Data Centers in Italy

Every data center in Italy that we have verified: operator, location, status and capacity, each checked against its source.

In short

As of 26 November 2026, DC Market Insights tracks 22 data centers in Italy run by 11 operators: 12 operational, 2 under construction and 8 planned. Stated operational capacity is 245 MW, with a further 59 MW under construction and 1,134 MW planned. Data4 holds the largest share of tracked operational capacity (69%).

22Facilities tracked
11Operators
245 MWOperational (12 sites)
59 MWUnder construction (2 sites)
1,134 MWPlanned (8 sites)

MW = IT capacity where the source states it, otherwise total capacity. 12 of 22 facilities have a stated capacity; the others are counted as sites only.

Milan campus · NTT DATA · Milan (approximate location)QTS Vimercate · QTS · Vimercate (approximate location)CyrusOne MIL1 Milan · CyrusOne · Segrate (approximate location)CyrusOne MIL2 Milan · CyrusOne · Milan (approximate location)Compass Milan campus (Noviglio) · Compass Datacenters · Noviglio (approximate location)Data4 MIL02 Vittuone · Data4 · Vittuone (approximate location)Milan AI Data Center Campus (Ferrera Erbognone) · Khazna Data Centers · Ferrera Erbognone (approximate location)Equinix ML3 · Equinix · Basiglio (approximate location)Aruba IT1 Arezzo · Aruba · Arezzo (approximate location)Aruba IT2 Arezzo · Aruba · Arezzo (approximate location)Aruba IT3 Global Cloud Data Center · Aruba · Ponte San Pietro (approximate location)Aruba IT4 Hyper Cloud Data Center · Aruba · Rome (approximate location) · Owned: part of the Aruba Group's own data center networkOVHcloud ITMIL01 · OVHcloud · Milan (approximate location)OVHcloud ITBSI01 · OVHcloud · Milan (approximate location)OVHcloud ITZVF01 · OVHcloud · Milan (approximate location)MXP Campus · CloudHQ · Milan (exact location)Data4 MIL01 Cornaredo · Data4 · Cornaredo (exact location)Equinix ML2 · Equinix · Milan (exact location)Equinix ML5 · Equinix · Settimo Milanese (exact location)Equinix GN1 · Equinix · Genoa (exact location)
Operational Under construction Planned Pin = exact site location; dot = city (approximate)

Market snapshot

Italy data center market: key facts

  • Capacity under construction or planned (1,193 MW) is 4.9 times the operational base of 245 MW.
  • The three largest operators by operational capacity, Data4, Aruba and Equinix, hold 100% of tracked operational MW.
  • Khazna Data Centers has the largest development pipeline in Italy: 500 MW under construction or planned.
  • The largest operational facility we track is Data4 MIL01 Cornaredo (Data4, Cornaredo) at 170 MW.
  • The largest project in the pipeline is Milan AI Data Center Campus (Ferrera Erbognone) by Khazna Data Centers (500 MW, planned).
  • Milan is the largest cluster: 18 of 22 facilities and 98% of tracked capacity.
  • By type, the tracker lists 13 colocation and 9 hyperscale facilities.
  • 12 of 22 facilities have a capacity stated by their source; the totals above count only those.
Capacity by status, MW
Operational245 MW
Under construction59 MW
Planned1,134 MW

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Largest operators in Italy by tracked capacity, MW
Data4270 MW
CloudHQ240 MW
NTT DATA128 MW
Aruba75 MW

OperationalUnder construction or planned

Capacity by market in Italy, MW
Milan1,408 MW
Rome30 MW

OperationalUnder construction or planned

Facilities by type
Colocation13
Hyperscale9

Source: DC Market Insights Data Center Tracker. MW as stated by each facility source.

Market context

What shapes the Italy data center market

Policy, power, land and demand, each statement checked against its source. Reviewed 18 October 2026. Government sources are linked; the full source list comes with the Excel data.

