Proprietary data

Data Centers in Peru

Every data center in Peru that we have verified: operator, location, status and capacity, each checked against its source.

In short

As of 14 November 2026, DC Market Insights tracks 20 data centers in Peru run by 11 operators: 18 operational, 1 under construction and 1 planned. Stated operational capacity is 24.7 MW. Cirion Technologies holds the largest share of tracked operational capacity (97%).

20Facilities tracked
11Operators
24.7 MWOperational (18 sites)
—Under construction (1 site)
—Planned (1 site)

MW = IT capacity where the source states it, otherwise total capacity. 3 of 20 facilities have a stated capacity; the others are counted as sites only.

LM1 · Equinix · Lima (approximate location)LIM1 · Cirion Technologies · Santiago de Surco (approximate location)LIM2 · Cirion Technologies · Lurín (approximate location)Surco · Gtd · Santiago de Surco (approximate location)Lurín Phase 1 · Gtd · Lurín (approximate location)Claro Perú Villa El Salvador · Claro · Villa El Salvador (approximate location)Data Center Santa Catalina · ON Empresas · La Victoria (approximate location)Data Center La Molina · ON Empresas · La Molina (approximate location)Data Center del Sur (Tacna) · ON Empresas · Tacna (approximate location)Arequipa · ON Empresas · Arequipa (approximate location)Canvia San Isidro · Canvia · San Isidro (approximate location)BCRP Centro de Datos Pagos Minoristas 1 · Banco Central de Reserva del Perú · Lima (approximate location)BCRP Centro de Datos Pagos Minoristas 2 · Banco Central de Reserva del Perú · Lima (approximate location)Banco de la Nación Data Center Primario y Sala MEF · Banco de la Nación · Lima (approximate location)BBVA Perú CPD · BBVA · Lima (approximate location)Data Center Monterrico · Telefónica del Perú · Lima (approximate location)BCP Centro de Cómputo de Chorrillos · Banco de Crédito del Perú · Chorrillos (approximate location)BCP Centro de Cómputo de La Molina · Banco de Crédito del Perú · La Molina (approximate location)
Operational Under construction Planned Pin = exact site location; dot = city (approximate)

Market snapshot

Peru data center market: key facts

  • The three largest operators by operational capacity, Cirion Technologies, Equinix and ON Empresas, hold 100% of tracked operational MW.
  • The largest operational facility we track is LIM2 (Cirion Technologies, Lurín) at 20 MW.
  • Lima is the largest cluster: 18 of 20 facilities and 100% of tracked capacity.
  • By type, the tracker lists 14 colocation and 6 enterprise facilities.
  • 3 of 20 facilities have a capacity stated by their source; the totals above count only those.
Largest operators in Peru by tracked capacity, MW
Equinix0.7 MW

OperationalUnder construction or planned

Facilities by type
Colocation14
Enterprise6

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Market context

What shapes the Peru data center market

Policy, power, land and demand, each statement checked against its source. Reviewed 13 October 2026. Government sources are linked; the full source list comes with the Excel data.

Peru has no data-center-specific national law, plan or incentive. Data centers are governed by general rules: large loads above 2,500 kW buy power as free users on negotiated contracts, Law 32249 (2025) opened supply tenders to solar and wind, Law 32449 (2025) created tax-advantaged private special economic zones, and data transfers abroad follow the 2024 data protection regulation. The grid is hydro-heavy: about 63% of 2025 SEIN output came from hydro, wind and solar. MINEM, Cifras preliminares del sector eléctrico, diciembre 2025

Policy and incentives

Government bodies told reporters in 2026 that there is no national data center policy: the PCM digital secretariat said it had not designed or formulated one, and MINAM, OEFA, Senace, ANA and MTC reported no data-center-specific rules, supervision or approvals.

Law 32449 (26 Sep 2025) created Private Special Economic Zones with 0% income tax for five years, rising to 15% from year 21, for accredited industrial, assembly and service activities; data centers are not named and depend on accreditation. Ley N° 32449

The AI law regulation (DS 115-2025-PCM, 9 Sep 2025) lets the digital secretariat enable public cloud resources for public, research and academic AI users. Decreto Supremo N° 115-2025-PCM

Power and grid

SEIN electricity production was 63,115 GWh in 2025 (+2.2%): hydro 33,380 GWh, thermal 23,575 GWh, wind 3,958 GWh and solar 2,202 GWh (solar +67%). MINEM, Cifras preliminares del sector eléctrico, diciembre 2025

Consumers with maximum demand above 2,500 kW are free users that negotiate supply contracts; those between 200 kW and 2,500 kW may choose regulated or free status (DS 022-2009-EM).

Law 32249 (19 Jan 2025) lets all generation technologies compete in supply tenders and allows separate power and energy blocks; MINEM expects about US$14 billion of renewable investment. Diario Oficial El Peruano

Data and digital rules

DS 016-2024-JUS (30 Nov 2024) allows cross-border personal data transfers to countries with adequate protection or with guarantees such as model contract clauses, with transfers entered in the national register. Decreto Supremo N° 016-2024-JUS

Operators in Peru

All operators
OperatorFacilitiesOperational MWPipeline MWShare of operational MW
ON Empresas4———
Gtd3———
Cirion Technologies224 MW—97%
Telefónica del Perú2———
Banco Central de Reserva del Perú2———
Banco de Crédito del Perú2———
Equinix10.7 MW—2.8%
Claro1———
Canvia1———
Banco de la Nación1———
BBVA1———

How Peru compares in Americas

Countries in the same region, by tracked capacity. Coverage grows as each country is researched.

