Proprietary data
Gtd Data Centers
Data centers operated by Gtd that we have verified: location, status and capacity, each checked against its source.
In short
As of 29 October 2026, DC Market Insights tracks 12 data centers operated by Gtd in 3 countries, of which 10 are operational.
MW = IT capacity where the source states it, otherwise total capacity. 0 of 12 facilities have a stated capacity; the others are counted as sites only.
Market snapshot
Gtd data centers: key facts
About Gtd
Gtd (Gtd Grupo Teleductos S.A.) is a Chilean telecommunications and technology group that runs a regional network of 10 data centers in Santiago, Puerto Montt, Lima (Surco and Lurin) and Medellin, six of them with Uptime Institute Tier III certification (gtd.cl, October 2026; its 2025 annual report counted 11). The data center assets sit in Gtdata Holdco SpA, 49% owned by InfraCorp (Grupo Romero) since 29 January 2026.
- Headquarters
- Santiago, Chile
- Founded
- 1979
- Ownership
- Private; Inmobiliaria e Inversiones El Coigue Limitada holds 99.39% (Casanueva family)
- Parent company
- Gtd Grupo Teleductos S.A.
- Tracked footprint
- 12 facilities in 3 countries
- Website
- gtd.cl
Data center business
- Gtd states on its data center page that it has an international network of 10 data centers, six of them certified Tier III by Uptime Institute: Panamericana, Lidice I, Lidice II, Huerfanos, Moneda and Holanda in Santiago; Puerto Montt in southern Chile; Surco and Lurin in Lima, Peru; and El Poblado in Medellin, Colombia. It quotes 99.982% availability and a colocation and connectivity network from Arica to Puerto Montt, described as ready for AI and high-performance loads.
- The July 2026 technical sheet gives the year each certified site entered operation: Lidice II (Santiago Centro) 2016, Panamericana (Conchali, Santiago) 2016, El Poblado (Medellin) 2016, Puerto Montt 2018, Surco (Lima) 2018 and Lurin (Lima) 2024. Lidice II, Panamericana, Lurin and El Poblado hold Tier III design, construction and operation awards; Puerto Montt and Surco list design and construction. Gtd counts 3 Tier III data centers in Chile, 2 in Peru and 1 in Colombia, linked by 500 Mbps MPLS.
- The 2025 annual report states 15,775 m2 of data center space and 3,758 m2 of white space in Chile, 2,632 m2 of data centers and 486 m2 of white space in Peru, and 3,399 m2 of data centers and 600 m2 of white space in Colombia (21,807 m2 in total). The same report lists 8 owned data center properties in Chile, 2 in Peru and 1 in Colombia. No megawatt capacity is published per site.
- The annual report's certification table lists Tier III design and construction for Lidice II, Panamericana, Puerto Montt, Providencia, El Poblado, Surco and Lurin, and Tier III Gold operational sustainability for Lidice II, Panamericana, El Poblado and Surco; Lidice II also holds LEED Gold and Panamericana SOC 1, SOC 2 and PCI DSS. Gtd says all its data centers run on energy from 100% renewable sources.
- Data centers are one business line of a wider group that also sells fibre broadband, TV, mobile, IT and cybersecurity services in Chile, Peru, Colombia, Ecuador, Mexico, Spain and Italy, with more than 300,000 residential, business and corporate clients and the Prat submarine fibre cable along the Chilean coast. Head office: Moneda 920, Santiago.
- Gtd won first place in the Energy Impact category of the DCD LATAM Awards 2025 for cooling optimisation at its Lidice 1 data center in Santiago, and was also recognised for design innovation at the modular Lurin data center in Peru; its 2025 annual report also records a Green Data Center certification.
Recent updates
- Gtd's July 2026 data center technical sheet shows the Lurin site in Lima in operation since 2024 with Tier III design, construction and operation certification, making it the newest of the group's six Tier III sites.
- The InfraCorp deal closed on 29 January 2026: InfraCorp became owner of 49% of Gtdata Holdco SpA for US$109,840,408, made up of a US$99,564,198 capital increase in Gtdata and a US$10,276,210 secondary sale of Gtd's shares. Gtd used the proceeds to repay debt, cutting financial debt to EBITDA from 3.18 to 2.56 times.
- On 9 October 2025 Gtd Grupo Teleductos signed a share purchase and subscription agreement with Cubo BidCo SpA, managed by InfraCorp, the infrastructure investment platform of Peru's Grupo Romero, to take 49% of Gtdata Holdco SpA, the subsidiary that holds the group's data center assets, for US$118 million subject to adjustments. Gtd and InfraCorp plan to develop the data center business in Chile, Peru and Colombia together and expand into new countries.
Company details checked against company and official sources, 29 Oct 2026.
- Chile accounts for 0% of tracked capacity (7 facilities).
- 0 of 12 facilities have a capacity stated by their source; the totals above count only those.