Italy is building a national rulebook for data centers. Since 21 Feb 2026 Decree-Law 21/2026 (Art. 8) gives data centers a single authorization procedure capped at 10 months, run by the Regions or by MASE depending on backup-plant size; a broader delegation law passed the Chamber in Feb 2026 and sits in the Senate. Lombardy, the main market around Milan, adopted the first regional data center law in June 2026. Industrial power is expensive (about 162 EUR/MWh for band ID in 2025) and 48% of power came from renewables in 2025. Regione Lombardia, Procedimento unico centri dati

Policy and incentives

Decree-Law 20 Feb 2026 n. 21, Art. 8 (converted by Law 10 Apr 2026 n. 49) created a single procedure for authorizing new and expanded data centers and their grid connections, concluded within 10 months of the completeness check, with halved EIA deadlines. Regione Lombardia, Procedimento unico centri dati

A bill delegating the Government to adopt data center decrees within six months (definition, single fast-track procedures, brownfield priority, public-utility status, priority grid access, self-generation) passed the Chamber of Deputies on 24 Feb 2026 and was sent to the Senate on 26 Feb 2026. Senato della Repubblica, DDL centri di elaborazione dati

MASE published first operational guidance on the data center single procedure (PUCD) on 25 Jul 2026, covering timelines, fees and filing with the Directorate-General for Environmental Assessments.

Power and grid

Eurostat puts the 2025 price for non-household band ID (2,000-19,999 MWh a year) at 0.1661 EUR/kWh in H1 and 0.1587 EUR/kWh in H2, excluding taxes and levies; H1 2026 was 0.1659 EUR/kWh. Eurostat nrg_pc_205

Decree-Law 21/2026 funds a cut of EUR 431.5 million in 2026 in the ASOS renewable-support charge for non-domestic users, excluding energy-intensive firms registered with CSEA; ARERA applies it from 1 Apr 2026. ARERA deliberation 91/2026/R/eel

Terna's CEO said on 14 Oct 2026 that the grid operator has received over 100 GW of connection requests for data centers from almost 600 initiatives, and that not all will be built.

Land, zoning and sites

Lombardy Regional Law 3 Jun 2026 n. 11 on the siting of data centers steers projects to disused industrial land, limits soil consumption, protects water, promotes waste-heat reuse and requires siting in line with network capacity; implementing resolutions DGR 6645 and 6646 were published on 28 Aug 2026. Regione Lombardia, Procedimento unico centri dati

Under the single procedure, Regions grant the AIA for data centers whose combustion plants total 50 MWt up to 300 MWt; the State handles 300 MWt and above and sites of national strategic interest. Regione Lombardia, Procedimento unico centri dati

Sustainability, water and climate

ISPRA reports that renewables supplied 48% of national electricity production in 2025. ISPRA Rapporto 430/2026

ISPRA's emission factor for electricity consumption was 192.6 gCO2/kWh in 2024 and 199.6 gCO2/kWh in 2025 (preliminary), up as lower hydro output was not offset by solar. ISPRA Rapporto 430/2026, Tabella 1.7

Operators in Italy

All operators
OperatorFacilitiesOperational MWPipeline MWShare of operational MW
Aruba475 MW—31%
Equinix4———
OVHcloud3———
Data42170 MW100 MW69%
CyrusOne2—81 MW—
Vantage Data Centers2—96 MW—
QTS1———
NTT DATA1—128 MW—
CloudHQ1—240 MW—
Khazna Data Centers1—500 MW—
Compass Datacenters1—48 MW—

Largest data center projects in Italy

Under construction and planned facilities with a stated capacity, largest first. 59 MW under construction and 1,134 MW planned in total.

