Data Center Power & Policy in Hong Kong
Every government action on data centers and power in Hong Kong that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.
In short
As of 22 October 2026, DC Market Insights tracks 12 government actions on data centers and power in Hong Kong, 10 of them in force. We have found no moratorium or restriction on new data centers in force in Hong Kong. 2 incentive schemes apply, including HK$3 billion AI Subsidy Scheme for Cyberport AI Supercomputing Centre.
Market snapshot
Hong Kong power and policy: key facts
- Industrial electricity price: 180 USD/MWh (2026). Rank 7 of 26 tracked countries, highest first.
- Grid emission factor: 0.59 kgCO2/kWh (2025). Rank 5 of 31 tracked countries, highest first.
- Latest change: Clean Energy Transmission System enhancement by end-2026 for Mainland zero-carbon imports (Secretary for Environment and Ecology (LegCo reply), 29 Apr 2026).
- By type: 3 plan or strategy, 2 incentive, 2 power tariff and 1 grid access.
Power indicators for Hong Kong
Latest official figure for each indicator, with earlier years where we have them.
In force now in Hong Kong
Power tariff (2)
2026 electricity tariffs: CLP 140.6 and HK Electric 163.3 cents per kWh average net tariff
After review under the Scheme of Control Agreements, CLP Power reduced its 2026 average Net Tariff by 2.6 per cent to 140.6 cents per kWh and HK Electric reduced its average Net Tariff by 2.2 per cent to 163.3 cents per kWh, helped by lower fuel clause charges.
140.6 HK cents/kWh CLP average Net Tariff 2026; HK Electric 163.3 HK cents/kWh
Scheme of Control Agreements: permitted rate of return cut to 8 per cent, 15-year term
New Scheme of Control Agreements (SCAs) with CLP Power and HK Electric, signed 25 April 2017, reduce the permitted rate of return of the power companies to 8 per cent and run for a 15-year term (replacing a 10-year term plus 5-year option). They also introduce a Feed-in Tariff and sale of RE certificates by the power companies. Under the SCAs the Government performs a gate-keeping role on annual tariff reviews.
8 % Permitted rate of return; 15-year term
Incentive (2)
HK$3 billion AI Subsidy Scheme for Cyberport AI Supercomputing Centre
The Government allocated HK$3 billion for a three-year AI Subsidy Scheme to help local universities, R&D centres and enterprises use the computing power of Cyberport's AI Supercomputing Centre (AISC). Deployment began in December 2024; about 20 projects approved with average subsidy at 70 per cent of list price and average utilisation around 80 per cent.
3 HKD billion Three-year scheme; applications open since October 2024
Waiver fee exemption for data centres in parts of industrial buildings aged 15+ years
The Government exempts the waiver fees for change of use to data centres in parts of industrial buildings aged 15 years or above in Industrial and OU(Business/Commercial) zones, approved by the Lands Department, for the lifetime of the existing building or until lease expiry, whichever is earlier. The measure continued after 31 March 2016; LandsD and OGCIO aim to approve new applications in around two weeks. The Digital Policy Office still lists promotion of these industrial-building incentive measures.
15 years Minimum building age for eligibility
Renewable energy (1)
Feed-in Tariff Scheme for distributed renewable energy (until 2033)
Under the SCAs a Feed-in Tariff lets private RE installations sell power to CLP and HK Electric at $4 to $2.5 per kWh. Some 26,000 applications approved by September 2024, generating about 399 million kWh (CLP) and 15 million kWh (HKE) a year, about 0.85 and 0.03 per cent of the two companies' fuel mix. The FiT lasts until 2033; target 7.5-10 per cent RE by 2035.
4 HKD/kWh (max rate) Prevailing FiT rates range HK$4 to HK$2.5 per kWh; scheme lasts until 2033 (exact end day not stated)
Efficiency rule (1)
Buildings Energy Efficiency (Amendment) Ordinance 2025 brings all data centres under the Building Energy Code
The amended Buildings Energy Efficiency Ordinance (Cap 610), gazetted on 20 June 2025, regulates the energy efficiency standards of building services installations for all data centres (previously data centre buildings and data centre portions of industrial buildings were outside the Ordinance). Registered Energy Assessor changes commenced on 20 September 2025; the remaining provisions commenced on 20 September 2026.