Facilities
12 facilities match. Each is checked against its source; source links come with the Excel data.
| Facility | Location | Status | Capacity | Year | Source |
|---|---|---|---|---|---|
| El PobladoColocation | Medellín, Colombia | Operational | — | 2016 | Operator / official |
| Gtd CayenaColocation | Barranquilla, Colombia | Planned | — | — | Trade press |
| Gtd HolandaColocation | Santiago, Chile | Operational | — | — | Operator / official |
| Gtd HuérfanosColocation | Santiago, Chile | Operational | — | — | Operator / official |
| Gtd Lídice IColocation | Santiago, Chile | Operational | — | — | Operator / official |
| Gtd Lídice IIColocation | Santiago, Chile | Operational | — | 2016 | Operator / official |
| Gtd MonedaColocation | Santiago, Chile | Operational | — | — | Operator / official |
| Gtd PanamericanaColocation | Conchalí, Chile | Operational | — | 2016 | Operator / official |
| Gtd Puerto MonttColocation | Puerto Montt, Chile | Operational | — | 2018 | Operator / official |
| Lurín Phase 1Colocation | Lurín, Peru | Operational | — | 2024 | Operator / official |
| Lurín Phase 2Colocation | Lurín, Peru | Planned | — | — | Trade press |
| SurcoColocation | Santiago de Surco, Peru | Operational | — | 2018 | Operator / official |
Market position
How Gtd compares
Computed from our tracker, Deal Tracker and Power & Policy Tracker. Capacity counts only facilities whose source states MW.
- In Chile, Gtd is one of 19 operators we track.
- Chile has 50 tracked data centers from 19 operators: 115 MW operational and 1,029 MW under construction or planned.
- In Peru, Gtd is one of 11 operators we track.
- In Colombia, Gtd is one of 18 operators we track.
- Santiago also hosts 6 other tracked data center(s), run by Ascenty, Huawei Cloud, Ufinet and Microsoft.
Data center operators in Chile
| Operator | Facilities | Operational MW | Pipeline MW |
|---|---|---|---|
| Grenergy | 3 | — | 400 MW |
| Ascenty | 5 | 42 MW | 225 MW |
| Scala Data Centers | 6 | 5 MW | 103 MW |
| TECfusions | 1 | — | 100 MW |
| DC Terranova | 1 | — | 92.7 MW |
| ODATA | 3 | 40.6 MW | 48 MW |
| EdgeConneX | 4 | 21 MW | 40 MW |
| Cirion Technologies | 2 | 4 MW | 20 MW |
All data centers in Chile Power and policy in Chile
Data center operators in Peru
| Operator | Facilities | Operational MW | Pipeline MW |
|---|---|---|---|
| Cirion Technologies | 2 | 24 MW | — |
| Equinix | 1 | 0.7 MW | — |
| ON Empresas | 4 | — | — |
| Banco de Crédito del Perú | 2 | — | — |
| Telefónica del Perú | 2 | — | — |
| Banco Central de Reserva del Perú | 2 | — | — |
| BBVA | 1 | — | — |
| Claro | 1 | — | — |
All data centers in Peru Power and policy in Peru
Data center operators in Colombia
| Operator | Facilities | Operational MW | Pipeline MW |
|---|---|---|---|
| ODATA | 3 | 7.8 MW | 144 MW |
| Ascenty | 2 | — | 20 MW |
| EdgeConneX | 3 | — | 19.2 MW |
| Cirion Technologies | 1 | 7 MW | — |
| Scala Data Centers | 3 | — | — |
| Equinix | 2 | — | — |
| Claro | 2 | — | — |
| Ufinet | 2 | — | — |
All data centers in Colombia Power and policy in Colombia
Other data centers in Santiago
How we build the tracker
- Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
- A second analyst re-opens each source before a facility is published.
- Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
- Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
- Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
- Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
- Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.
Questions
How many data centers does Gtd operate?
DC Market Insights tracks 12 Gtd data center(s) in 3 countries as of October 2026: 10 operational, 0 under construction and 2 planned.
Where is Gtd headquartered?
Gtd is headquartered in Santiago, Chile. Ownership: Private; Inmobiliaria e Inversiones El Coigue Limitada holds 99.39% (Casanueva family).
Which other companies operate data centers in Chile?
Besides Gtd, the largest operators we track in Chile by capacity are Grenergy, Ascenty, Scala Data Centers, TECfusions and DC Terranova. The Chile page lists all 19 operators.
What rules apply to data centers in Chile?
Our Power & Policy Tracker lists 7 government actions on data centers and power in Chile, including 0 restriction(s) and 0 incentive scheme(s) in force.
Which other data centers are in Santiago?
Other tracked data centers in Santiago include Santiago 5 (Ascenty), Huawei Cloud LA-Santiago region (Huawei Cloud), Magnus II (Ufinet) and Microsoft Chile Central cloud region (Santiago) (Microsoft).
Where does this data come from?
Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.
What does the MW figure mean?
We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.
How exact are the map locations?
When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.
How often is it updated?
The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.
Can I get the data in Excel?
Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.
Global capacity
How much data center capacity is installed worldwide?
Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.
Need the full list, or a capacity view of one market?
Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.