from?
Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.
What does the MW figure mean?
We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.
How exact are the map locations?
When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.
How often is it updated?
The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.
Can I get the data in Excel?
Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.
Global capacity
How much data center capacity does United States have?
Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.