Norway Data Center Capacity

Installed data center capacity in Norway (MW, IT load), its share of the region, tracked sites, recent deals and the rules in force. Forecast to 2035 in the data pack.

Data pack · Updated 12 November 2026

How much data center capacity Norway has installed, how it compares with the rest of Europe, and what our trackers show about its sites, operators, deals and rules.

0.5 GWInstalled, end 2025IT load, DC Market Insights estimate
3%Share of Europe2025
#23Rank among 33 countriesInstalled capacity, 2025
22Sites in our tracker20 with a stated MW

Norway data center capacity at a glance

Norway had about 0.5 GW of installed data center capacity (IT load) at the end of 2025, by our estimate. That is about 3% of the capacity in Europe and puts Norway at number 23 of the 33 countries in our global model. Our Data Center Tracker holds 22 sites in Norway run by 8 operators: 15 operational, 2 under construction and 5 planned. Our trackers also hold 15 verified deals and 6 government measures in force for the country.

Installed capacity is IT load, the power available to servers, storage and network. The country figure comes from the same model as the global and regional totals and is benchmarked against dated public figures. Site figures below are what each source states, often a campus’s full build-out, so they are not the same measure.

What our tracker holds for Norway

446 MWStated at operational sites (15)
310 MWUnder construction (2 sites)
510 MWPlanned (5 sites)
8Operators

Largest tracked sites

SiteOperatorCityStatusMW
atNorth NOR01 HaugalandatNorthTysværPlanned350
Nscale Narvik campus (Kvandal)NscaleNarvikUnder construction230
Green Mountain OSL-HamarGreen MountainHamarOperational150 IT
Green Mountain SVG-UndheimGreen MountainTimeUnder construction80 IT
Lefdal Mine Datacenter (Nordfjord)Lefdal Mine DatacenterMåløyOperational80
Lefdal Mine Datacenter Sunnfjord (LMD2)Lefdal Mine DatacenterFørdePlanned80
Green Mountain OSL-EnebakkGreen MountainEnebakkOperational75 IT
Green Mountain TEL-RjukanGreen MountainRjukanOperational50 IT
Polar DRA02 TørdalPolar Data CentersTørdalPlanned40 IT
Polar HER01 HerøyaPolar Data CentersPorsgrunnPlanned40

Every Norway site on the Data Center Map

Where the sites are

CitySitesOperatorsMW stated, live
Fetsund4122
Holtskogen3118
Tørdal2112
Hamar11150
Måløy1180
Enebakk1175
Rjukan1150
Stavanger1125

Cities with the most tracked sites. MW only where a source states it.

Who runs them

OperatorSitesMW liveMW pipeline
Green Mountain530080
atNorth1n/a350
Nscale1n/a230
Lefdal Mine Datacenter28080
Polar Data Centers31280
STACK Infrastructure740n/a
Bulk Infrastructure214n/a
Google1n/an/a

Operators ranked by MW stated at their tracked sites in Norway.

Power context

Rules in force

  • MoratoriumStatnett temporary halt on new grid-connection reservations for data centres
  • GridGrid connection rules: first-in-time allocation, maturity assessment and capacity hold-back (NEM §§ 3-2a, 3-4)
  • TariffData centres pay the ordinary electricity tax; reduced rate for data centres repealed in 2023
  • PlanNational data centre strategy 2025: a sustainable industry of the future for digital Norway
  • RegulationData centre regulation: mandatory registration with Nkom

From government sources. Power and policy in Norway

Recent deals

  • Oct 2026 · JV / partnershipDRA02, 40 MW critical liquid-cooled IT capacity, Polar Tørdal campus, Drangedal (go-live late 2027), 40 MW
  • Oct 2026 · M&AOperating data center in Oslo, ~1,400 sqm, up to 2 MW IT load, 2 MW
  • Sep 2026 · Land / campusTitan Group AS and its data center site in Moskog, Sunnfjord
  • Sep 2026 · FinancingAsp Data Center K11 data center, Stavanger (incl. refinancing of NOK 685m bond), USD 170 m
  • Aug 2026 · JV / partnershipPilot AI data center powered by Zephyros-One floating wind turbine off Norway, 1 MW
  • Aug 2026 · Land / campusGiga Arctic site conversion to 50MW data center, Mo i Rana, 50 MW

Deal Tracker

Other countries in Europe

Installed capacity, end 2025, DC Market Insights estimate. All countries and regions

Norway in the full data pack

By year to 2035

Installed MW for Norway from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases.

Leading hubs

Live and pipeline MW for the main metro markets, with the basis of each figure.

Every tracked site

The full site list with operator, location, status, MW and source, refreshed from our tracker.

Frequently asked questions

How much data center capacity does Norway have?

We estimate about 0.5 GW of installed data center capacity (IT load) in Norway at the end of 2025, about 3% of Europe and number 23 of the 33 countries in our model. This is a DC Market Insights estimate, benchmarked against dated public figures.

How many data centers are there in Norway?

Our Data Center Tracker lists 22 sites in Norway (15 operational, 2 under construction, 5 planned), run by 8 operators. Each site is verified from operator, planning or utility sources; the list grows as new sites are confirmed.

Which companies have the most tracked data center capacity in Norway?

By capacity stated at their sites (operational plus pipeline), the largest in our tracker are Green Mountain, atNorth, Nscale. Site capacity is counted only where a source states it.

What rules apply to data centers in Norway?

Our Power and Policy Tracker lists 6 government measures in force for Norway, such as incentives, tariffs, grid rules and national plans, each linked to the official source.

How will Norway data center capacity grow to 2035?

The full data pack gives installed capacity for Norway by year from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases and the main metro hubs.