How much data center capacity Indonesia has installed, how it compares with the rest of Asia Pacific, and what our trackers show about its sites, operators, deals and rules.
Indonesia data center capacity at a glance
Indonesia had about 0.5 GW of installed data center capacity (IT load) at the end of 2025, by our estimate. That is about 1% of the capacity in Asia Pacific and puts Indonesia at number 22 of the 33 countries in our global model. Our Data Center Tracker holds 76 sites in Indonesia run by 33 operators: 61 operational, 8 under construction and 7 planned. Our trackers also hold 11 verified deals and 6 government measures in force for the country.
Installed capacity is IT load, the power available to servers, storage and network. The country figure comes from the same model as the global and regional totals and is benchmarked against dated public figures. Site figures below are what each source states, often a campus’s full build-out, so they are not the same measure.
What our tracker holds for Indonesia
Largest tracked sites
| Site | Operator | City | Status | MW |
|---|---|---|---|---|
| DCI H5 Data Center Park | DCI Indonesia | Bintan | Planned | 1,000 IT |
| CGK Campus | Digital Edge | Bekasi | Under construction | 500 IT |
| Kabil Industrial Tech Park (KITP) | DayOne | Batam | Planned | 360 IT |
| CGK5 Suryacipta AI Campus 3 | BDx | Karawang | Planned | 290 IT |
| JC4 | Princeton Digital Group | Bekasi | Under construction | 240 |
| AI Campus 2 (CGK4) | BDx | Purwakarta | Under construction | 120 IT |
| JC3 | Princeton Digital Group | Bekasi | Under construction | 120 |
| STTGDC JKT7 | ST Telemedia Global Data Centres | Cikarang | Planned | 60 IT |
| STTGDC JKT8 | ST Telemedia Global Data Centres | Cikarang | Planned | 60 IT |
| STTGDC JKT9 | ST Telemedia Global Data Centres | Cikarang | Planned | 60 IT |
Where the sites are
| City | Sites | Operators | MW stated, live |
|---|---|---|---|
| Jakarta | 23 | 19 | 105 |
| Cikarang | 11 | 3 | 64 |
| Bekasi | 7 | 5 | 71 |
| Cibitung | 5 | 1 | 73 |
| Surabaya | 5 | 5 | 12 |
| Karawang | 4 | 3 | n/a |
| South Tangerang | 3 | 3 | 17 |
| Batam | 3 | 2 | n/a |
Cities with the most tracked sites. MW only where a source states it.
Who runs them
| Operator | Sites | MW live | MW pipeline |
|---|---|---|---|
| DCI Indonesia | 10 | 101 | 1,000 |
| Digital Edge | 3 | 29 | 500 |
| BDx | 5 | 37 | 410 |
| Princeton Digital Group | 7 | 26 | 360 |
| ST Telemedia Global Data Centres | 9 | 42 | 332 |
| DayOne | 2 | n/a | 360 |
| NTT DATA | 3 | 66 | n/a |
| NeutraDC | 4 | 44 | n/a |
Operators ranked by MW stated at their tracked sites in Indonesia.
Rules in force
- PlanPusat Data Nasional (PDN) 1 limited operation
- PlanPeraturan Menteri Komunikasi dan Digital Nomor 18 Tahun 2025 tentang Organisasi dan Tata Kerja Balai Layanan Pusat Data Nasional
- RenewablePLN REC service for the data centre industry
- IncentivePeraturan Pemerintah Nomor 68 Tahun 2021 tentang Kawasan Ekonomi Khusus Nongsa
- RegulationPeraturan Pemerintah Nomor 71 Tahun 2019 tentang Penyelenggaraan Sistem dan Transaksi Elektronik
From government sources. Power and policy in Indonesia
Recent deals
- Oct 2026 · Land / campus16.6 ha land, Cluster 2B, D-Hub Special Economic Zone, BSD City, Tangerang, Banten, USD 186 m
- Oct 2026 · M&APDG Indonesia enterprise data center business (5 operational data centers: Greater Jakarta, Bandung, Surabaya, Pekanbaru)
- Sep 2026 · JV / partnershipPlanned ~500MW wholesale AI and cloud data centre campus, KEK Galang Batang, Bintan (phase 1 ~50MW), 500 MW
- Aug 2026 · Land / campusSMX01 data center, Jakarta (27MW facility)
- Aug 2026 · JV / partnershipZankore by Indosat AI factory platform (200MW by 1H 2027, up to 1GW), 1,000 MW, USD 800 m
- Aug 2026 · Land / campusThree data centers in Indonesia (360MW contracted IT power), 360 MW
Other countries in Asia Pacific
- China20.7 GW
- Japan2.6 GW
- South Korea1.5 GW
- Australia1.5 GW
- India1.5 GW
- Singapore1.5 GW
- Malaysia1.0 GW
- Hong Kong0.8 GW
- Taiwan0.6 GW
- Thailand0.4 GW
- Vietnam0.2 GW
- Pakistan0.1 GW
- Bangladesh0.1 GW
- Cambodia0.0 GW
Installed capacity, end 2025, DC Market Insights estimate. All countries and regions
Indonesia in the full data pack
By year to 2035
Installed MW for Indonesia from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases.
Leading hubs
Live and pipeline MW for the main metro markets, with the basis of each figure.
Every tracked site
The full site list with operator, location, status, MW and source, refreshed from our tracker.
Related research on Indonesia
Frequently asked questions
How much data center capacity does Indonesia have?
We estimate about 0.5 GW of installed data center capacity (IT load) in Indonesia at the end of 2025, about 1% of Asia Pacific and number 22 of the 33 countries in our model. This is a DC Market Insights estimate, benchmarked against dated public figures.
How many data centers are there in Indonesia?
Our Data Center Tracker lists 76 sites in Indonesia (61 operational, 8 under construction, 7 planned), run by 33 operators. Each site is verified from operator, planning or utility sources; the list grows as new sites are confirmed.
Which companies have the most tracked data center capacity in Indonesia?
By capacity stated at their sites (operational plus pipeline), the largest in our tracker are DCI Indonesia, Digital Edge, BDx. Site capacity is counted only where a source states it.
What rules apply to data centers in Indonesia?
Our Power and Policy Tracker lists 6 government measures in force for Indonesia, such as incentives, tariffs, grid rules and national plans, each linked to the official source.
How will Indonesia data center capacity grow to 2035?
The full data pack gives installed capacity for Indonesia by year from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases and the main metro hubs.