Regulation (1)
GBA Standard Contract for cross-boundary personal information flow extended to all sectors
The facilitation measure on the Standard Contract for Cross-boundary Flow of Personal Information within the Guangdong-Hong Kong-Macao Greater Bay Area (Mainland, Hong Kong), first piloted from December 2023 for banking, credit referencing and healthcare, was extended from 1 November 2024 to all sectors in the nine Mainland GBA cities and Hong Kong.
Plan or strategy (2)
Zero-carbon electricity target of 60-70 per cent by 2035, incl. 7.5-10 per cent local renewables
In 2025 zero-carbon energy (nuclear and renewable) was about one-fourth of Hong Kong's electricity fuel mix, natural gas over 50 per cent and coal under 20 per cent. The Government aims to raise zero-carbon energy to about 60-70 per cent by 2035, including 7.5-10 per cent local renewable energy, with more Mainland zero-carbon imports after the Clean Energy Transmission System is enhanced by end-2026.
60 % (lower bound, 2035) Target 60-70% zero-carbon share by 2035
Sandy Ridge Data Facility Cluster site awarded for high-tier data centres
On 2 March 2026 the Government awarded the Sandy Ridge Data Facility Cluster site (over 110,000 sq m, total GFA 250,000 sq m) to Hong Kong Range Intelligent Computing Technology Company Limited on a 50-year land grant, with a premium proposal of HK$581 million. The site is dedicated to high-tier data centre use and related industries; the Sandy Ridge rezoning was completed in November 2025 (Digital Policy Office).
581 HKD million Premium proposal of the tender; land grant term 50 years
Other (1)
Sandy Ridge I&T site expanded to 10 hectares for data centres; Data Centre Facilitation Unit measures
The 2024 Policy Address (delivered 16 October 2024) announced that the Sandy Ridge I&T site would be expanded to 10 hectares for use as data centres and related purposes. The Digital Policy Office also lists four standing facilitation measures: a Data Centre Facilitation Unit and thematic information portal, promotion of Hong Kong as a prime Asia Pacific data centre location, promotion of incentive measures for industrial buildings, and identifying sites for high-tier data centres with appropriate land disposal arrangements.
10 hectares Sandy Ridge site size per 2024 Policy Address (16 Oct 2024); the Digital Policy Office page gives no page date
Announced and proposed
Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.
Clean Energy Transmission System enhancement by end-2026 for Mainland zero-carbon imports
The Government states that with the enhancement of the Clean Energy Transmission System by end-2026, Hong Kong expects to import more zero-carbon energy from the Chinese Mainland, supporting the 2035 zero-carbon electricity target.