CountryFacilitiesOperatorsOperational MWPipeline MW
United States1,31517111,392 MW66,365 MW
Canada7818495 MW9,870 MW
Brazil16456493 MW2,645 MW
Mexico3710179 MW1,306 MW
Chile5019115 MW1,029 MW
Argentina151414.5 MW920 MW
Uruguay95—500 MW
Colombia291814.8 MW183 MW
Guatemala1082.9 MW52 MW
Peru201124.7 MW—
Ecuador1261 MW16 MW
Panama753.5 MW—

Facilities

20 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
LIM2Cirion Technologies
History
  1. Under construction
  2. Operational
  3. Under construction
  4. Operational
Lurín Operational 20 MW total — Operator / official
LIM1Cirion Technologies Santiago de Surco Operational 4 MW total — Operator / official
LM1Equinix Lima Operational 0.7 MW total — Operator / official
ArequipaON Empresas Arequipa Operational — — Operator / official
Banco de la Nación Data Center Primario y Sala MEFBanco de la Nación Lima Operational — — Operator / official
BBVA Perú CPDBBVA Lima Operational — — Operator / official
BCP Centro de Cómputo de ChorrillosBanco de Crédito del Perú Chorrillos Operational — — Operator / official
BCP Centro de Cómputo de La MolinaBanco de Crédito del Perú La Molina Operational — — Operator / official
BCRP Centro de Datos Pagos Minoristas 1Banco Central de Reserva del Perú Lima Operational — — Operator / official
BCRP Centro de Datos Pagos Minoristas 2Banco Central de Reserva del Perú Lima Operational — — Operator / official
Canvia San IsidroCanvia San Isidro Operational — 2023 Trade press
Claro Perú Villa El SalvadorClaro Villa El Salvador Operational — — Operator / official
Data Center del Sur (Tacna)ON Empresas
History
  1. Operational
  2. Operational
  3. Operational
Tacna Operational — 2019 Operator / official
Data Center La MolinaON Empresas
History
  1. Under construction
  2. Under construction
  3. Under construction
  4. Under construction
La Molina Under construction — — Operator / official
Data Center MonterricoTelefónica del Perú Lima Operational — — Operator / official
Data Center Santa CatalinaON Empresas
History
  1. Operational
  2. Operational
  3. Operational
La Victoria Operational — 2020 Operator / official
DC LinceTelefónica del Perú Lince Operational — — Trade press
Lurín Phase 1Gtd Lurín Operational — 2024 Operator / official
Lurín Phase 2Gtd Lurín Planned — — Trade press
SurcoGtd Santiago de Surco Operational — 2018 Operator / official

Get the data

Every data center in Peru, in Excel

Every facility with operator, city, status, capacity, year and source, plus summaries and the status history. Built from the live tracker.

All countries

Global Data Center Database: annual licence

3,314 facilities

Every facility in the tracker worldwide, in Excel, with sources and status history. A fresh file every month for a year.

Request a quote

Scoped to the markets and fields you need. Quote within one business day.

Custom cut

One operator, one city, a capacity pipeline or a site-selection shortlist, prepared by our analysts.

Talk to an analyst

Free updates: data centers in Peru

Leave your work email and our team will send you new facilities, status changes and deals for this market, each checked against its source.

Request a quote

Peru

Tell us what you need. We reply by email with scope, delivery date and a quote, usually within one business day.

Contact Form

Your data is safe with us

  • Your details stay private. We never sell or share them.
  • Used only to reply to your message
  • No spam: we only send what you asked for
  • Encrypted (SSL) form, handled by our own team

Privacy Policy

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
  • Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers are there in Peru?

DC Market Insights tracks 20 data centers in Peru as of November 2026: 18 operational, 1 under construction and 1 planned, run by 11 operators. The count grows as we verify more sites.

What is the data center capacity of Peru?

Tracked operational capacity in Peru is 24.7 MW, with — under construction and — planned. These totals use the capacity each source states (IT load where given) and cover 3 of 20 tracked facilities.

Which companies operate the most data center capacity in Peru?

By tracked operational capacity, the largest operators in Peru are Cirion Technologies (24 MW) and Equinix (0.7 MW).

Where are the data centers in Peru located?

The largest clusters by tracked capacity are Lima (18 facilities), Arequipa (1 facilities) and Tacna (1 facilities). The map above shows every site.

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Global capacity

How much data center capacity is installed worldwide?

Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.

Open the Global Capacity Tracker

Need the full list, or a capacity view of one market?

Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.

Talk to an analyst

Request a quote

Data Center Map data

Tell us the markets, companies or sites and the fields you need. A senior analyst replies with scope, delivery date and a quote, usually within one business day.

Contact Form

Your data is safe with us

  • Your message goes straight to our research team
  • Your details stay private. We never sell or share them.

Privacy Policy