Uruguay offers a near-fully renewable grid (98% of 2025 generation) with a very low emission factor, tax-free free zones and an investment promotion regime. Google is building a data center in the Parque de las Ciencias free zone in Canelones, and in October 2026 the government signed a 500 MW data center park agreement with Solaria under the free zone regime. Presidencia de la República
Policy and incentives
Free zone users are exempt from all national taxes, existing or future, on authorized activities (Ley 15.921 of 1987, amended by Ley 19.566 of 2017); social security contributions are not exempt. IMPO – Ley 15.921
Outside free zones, projects declared 'promoted' under Ley 16.906 get IRAE (corporate income tax) relief. Decree 329/025, in force from 1 February 2026, caps the exemption at 100% of eligible investment and 90% of yearly IRAE, with up to 100% of eligible investment for projects above UI 180 million. IMPO – Decreto 329/025
The National AI Strategy 2024-2030, approved by the public sector AI and Data committee led by AGESIC, covers governance, capabilities (including infrastructure and data) and sustainable development. AGESIC
Power and grid
State utility UTE sells power under an annual tariff schedule. For 2026 (Decree 339/025, average +4.0%) the optional Large Consumer tariffs apply from 200 kW of contracted valley demand; GC3 at 31.5-63 kV charges 2.400 / 3.944 / 5.261 UYU/kWh in valley, shoulder and peak bands plus demand charges. IMPO – Decreto 339/025
Under Ley 16.832, generators may sign freely negotiated supply contracts directly with large consumers in the wholesale market run by ADME. Decree 12/026 sets the Large Consumer threshold at 1,500 kW of contracted demand and lets large consumers install their own generation under a use/connection agreement. IMPO – Decreto 12/026
Electricity generation in 2025 was 98% renewable, according to the Ministry of Industry, Energy and Mining. MIEM
Land, zoning and sites
Google's data center building is in the Parque de las Ciencias free zone, Ruta 101 km 23.5, Ciudad de la Costa, Canelones, supplied by UTE with diesel backup generators; its environmental assessment file ends in Ministry of Environment Resolution 644-2024. Ministerio de Ambiente – Observatorio Ambiental Nacional
Solaria's planned 500 MW data center park (USD 5.5 billion, plus USD 200 million for 350 MW of solar) will be spread over Canelones, San José and Florida under the free zone regime; phase 1 is 200 MW of data centers. Presidencia de la República
Building or expanding free zones and industrial parks, power plants above 10 MW and transmission lines of 150 kV or more need Prior Environmental Authorization under Decree 349/005. IMPO – Decreto 349/005
Sustainability, water and climate
The grid CO2 emission factor was 11.2 tCO2/GWh (0.0112 kgCO2/kWh) in 2025 as an annual average, with significant month-to-month variation. MIEM
The Ministry of Environment project file for Google's Canelones data center describes an air-based cooling system ('sistema de enfriamiento por aire'). Ministerio de Ambiente – Observatorio Ambiental Nacional
Ley 18.597 (2009) declares efficient energy use of national interest and requires a National Energy Efficiency Plan; it sets no data center specific efficiency rule. IMPO – Ley 18.597