ProjectLocationStatusTypeCapacity
Milan AI Data Center Campus (Ferrera Erbognone)Khazna Data Centers Ferrera Erbognone Planned Hyperscale 500 MW
MXP CampusCloudHQ Milan Planned Hyperscale 240 MW
Milan campusNTT DATA Milan Planned Colocation 128 MW
Data4 MIL02 VittuoneData4 Vittuone Planned Colocation 100 MW
Vantage Milan I (MXP1) campusVantage Data Centers Melegnano Planned Hyperscale 64 MW
CyrusOne MIL2 MilanCyrusOne Milan Planned Colocation 54 MW
Compass Milan campus (Noviglio)Compass Datacenters Noviglio Planned Hyperscale 48 MW
Vantage Milan II campusVantage Data Centers Settimo Milanese Under construction Hyperscale 32 MW
CyrusOne MIL1 MilanCyrusOne Segrate Under construction Colocation 27 MW

How Italy compares in Europe

Countries in the same region, by tracked capacity. Coverage grows as each country is researched.

CountryFacilitiesOperatorsOperational MWPipeline MW
United Kingdom207551,064 MW7,741 MW
Germany20364933 MW4,386 MW
Finland4824230 MW2,661 MW
France10920338 MW2,422 MW
Sweden4518172 MW2,510 MW
Ireland461953 MW1,458 MW
Italy2211245 MW1,193 MW
Norway228446 MW820 MW
Denmark361654.6 MW1,004 MW
Russia11121516 MW425 MW
Spain411979.4 MW815 MW
Netherlands11034217 MW449 MW

Data center deals in Italy

Our Deal Tracker lists 6 deals in Italy since April 2026, with $6.53B in disclosed value.

  • Greenfield Group and Finsbury Infrastructure → 36MW IT data center east of Milan (80MW power secured) JV / partnership $418.1M · 36 MW

All Italy deals in the Deal Tracker

Facilities

22 facilities match. Each is checked against its source; source links come with the Excel data.

Facility Location Status Capacity Year Source
Milan AI Data Center Campus (Ferrera Erbognone)Khazna Data Centers
History
  1. Announced
  2. Planned
Ferrera Erbognone Planned 500 MW IT — Operator / official
MXP CampusCloudHQ Milan Planned 240 MW IT — Operator / official
Data4 MIL01 CornaredoData4 Cornaredo Operational 170 MW — Operator / official
Milan campusNTT DATA Milan Planned 128 MW total — Operator / official
Data4 MIL02 VittuoneData4 Vittuone Planned 100 MW — Operator / official
Vantage Milan I (MXP1) campusVantage Data Centers Cooling: Hybrid Melegnano Planned 64 MW IT — Operator / official
CyrusOne MIL2 MilanCyrusOne Milan Planned 54 MW IT — Operator / official
Compass Milan campus (Noviglio)Compass Datacenters
History
  1. Announced
  2. Planned
Noviglio Planned 48 MW IT — Operator / official
Aruba IT3 Global Cloud Data CenterAruba Ponte San Pietro Operational 45 MW IT — Operator / official
Vantage Milan II campusVantage Data Centers
History
  1. Under construction
  2. Under construction
Settimo Milanese Under construction 32 MW IT — Operator / official
Aruba IT4 Hyper Cloud Data CenterAruba Owned: part of the Aruba Group's own data center network Rome Operational 30 MW IT — Operator / official
CyrusOne MIL1 MilanCyrusOne Segrate Under construction 27 MW IT — Operator / official
Aruba IT1 ArezzoAruba Arezzo Operational — — Operator / official
Aruba IT2 ArezzoAruba Arezzo Operational — — Operator / official
Equinix GN1Equinix Genoa Operational — — Operator / official
Equinix ML2Equinix Milan Operational — — Operator / official
Equinix ML3Equinix Basiglio Operational — — Operator / official
Equinix ML5Equinix Settimo Milanese Operational — — Operator / official
OVHcloud ITBSI01OVHcloud Milan Operational — — Operator / official
OVHcloud ITMIL01OVHcloud Milan Operational — — Operator / official
OVHcloud ITZVF01OVHcloud Milan Operational — — Operator / official
QTS VimercateQTS Vimercate Planned — — Operator / official

Get the data

Every data center in Italy, in Excel

Every facility with operator, city, status, capacity, year and source, plus summaries and the status history. Built from the live tracker.