Timeline of data center and power policy in Hong Kong
| Date | Action | Type | Status | Authority |
|---|---|---|---|---|
| 29 Apr 2026 | Clean Energy Transmission System enhancement by end-2026 for Mainland zero-carbon imports | Grid access | Announced | Secretary for Environment and Ecology (LegCo reply) |
| 29 Apr 2026 | Zero-carbon electricity target of 60-70 per cent by 2035, incl. 7.5-10 per cent local renewables | Plan or strategy | In force | Secretary for Environment and Ecology (LegCo reply) |
| 2 Mar 2026 | Sandy Ridge Data Facility Cluster site awarded for high-tier data centres North District (Northern Metropolis) | Plan or strategy | In force | Innovation, Technology and Industry Bureau (ITIB) |
| 2 Jan 2026 | HK$3 billion AI Subsidy Scheme for Cyberport AI Supercomputing Centre | Incentive | In force | Digital Policy Office / Cyberport |
| 18 Nov 2025 | 2026 electricity tariffs: CLP 140.6 and HK Electric 163.3 cents per kWh average net tariff | Power tariff | In force | Environment and Ecology Bureau (EEB); CLP Power; HK Electric |
| 10 Oct 2025 | Sandy Ridge data facility land tender: two-envelope approach, min 70% GFA for high-tier data centres North District (Northern Metropolis) | Plan or strategy | Expired | Lands Department / HKSAR Government |
| 20 Jun 2025 | Buildings Energy Efficiency (Amendment) Ordinance 2025 brings all data centres under the Building Energy Code | Efficiency rule | In force | Electrical and Mechanical Services Department (EMSD) / Environment and Ecology Bureau |
| 20 Nov 2024 | Feed-in Tariff Scheme for distributed renewable energy (until 2033) | Renewable energy | In force | Secretary for Environment and Ecology (LegCo reply) |
| 1 Nov 2024 | GBA Standard Contract for cross-boundary personal information flow extended to all sectors | Regulation | In force | Innovation, Technology and Industry Bureau (ITIB) with Cyberspace Administration of China |
| 16 Oct 2024 | Sandy Ridge I&T site expanded to 10 hectares for data centres; Data Centre Facilitation Unit measures | Other | In force | Digital Policy Office (DPO) |
| 25 Apr 2017 | Scheme of Control Agreements: permitted rate of return cut to 8 per cent, 15-year term | Power tariff | In force | HKSAR Government (Environment Bureau, now EEB) |
| 30 Mar 2016 | Waiver fee exemption for data centres in parts of industrial buildings aged 15+ years | Incentive | In force | Lands Department / OGCIO (now Digital Policy Office) |
How Hong Kong compares
Latest official figures for the countries we track.
| Country | Industrial power price | Renewable share | Grid emission factor | Restrictions in force | Incentives in force |
|---|---|---|---|---|---|
| Argentina | — | 19.6% (2025) | 0.28 kgCO2/kWh (2022) | 0 | 2 |
| Australia | — | 39% (2025) | — | 0 | 2 |
| Bangladesh | — | 2% (2025) | — | 0 | 0 |
| Belgium | 183 USD/MWh (2025) | 34.3% (2025) | 0.19 kgCO2/kWh (2024) | 0 | 0 |
| Brazil | — | 86.8% (2025) | 0.07 kgCO2/kWh (2025) | 0 | 1 |
| Canada | — | 63.9% (2024) | 0.10 kgCO2/kWh (2022) | 2 | 0 |
| Chile | — | 66% (2025) | 0.24 kgCO2/kWh (2023) | 0 | 0 |
| Colombia | — | — | 0.22 kgCO2/kWh (2024) | 0 | 2 |
| Denmark | 134 USD/MWh (2025) | 81.5% (2024) | 0.11 kgCO2/kWh (2024) | 1 | 0 |
| Ecuador | — | — | 0.16 kgCO2/kWh (2024) | 1 | 0 |
| Finland | 58.4 USD/MWh (2025) | 57% (2024) | 0.03 kgCO2/kWh (2025) | 0 | 0 |
| France | 104 USD/MWh (2025) | 27% (2025) | 0.02 kgCO2/kWh (2025) | 0 | 1 |
| Germany | 180 USD/MWh (2025) | 58.8% (2025) | 0.34 kgCO2/kWh (2025) | 1 | 0 |
