France Data Center Capacity

Installed data center capacity in France (MW, IT load), its share of the region, tracked sites, recent deals and the rules in force. Forecast to 2035 in the data pack.

Data pack · Updated 12 November 2026

How much data center capacity France has installed, how it compares with the rest of Europe, and what our trackers show about its sites, operators, deals and rules.

1.2 GWInstalled, end 2025IT load, DC Market Insights estimate
7%Share of Europe2025
#13Rank among 33 countriesInstalled capacity, 2025
109Sites in our tracker33 with a stated MW

France data center capacity at a glance

France had about 1.2 GW of installed data center capacity (IT load) at the end of 2025, by our estimate. That is about 7% of the capacity in Europe and puts France at number 13 of the 33 countries in our global model. Our Data Center Tracker holds 109 sites in France run by 20 operators: 93 operational, 2 under construction and 14 planned. Our trackers also hold 11 verified deals and 4 government measures in force for the country.

Installed capacity is IT load, the power available to servers, storage and network. The country figure comes from the same model as the global and regional totals and is benchmarked against dated public figures. Site figures below are what each source states, often a campus’s full build-out, so they are not the same measure.

What our tracker holds for France

338 MWStated at operational sites (93)
216 MWUnder construction (2 sites)
2,206 MWPlanned (14 sites)
20Operators

Largest tracked sites

SiteOperatorCityStatusMW
Data4 Escaudain campusData4EscaudainPlanned700
Vantage Bordeaux campusVantage Data CentersBordeauxPlanned400
Data4 PAR01 campusData4NozayOperational250
Data4 PAR03 AI campusData4NozayPlanned250
Data Hills Aulnay-sous-Bois data centerData HillsAulnay-sous-BoisPlanned240
Dugny Digital Hub (PAR15-PAR17)Digital RealtyDugnyUnder construction176 IT
CDG CampusCloudHQLissesPlanned150 IT
PIPA-DC1 Blyes data centerPIPA-DC1BlyesPlanned130 IT
NTT DATA Paris 1 Data CenterNTT DATALe Coudray-MontceauxPlanned84 IT
Equinix PA15 (Meudon hyperscale project)EquinixMeudonPlanned80

Every France site on the Data Center Map

Where the sites are

CitySitesOperatorsMW stated, live
Paris941
Roubaix91n/a
Marseille73n/a
Saint-Denis62n/a
La Courneuve51n/a
Aubervilliers42n/a
Gravelines41n/a
Les Ulis3224

Cities with the most tracked sites. MW only where a source states it.

Who runs them

OperatorSitesMW liveMW pipeline
Data44255950
Vantage Data Centers1n/a400
Data Hills1n/a240
Digital Realty19n/a176
Colt DCS524137
CloudHQ1n/a150
PIPA-DC11n/a130
NTT DATA1n/a84

Operators ranked by MW stated at their tracked sites in France.

Power context

Rules in force

  • IncentiveLoi n° 2026-403 de simplification de la vie économique: data centres eligible for projet d'intérêt national majeur (art. 35)
  • EfficiencyPUE target of 1.20 by 2030 for the largest data centres under the tertiary-sector decree
  • GridCRE-approved electrical capacity pre-reservation procedure (fast-track connection) for high-power sites
  • EfficiencyAnnual energy and water performance reporting by large data centres under the EU Energy Efficiency Directive

From government sources. Power and policy in France

Recent deals

  • Oct 2026 · Land / campusFreehold interest in land under Digital Realty's Dugny campus, USD 90 m
  • Sep 2026 · M&APHOCEA DC
  • Aug 2026 · Land / campusHRS headquarters site, Champagnier (Isère), 14,100 sqm, to be converted to a data center
  • Jul 2026 · JV / partnershipOrange France data centre platform (5 data centres on 4 campuses: Chevilly-Larue, Aubervilliers, Chartres, Val-de-Reuil), 400 MW, USD 3.4 bn
  • Jul 2026 · JV / partnership48MW fully fitted data centre, Paris Availability Zone, 48 MW, USD 1.1 bn
  • Jul 2026 · JV / partnershipTwo AI gigafactory sites FR-SXB1 and FR-SXB2, Strasbourg region, 42 MW

Deal Tracker

Other countries in Europe

Installed capacity, end 2025, DC Market Insights estimate. All countries and regions

France in the full data pack

By year to 2035

Installed MW for France from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases.

Leading hubs

Live and pipeline MW for the main metro markets, with the basis of each figure.

Every tracked site

The full site list with operator, location, status, MW and source, refreshed from our tracker.

Frequently asked questions

How much data center capacity does France have?

We estimate about 1.2 GW of installed data center capacity (IT load) in France at the end of 2025, about 7% of Europe and number 13 of the 33 countries in our model. This is a DC Market Insights estimate, benchmarked against dated public figures.

How many data centers are there in France?

Our Data Center Tracker lists 109 sites in France (93 operational, 2 under construction, 14 planned), run by 20 operators. Each site is verified from operator, planning or utility sources; the list grows as new sites are confirmed.

Which companies have the most tracked data center capacity in France?

By capacity stated at their sites (operational plus pipeline), the largest in our tracker are Data4, Vantage Data Centers, Data Hills. Site capacity is counted only where a source states it.

What rules apply to data centers in France?

Our Power and Policy Tracker lists 4 government measures in force for France, such as incentives, tariffs, grid rules and national plans, each linked to the official source.

How will France data center capacity grow to 2035?

The full data pack gives installed capacity for France by year from 2020 to 2035, in the same model as the global and regional totals, with low, base and high cases and the main metro hubs.