How much data center capacity Canada has installed, how it compares with the rest of North America, and what our trackers show about its sites, operators, deals and rules.
Canada data center capacity at a glance
Canada had about 1.8 GW of installed data center capacity (IT load) at the end of 2025, by our estimate. That is about 4% of the capacity in North America and puts Canada at number 6 of the 33 countries in our global model. Our Data Center Tracker holds 100 sites in Canada run by 22 operators: 85 operational, 8 under construction and 7 planned. Our trackers also hold 10 verified deals and 9 government measures in force for the country.
Installed capacity is IT load, the power available to servers, storage and network. The country figure comes from the same model as the global and regional totals and is benchmarked against dated public figures. Site figures below are what each source states, often a campus’s full build-out, so they are not the same measure.
What our tracker holds for Canada
Largest tracked sites
| Site | Operator | City | Status | MW |
|---|---|---|---|---|
| Wonder Valley AI data centre industrial park | O'Leary Ventures | Municipal District of Greenview | Planned | 7,500 |
| Meta Sturgeon County Data Center | Meta | Sturgeon County | Under construction | 1,000 |
| Beacon AI Centers Heartland data centre | Beacon AI Centers | Sturgeon County | Planned | 920 |
| Bell AI Fabric Saskatchewan (Sherwood) campus | Bell Canada | Sherwood (RM) | Under construction | 300 |
| eStruxture CAL-3 | eStruxture | Rocky View County | Planned | 90 |
| Vantage Quebec City (QC2) campus | Vantage Data Centers | Quebec City | Operational | 86 IT |
| QScale Q01 Campus Building B | QScale | Lévis | Under construction | 60 IT |
| STACK TOR01 Toronto (Scarborough) | STACK Infrastructure | Toronto | Operational | 56 IT |
| Cologix MTL10 | Cologix | Longueuil | Operational | 35 |
| Compass Toronto campus (Etobicoke) | Compass Datacenters | Toronto | Operational | 30 IT |
Where the sites are
| City | Sites | Operators | MW stated, live |
|---|---|---|---|
| Toronto | 19 | 10 | 113 |
| Montreal | 16 | 4 | 97 |
| Vancouver | 11 | 4 | 11 |
| Markham | 5 | 4 | 29 |
| Calgary | 5 | 3 | 15 |
| Mississauga | 4 | 3 | 19 |
| Kamloops | 4 | 3 | 7 |
| Lévis | 3 | 2 | n/a |
Cities with the most tracked sites. MW only where a source states it.
Who runs them
| Operator | Sites | MW live | MW pipeline |
|---|---|---|---|
| O'Leary Ventures | 1 | n/a | 7,500 |
| Meta | 1 | n/a | 1,000 |
| Beacon AI Centers | 1 | n/a | 920 |
| Bell Canada | 4 | 7 | 307 |
| eStruxture | 16 | 148 | 90 |
| Vantage Data Centers | 4 | 127 | n/a |
| Cologix | 23 | 86 | n/a |
| QScale | 2 | n/a | 60 |
Operators ranked by MW stated at their tracked sites in Canada.
Power context
- Grid emission factor, 20220.1 kgCO2/kWh · Canada Energy Regulator, Provincial and Territorial Energy Profiles: Canada
- Renewable share of electricity, 202463.9 % · Statistics Canada, The Daily, Electricity supply and disposition, 2024 (preliminary), 22 Oct 2025
Rules in force
- MoratoriumOakville Interim Control By-law 2026-129 on data centres and similar high-intensity digital processing facilities
- RestrictionRocky View County Bylaw C-8766-2026: Data Centre Campus made a discretionary use in the S-DAT District
- MoratoriumRocky View County temporary moratorium on Special, Data Centre District (S-DAT) redesignation applications
- RegulationAESO connection requirements for transmission-connected data centres (TCDC Guide)
- GridData Centre Regulation (Alberta Regulation 117/2026) under the Electric Utilities Act
From government sources. Power and policy in Canada
Recent deals
- Nov 2026 · M&ABitRock Ltd. (Calgary AI data center developer, ~44% stake), 10 MW, USD 22 m
- Nov 2026 · JV / partnershipBlueFlare Energy Solutions Brooks Corridor Campus Program (up to 100 MW powered land and colocation campuses), first site Brooks Campus No. 1, 100 MW
- Oct 2026 · Land / campusSite for 2 MW modular AI data center (about 1.77 MW IT), Ontario, 2 MW
- Oct 2026 · Land / campusEverWind Point Tupper data centre campus, Nova Scotia (95 MW initial, 420 MW full), 420 MW
- Sep 2026 · Land / campusBell AI data centre project, Regina area, Saskatchewan (expanded to pathway to 1.2 GW), 1,200 MW
- Jul 2026 · Power deal250 MW capacity and energy for Meta data centre, Sturgeon County, Alberta, 250 MW
Other countries in North America
- United States50.4 GW
Installed capacity, end 2025, DC Market Insights estimate. All countries and regions
Canada in the full data pack
By year to 2035
Installed MW for Canada from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases.
Leading hubs
Live and pipeline MW for the main metro markets, with the basis of each figure.
Every tracked site
The full site list with operator, location, status, MW and source, refreshed from our tracker.
Related research on Canada
Frequently asked questions
How much data center capacity does Canada have?
We estimate about 1.8 GW of installed data center capacity (IT load) in Canada at the end of 2025, about 4% of North America and number 6 of the 33 countries in our model. This is a DC Market Insights estimate, benchmarked against dated public figures.
How many data centers are there in Canada?
Our Data Center Tracker lists 100 sites in Canada (85 operational, 8 under construction, 7 planned), run by 22 operators. Each site is verified from operator, planning or utility sources; the list grows as new sites are confirmed.
Which companies have the most tracked data center capacity in Canada?
By capacity stated at their sites (operational plus pipeline), the largest in our tracker are O'Leary Ventures, Meta, Beacon AI Centers. Site capacity is counted only where a source states it.
What rules apply to data centers in Canada?
Our Power and Policy Tracker lists 9 government measures in force for Canada, such as incentives, tariffs, grid rules and national plans, each linked to the official source.
How will Canada data center capacity grow to 2035?
The full data pack gives installed capacity for Canada by year from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases and the main metro hubs.