Austria's power system is hydro-led: renewables covered 78% of gross electricity consumption in 2025, against a legal target of 100% net renewable electricity by 2030 (EAG). The new Electricity Act (ElWG, in force 24 Dec 2025) adds published grid capacity, paid reservations, permit-based queuing and flexible access. Transmission operator APG reports about 2,500 MW of data center demand registered. A draft EIA amendment would for the first time require an environmental impact assessment for new data centers of 100 MW or more.
Power and grid
APG's grid development plan to 2035 (7 Apr 2026) foresees about EUR 9bn of transmission investment; data centers have registered about 2,500 MW of demand, alongside more than 10,000 MW of wind and solar access requests.
Under the ElWG, loads of more than 5 MW up to 200 MW connect at Netzebene 4 or 3; grid operators publish available capacity per substation each quarter, reservations carry a deposit forfeited after 12 months, and requests are queued by the date all permits are in hand.
2026 grid tariffs at Netzebene 3 range from 2,412 c/kW plus 0.46 c/kWh in Upper Austria to 4,848 c/kW plus 0.76 c/kWh in Lower Austria (SNE-V 2018 Novelle 2026).
From 1 Jan 2027 the new SNE-G-V moves grid tariffs towards a 50:50 energy/capacity split; flexible capacity is expected to pay 25% of the regular capacity price. E-Control
Policy and incentives
The federal electricity levy is cut from 1.5 c/kWh to 0.82 c/kWh for calendar year 2026 only. Bundesministerium für Finanzen
Data centers with 500 kW or more of installed IT power must report energy, water, waste heat and renewable use every year from 15 May 2024 (Energy Efficiency Act amendment, BGBl. I Nr. 29/2024). Unternehmensserviceportal
Vienna, backed by the Federal Chancellor, bid on 18 Jun 2025 to host an EU AI Gigafactory. Bundeskanzleramt
Land, zoning and permits
A ministry draft of the EIA Act (138/ME, consultation until 1 Nov 2026) would require a full EIA for new data centers of 100 MW or more, and screening for 50 MW or more in protected category D areas. Parlament Österreich, 138/ME
A Green opposition motion (1004/A(E), 14 Sep 2026) notes that the Kronstorf project (150 MW first phase, up to 500 MW) needed no EIA and calls for a national data center master plan. Parlament Österreich, 1004/A(E)
The Renewables Acceleration Act (EABG, BGBl. I Nr. 47/2026) gives renewable plants and the related grid and storage an overriding public interest in permitting. Parlament Österreich, 11830 d.B.
Sustainability, water and climate
Renewables covered 78% of gross electricity consumption in 2025; the EAG targets 100% on a net basis and 27 TWh of additional renewable generation by 2030. E-Control EAG-Monitoringbericht 2026
The Austrian electricity supply mix (generation plus imports, 2023 data) emits 152 g CO2-eq/kWh including upstream emissions, 123 g direct. Umweltbundesamt REP-0989
Demand and connectivity
The Vienna Internet eXchange (VIX) has been run by the University of Vienna since 1996 and operates at three sites in Vienna.