Chile's data center market is centred on the Santiago Metropolitan Region. The government's National Data Center Plan 2024-2030 put installed capacity at 198 MW, almost five times the level of ten years earlier, and expects the industry to triple in five years, with new sites pushed toward regions with solar and wind power. There is no data center law: projects go through sectoral permits and, when their power lines, generators or fuel storage trigger it, the SEIA environmental assessment. MinCiencia, Plan Nacional de Data Centers 2024-2030
Policy and incentives
The National Data Center Plan (PDATA) 2024-2030, presented by the Ministry of Science on 5 Dec 2024, has nine measures: a geospatial siting tool, a permits guide, SEIA evaluation criteria, a Clean Production Agreement, a state multi-cloud service, skills, regional AI campuses, AI compute for research and a multi-stakeholder committee. MinCiencia, PDATA 2024-2030
At the first PDATA multi-stakeholder committee (6 May 2025) the plan showed progress on 7 of its 9 measures; the siting tool crosses 71 variables and is for state use only because it holds sensitive information. MinCiencia, Acta Comité Multiactor PDATA No. 1
Law 21.770 (29 Sep 2025) replaces many sectoral permits with notices and sworn statements, allows administrative silence when deadlines lapse and lets projects with an environmental approval keep the rules in force at filing for up to 8 years. Diario Oficial, Ley 21.770
Law 21.719 on personal data protection takes effect on 1 Dec 2026; it regulates international data transfers by adequacy and safeguards. Diario Oficial, Ley 21.719
Power and grid
The government guide advises choosing land with spare substation capacity and coordinating early with the Coordinador Eléctrico Nacional; it reports more than 14,800 MW of non-conventional renewable capacity and over 7,300 MW of new renewable projects in construction or testing. MinCiencia, ¿Cómo instalar un Data Center en Chile?
The Ministry of Energy fixed the method for the National Electric System's operational and residual emission factors in Res. 61 exenta (17 Sep 2026); the annual factor is published each February. Diario Oficial, Res. 61 exenta Ministerio de Energía
Backup diesel generators of 19 kW or more fall under emission standard DS 38/2020; the stricter limits for new units now apply from 15 Sep 2028, and the Ministry of the Environment opened a review of the standard in January 2026. Diario Oficial, Res. 338 exenta MMA
Land, zoning and sites
Data centers are classed as 'energy infrastructure' and 'nuisance industry' in land-use plans, which restricts urban locations; the guide suggests mixed-use zones and expects a DIA environmental filing to take 12-18 months, a building permit 6-8 months and an archaeological permit about 18 months. MinCiencia, ¿Cómo instalar un Data Center en Chile?
The SEA criterion for data centers (Res. Ex. 20269910149, published 25 Feb 2026) explains which SEIA entry categories apply, since data centers have no category of their own. Diario Oficial, SEA extract