Guatemala has no data-center-specific law. Data centers (above 100 kW) qualify as Grandes Usuarios and can buy power freely in the AMM wholesale market (spot average 84.5 USD/MWh in 2025, 116.5 in 2024). Incentives come from the ZDEEP free-zone regime (10-year income tax exemption) and the renewable incentive law (Decreto 52-2003). Renewables were 53.48% of 2024 generation (61.42% in H1 2025) against an 80% target; the grid factor was 0.2945 kgCO2e/kWh in 2024. A 1,400 MW tender (PEG-5) targets supply from 2030, and MEM flags transmission constraints. A cybersecurity bill is pending. CNEE – Reglamento de la Ley General de Electricidad
Policy and incentives
Guatemala has no data-center-specific law or incentive. The relevant regimes are the ZDEEP free-zone regime (10-year 100% income tax exemption, VAT and import duty exemptions for users of ZOLIC-authorised zones) and Decreto 52-2003 for renewable generation.
Decreto 52-2003 grants qualified renewable projects an income tax exemption for ten years from commercial operation, plus import duty and VAT exemption on generation equipment during pre-investment and construction (max 10 years). CNEE – Decreto 52-2003 renewable incentive law
A cybersecurity bill (Iniciativa 6347) received a favourable committee opinion on 26 Aug 2025 but was still pending in Congress in 2026; it proposes a national incident response centre and protection of critical infrastructure such as telecom networks.
Power and grid
Under the electricity law regulation, any consumer with demand above 100 kW is a Gran Usuario: not price-regulated and free to contract with generators or marketers in the Wholesale Market. CNEE – Reglamento de la Ley General de Electricidad
The AMM wholesale spot price averaged 116 USD/MWh in 2024 (105.2 in 2023, 86.2 in 2022). The average principal transmission toll was about 5 USD/kW-month in 2024. Production was 14,937 GWh in 2024. CNEE – Compendio Estadístico 2024-2025
The PEG-5-2025 tender seeks 1,400 MW of guaranteed capacity plus up to 150 MW installed, with supply starting 2030-2033 under contracts of up to 15 years.
MEM's 2026-2050 expansion plan warns that load-flow results for 2025-2026 show nodes outside operating limits, making reinforcement of generation, transmission and distribution urgent; the policy target is 1,500 km of new transmission lines. MEM – PEIG 2026-2050
Land/zoning/sites
ZDEEPs are extra-customs zones authorised by ZOLIC for industrial, commercial and service activities; named zones include Zona Franca Quetzal, Puerta del Istmo and Michatoya Pacifico.
Every project is categorised by MARN's Listado Taxativo into category A (highest impact, incl. megaprojects), B1/B2 (moderate) or C (low impact, register only), which sets the environmental assessment required before construction.