| Guatemala | 84.5 USD/MWh (2025) | 53.5% (2024) | 0.29 kgCO2/kWh (2024) | 0 | 2 |
| Hong Kong | 180 USD/MWh (2026) | — | 0.59 kgCO2/kWh (2025) | 0 | 2 |
| India | 82.1 USD/MWh (2025) | 28.7% (2026) | 0.68 kgCO2/kWh (2025) | 0 | 5 |
| Indonesia | 62.9 USD/MWh (2024) | 16.3% (2025) | 0.68 kgCO2/kWh (2024) | 0 | 1 |
| Ireland | 234 USD/MWh (2025) | 41.3% (2024) | 0.20 kgCO2/kWh (2025) | 2 | 0 |
| Italy | 184 USD/MWh (2025) | 48% (2025) | 0.20 kgCO2/kWh (2025) | 0 | 0 |
| Japan | — | 23.1% (2024) | 0.45 kgCO2/kWh (2024) | 0 | 0 |
| Kazakhstan | — | 14.6% (2025) | 0.81 kgCO2/kWh (2025) | 0 | 0 |
| Kyrgyzstan | 41.7 USD/MWh (2026) | 88% (2024) | 0.16 kgCO2/kWh (2019) | 1 | 1 |
| Luxembourg | 165 USD/MWh (2025) | 23.3% (2025) | — | 0 | 0 |
| Malaysia | 105 USD/MWh (2026) | 21% (2025) | 0.74 kgCO2/kWh (2024) | 1 | 1 |
| Mexico | — | — | 0.44 kgCO2/kWh (2023) | 0 | 0 |
| Nepal | — | — | — | 0 | 0 |
| Netherlands | 148 USD/MWh (2025) | 49% (2025) | 0.20 kgCO2/kWh (2024) | 4 | 0 |
| Pakistan | 97.5 USD/MWh (2026) | 34.7% (2025) | — | 0 | 1 |
| Panama | 66.3 USD/MWh (2025) | 74.7% (2025) | 0.15 kgCO2/kWh (2024) | 0 | 1 |
| Peru | — | 62.6% (2025) | — | 0 | 1 |
| Russia | — | 17.6% (2025) | — | 2 | 0 |
| Singapore | 189 USD/MWh (2025) | 2.1% (2024) | 0.40 kgCO2/kWh (2024) | 0 | 0 |
| South Korea | — | 9.8% (2025) | — | 0 | 0 |
| Spain | 113 USD/MWh (2025) | 55.5% (2025) | — | 0 | 0 |
| Sri Lanka | — | 60.2% (2025) | — | 0 | 0 |
| Sweden | 78.5 USD/MWh (2025) | — | 0.06 kgCO2/kWh (2023) | 0 | 0 |
| Switzerland | 240 USD/MWh (2026) | 70.8% (2025) | 0.13 kgCO2/kWh (2022) | 0 | 0 |
| United Arab Emirates | 120 USD/MWh (2026) | 8.8% (2024) | 0.47 kgCO2/kWh (2024) | 0 | 0 |
| United Kingdom | 234 USD/MWh (2026) | 52.1% (2025) | 0.15 kgCO2/kWh (2026) | 1 | 1 |
| United States | 86.2 USD/MWh (2025) | 24% (2025) | 0.35 kgCO2/kWh (2023) | 0 | 1 |
| Uruguay | 101 USD/MWh (2026) | 98% (2025) | 0.01 kgCO2/kWh (2025) | 0 | 3 |
| Uzbekistan | 83.3 USD/MWh (2026) | 19.4% (2025) | — | 1 | 0 |
Questions
Is there a data center moratorium in Hong Kong?
We have found no moratorium or restriction on new data centers in force in Hong Kong as of 22 October 2026. Proposed or announced measures, if any, are listed in the timeline.
What incentives does Hong Kong offer data centers?
In force: HK$3 billion AI Subsidy Scheme for Cyberport AI Supercomputing Centre and Waiver fee exemption for data centres in parts of industrial buildings aged 15+ years. Each is listed with its authority and dates on this page.
What does electricity cost for data centers in Hong Kong?
The industrial electricity price in Hong Kong was 180 USD/MWh in 2026 (CLP Power 2026 average Net Tariff 140.6 HK cents/kWh (all customer classes, not a large-power-only tariff) = HK$1,406/MWh; converted at HKD 7.8 per USD (linked-rate midpoint, assumed as of 22 Oct 2026) = USD 180.3/MWh. HK Electric 163.3 HK cents/kWh = USD). Data center contracts can differ by voltage level, contract length and location.
Where does this data come from?
Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.
What counts as a restriction or moratorium?
A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.
How are power prices compared?
We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.
How often is it updated?
Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.
Global capacity
How much data center capacity does Hong Kong have?
Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.