All countries

Global Data Center Database: annual licence

4,451 facilities

Every facility in the tracker worldwide, in Excel, with sources and status history. A fresh file every month for a year.

Request a quote

Scoped to the markets and fields you need. Quote within one business day.

Custom cut

One operator, one city, a capacity pipeline or a site-selection shortlist, prepared by our analysts.

Talk to an analyst

Free updates: data centers in Italy

Leave your work email and our team will send you new facilities, status changes and deals for this market, each checked against its source.

Request a quote

Italy

Tell us what you need. We reply by email with scope, delivery date and a quote, usually within one business day.

Contact Form

Your data is safe with us

  • Your details stay private. We never sell or share them.
  • Used only to reply to your message
  • No spam: we only send what you asked for
  • Encrypted (SSL) form, handled by our own team

Privacy Policy

How we build the tracker

  • Sources: operator websites and announcements, stock-exchange filings, planning and government records, and named trade publications. Never another directory.
  • A second analyst re-opens each source before a facility is published.
  • Capacity, size, year, tier and PUE appear only when the source states them. Nothing is estimated.
  • Status: operational, under construction (building work started) or planned (announced or permitted, not yet under construction).
  • Map locations: a pin where the source gives the address, parcel or coordinates; otherwise a dot at the city centre (approximate).
  • Cooling type and tenancy (owned or leased in colocation) come from our site footprint research in planning, permit and operator records, shown where found.
  • Maps: Natural Earth (public domain). City locations: GeoNames, licensed under CC BY 4.0.

Questions

How many data centers are there in Italy?

DC Market Insights tracks 22 data centers in Italy as of November 2026: 12 operational, 2 under construction and 8 planned, run by 11 operators. The count grows as we verify more sites.

What is the data center capacity of Italy?

Tracked operational capacity in Italy is 245 MW, with 59 MW under construction and 1,134 MW planned. These totals use the capacity each source states (IT load where given) and cover 12 of 22 tracked facilities.

Which companies operate the most data center capacity in Italy?

By tracked operational capacity, the largest operators in Italy are Data4 (170 MW) and Aruba (75 MW).

Where are the data centers in Italy located?

The largest clusters by tracked capacity are Milan (18 facilities), Rome (1 facilities) and Arezzo (2 facilities). The map above shows every site.

Which new data centers are being built in Italy?

We track 59 MW under construction and 1,134 MW planned. The largest projects are Milan AI Data Center Campus (Ferrera Erbognone) by Khazna Data Centers (500 MW), MXP Campus by CloudHQ (240 MW) and Milan campus by NTT DATA (128 MW).

Where does this data come from?

Every facility comes from a page we opened: the operator’s own website or announcement, a stock-exchange filing, a planning or government record, or a named trade publication. A second analyst re-opens the source and checks the name, location, status and capacity before the row is published. We do not copy other data center directories.

What does the MW figure mean?

We show IT (critical) capacity when the source states it, otherwise the total or utility capacity the source gives, and say which in the facility’s note. When a source gives no capacity, the field stays empty. We never estimate it.

How exact are the map locations?

When the source gives an address or coordinates we use them. Otherwise the dot sits at the centre of the facility’s city (marked as approximate), using the GeoNames gazetteer.

How often is it updated?

The tracker is updated every week as new facilities are announced and existing ones change status. Each row shows the date it was last checked.

Can I get the data in Excel?

Yes. Each country with 50 or more facilities has a Capacity Sheet in Excel with every facility, its source link, the status history and summaries. Our analysts can also prepare an operator extract or a custom cut.

Global capacity

How much data center capacity does Italy have?

Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.

See Italy capacity

Need the full list, or a capacity view of one market?

Our analysts prepare country and operator extracts in Excel, capacity pipelines and site-selection briefings.

Talk to an analyst

Request a quote

Data Center Map data

Tell us the markets, companies or sites and the fields you need. A senior analyst replies with scope, delivery date and a quote, usually within one business day.

Contact Form

Your data is safe with us

  • Your message goes straight to our research team
  • Your details stay private. We never sell or share them.

Privacy Policy