Every data center in Sweden that we have verified: operator, location, status and capacity, each checked against its source.
By Amit JainReviewed by Deepti AgrawalUpdated 9 Nov 2026
In short
As of 9 November 2026, DC Market Insights tracks 39 data centers in Sweden run by 16 operators: 30 operational, 2 under construction and 7 planned. Stated operational capacity is 171 MW, with a further 250 MW under construction and 1,248 MW planned. EcoDataCenter holds the largest share of tracked operational capacity (47%).
39Facilities tracked
16Operators
171 MWOperational (30 sites)
250 MWUnder construction (2 sites)
1,248 MWPlanned (7 sites)
MW = IT capacity where the source states it, otherwise total capacity. 15 of 39 facilities have a stated capacity; the others are counted as sites only.
OperationalUnder constructionPlannedPin = exact site location; dot = city (approximate)
Market snapshot
Sweden data center market: key facts
Capacity under construction or planned (1,498 MW) is 8.7 times the operational base of 171 MW.
The three largest operators by operational capacity, EcoDataCenter, Conapto and Hydro66, hold 81% of tracked operational MW.
Brookfield has the largest development pipeline in Sweden: 750 MW under construction or planned.
The largest operational facility we track is EcoDataCenter 1 Falun (EcoDataCenter, Falun) at 80 MW.
The largest project in the pipeline is Brookfield Strängnäs AI campus (750 MW, planned).
Strängnäs is the largest cluster: 1 of 39 facilities and 45% of tracked capacity.
By type, the tracker lists 28 colocation and 11 hyperscale facilities.
15 of 39 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational171 MW
Under construction250 MW
Planned1,248 MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Largest operators in Sweden by tracked capacity, MW
Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.
Market context
What shapes the Sweden data center market
Policy, power, land and demand, each statement checked against its source. Reviewed 16 October 2026. Government sources are linked; the full source list comes with the Excel data.
Sweden pays the full energy tax on data-centre electricity since the reduction ended on 1 July 2023 (36.0 öre/kWh in 2026). Data centres of 500 kW IT or more must publish energy performance under Act 2025:570. Grid access is the main constraint: on 1 October 2026 Svenska kraftnät's queue held 7,326 MW of data-centre applications, and its April 2026 connection review proposes zones, a ready-first track and lowest-voltage connection. Svenska kraftnät: Information om pågående anslutningsärenden
Policy and incentives
Energy-tax reduction for electricity used in data centres abolished from 1 July 2023. Skatteverket
General energy tax on electricity 2026: 36.0 öre/kWh; the northern-Sweden 9.6 öre/kWh reduction excludes industrial use. Skatteverket
Energy minister answered interpellation 2025/26:414 on a national data-centre plan (13 Apr 2026): no plan committed; points to the AI strategy (20 Feb 2026), Svenska kraftnät connection review and waste-heat requirements. Riksdagen
Government confirmed work on a national data-centre strategy (Aug 2026); no details or date yet.
Power and grid
Svenska kraftnät queue on 1 Oct 2026: 7,326 MW data-centre applications out of 25,801 MW consumption applications. Svenska kraftnät
New transmission station considered only for at least 100 MW (220 kV) or 300 MW (400 kV); applications go via the distribution grid first. Svenska kraftnät
Connection review report (29 Apr 2026): lowest suitable voltage as main rule, capacity zones, ready-first track, possible fossil-free new-generation requirement for large loads, geographic fixed tariff fee from 2027. Svenska kraftnät
Proposed capacity reservation for general societal growth at congested stations; connections above 0.5 MW excluded (consultation 5 Feb 2026). Svenska kraftnät
2025 large industrial price (Eurostat band IE, excl. VAT): about 0.069 EUR/kWh (78.5 USD/MWh). Eurostat
Sustainability, water and climate
Electricity production 2024: 169.3 TWh, of which hydro 64.2, nuclear 48.7, wind 40.4, solar 4.1 and conventional thermal 11.8 TWh. Energimyndigheten
Naturvårdsverket electricity emission factor 59 g CO2e/kWh (Nordic mix average 2021-2023). Naturvårdsverket
Data centres of at least 500 kW IT report energy performance yearly to the EU database via the Swedish Energy Agency (2025 data due 15 May 2026). Energimyndigheten
Data rules
Act 2025:570 exempts confidential information from publication; data centres covered by the Protective Security Act (2018:585) are exempt per the Swedish Energy Agency. Energimyndigheten
Our Deal Tracker lists 7 deals in Sweden since January 2026, with $1.43B in disclosed value.
Vertical Data Inc. (Vertical Data Nordic AB) → Existing 4.5 MW industrial data center site, Hamre Industrial Park, Sollefteå Municipality (application for up to 100 MW) M&A · 4.5 MW
Amazon → Fageråsen, Boarp, Dållebo and Fågelås wind farms Power deal
EcoDataCenter → 52-hectare site for third Dalarna campus, Smedjebacken Land / campus · 150 MW
Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
A second analyst re-opens each source before a facility is published.
Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.
Questions
How many data centers are there in Sweden?
DC Market Insights tracks 39 data centers in Sweden as of November 2026: 30 operational, 2 under construction and 7 planned, run by 16 operators. The count grows as we verify more sites.
What is the data center capacity of Sweden?
Tracked operational capacity in Sweden is 171 MW, with 250 MW under construction and 1,248 MW planned. These totals use the capacity each source states (IT load where given) and cover 15 of 39 tracked facilities.
Which companies operate the most data center capacity in Sweden?
By tracked operational capacity, the largest operators in Sweden are EcoDataCenter (80 MW), Conapto (39 MW) and Hydro66 (19.2 MW).
Where are the data centers in Sweden located?
The largest clusters by tracked capacity are Strängnäs (1 facilities), Långsele (1 facilities) and Borlänge (1 facilities). The map above shows every site.
Which new data centers are being built in Sweden?
We track 250 MW under construction and 1,248 MW planned. The largest projects are Brookfield Strängnäs AI campus (750 MW), atNorth SWE04 Sollefteå (Hamre Industrial Park) (300 MW) and EcoDataCenter 2 Borlänge (250 MW).
Where does this data come from?
Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.
What does the MW figure mean?
We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.
How exact are the map locations?
When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.
How often is it updated?
The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.
Can I get the data in Excel?
Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.
Global capacity
How much data center capacity does Sweden have?
Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.