Data Center Power & Policy in Brazil
Every government action on data centers and power in Brazil that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.
In short
As of 16 November 2026, DC Market Insights tracks 12 government actions on data centers and power in Brazil, 5 of them in force. We have found no moratorium or restriction on new data centers in force in Brazil. 1 incentive scheme applies: Law 15.504/2026: Redata special tax regime for data center services.
Market snapshot
Brazil power and policy: key facts
- Renewable share of electricity generation: 86.8% (2025). Rank 4 of 42 tracked countries, highest first.
- Grid emission factor: 0.07 kgCO2/kWh (2025). Rank 32 of 36 tracked countries, highest first.
- Latest change: Preliminary schedule for the 1st PNAST Access Season of 2027 (MME / ONS, 7 Oct 2026).
- By type: 6 grid access, 2 incentive, 2 regulation and 1 plan or strategy.
Power indicators for Brazil
Latest official figure for each indicator, with earlier years where we have them.
In force now in Brazil
Grid access (3)
1st PNAST Access Season 2026 drew 367 registrations at 64 SIN busbars
According to the ONS balance presented at the close of the 1st Access Season of 2026, 367 generation and consumption projects registered at 64 busbars of the National Interconnected System (SIN). Together they requested more than 20 GW of access.
MME Normative Ordinance 129/2026: rules for PNAST Access Seasons
Sets how Access Seasons work: ONS publishes remaining capacity separately for consumption and generation; where requests exceed capacity, the main criterion is the highest premium offered in R$/kW, paid upfront; bidders post a participation guarantee; winners that fail to pay or sign a transmission use contract (CUST) lose the capacity and are barred from the next two seasons. When load and generation compete without a specific directive, consumption has priority.
Decree 12.772/2025: National Transmission Access Policy (PNAST)
Replaces first-come access to the transmission grid with periodic Access Seasons run by the grid operator ONS; where demand at a connection point exceeds capacity, a competitive process allocates it and the proceeds lower tariffs. Pending consumer requests (including large loads such as data centers) had to post a financial guarantee within 45 days to stay in line. Amends Decree 5.597/2005 to allow new consumer units connected at 230 kV or higher and shared connection points for industrial clusters; EPE must map large consumers each year.
Incentive (1)
Law 15.504/2026: Redata special tax regime for data center services
Creates Redata inside Law 11.196/2005. Qualifying data center projects get PIS/Pasep, Cofins, IPI and (where no national equivalent exists) import tax suspended on fixed-asset purchases, converted to a zero rate once commitments are met. Conditions: offer at least 10% of capacity to the domestic market (or invest an extra 10% in R&D), meet all power demand with renewable or low-emission supply contracts or self-generation, keep WUE at or below 0.05 L/kWh, invest 2% of the value of the goods in national R&D, and publish sustainability indicators. Commitments are cut by 20% for sites in the North, Northeast and Centre-West. Benefit term of 5 years (Art. 11-J).
0.05 L/kWh maximum Water Usage Effectiveness for Redata beneficiaries
Regulation (1)
Ceará Law 19.849/2026 – environmental licensing regime for data centers by size and polluting potential
This Ceará state law sets up a state policy to encourage battery storage systems and data centers. It also creates a dedicated environmental licensing regime. Its annex classes data centers as having high polluting-degrading potential, with size classes based on power. Micro-size sites are licensed by municipal agencies, or by Semace where no qualified municipal agency exists. Small and medium sites go through two licensing stages; large and exceptional sites go through three. Medium, large and exceptional data centers must keep permanent environmental monitoring and share performance data when asked. Semace is to issue a normative instruction. The state may also grant ICMS treatment, subject to Confaz.
3 licensing stages Three-stage licensing (LP, LI, LO) applies to large and exceptional data centers; small and medium need two stages (LP and LIO). The law takes effect on publication (D.O. 16.07.26).
Announced and proposed
Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.
Preliminary schedule for the 1st PNAST Access Season of 2027
From 2027 PNAST will run two Access Seasons per year. The preliminary schedule for the first 2027 season, which the MME says may still change, has these steps: registration instructions and the methodology technical note on 4 December, the process rules (sistemática) on 18 December, a registration window from 4 to 18 January 2027, admission of requests by 2 February, and the Competitive Process on 4 to 6 May 2027.
ANEEL Public Consultation 36/2026: transition rule for large-load expansions under PNAST
ANEEL proposes adapting transmission rules (REN 1.017/2022, network procedures) to PNAST, with a transition rule for load expansions by consumers already in the access process before the new model, including data centers. ONS would prioritise expansions due in 2029 for requests filed by 22 January 2026, subject to remaining capacity and technical validation; it is not an automatic capacity reserve. Contributions run 8 October to 22 November 2026.
Bill PL 1.680/2025: National Data Center Policy
Bill to create a National Data Center Policy: priority access to the transmission grid for projects in regions with surplus generation, companies may finance their own grid connection without passing the cost to tariffs, incentives to spread data centers across regions, and a 'data embassies' regime for foreign government data. Tax exemptions were removed by the rapporteur. Approved by a Chamber of Deputies committee in June 2026; still needs the Finance and Justice committees and the Senate.
PL 414/2026 – mandatory EIA/RIMA for large data centers
This federal bill would make a full Environmental Impact Study and Report (EIA/RIMA) mandatory for installing or expanding any large data center. The requirement would apply even in export processing zones (ZPE), industrial districts or areas that already hold a licence. It would also require in-person public hearings in affected municipalities, continuous public monitoring of water, energy, emissions, noise, PUE and WUE, and penalties up to suspension of licences or shutdown of the site. Facilities not yet holding an operating licence could only get one after meeting the bill's requirements.
PL 414/2026 – siting ban for large data centers near homes, schools, hospitals and traditional communities
This is a federal bill filed by Deputy Vanderlan Alves (União Brasil/CE) in the Chamber of Deputies. It would set national general rules for installing, operating, expanding and decommissioning large data centers. Among its restrictions, it would bar large data centers within a set distance of consolidated residential areas, schools, hospitals and sensitive public facilities, and indigenous, quilombola or traditional communities. It would also limit cooling water to reuse, industrial, desalinated or closed-loop sources, and ban drawing cooling water from deep wells, aquifers or public reservoirs. The bill has been attached to PL 2080/2025 and is subject to conclusive review by committees.
1 km Minimum distance from consolidated residential areas, schools, hospitals, sensitive public facilities and indigenous, quilombola or traditional communities. Applies only to 'Data Centers de Grande Porte' as the bill defines them.
Timeline of data center and power policy in Brazil
| Date | Action | Type | Status | Authority |
|---|---|---|---|---|
| 7 Oct 2026 | Preliminary schedule for the 1st PNAST Access Season of 2027 | Grid access | Announced | MME / ONS |
| 7 Oct 2026 | 1st PNAST Access Season 2026 drew 367 registrations at 64 SIN busbars | Grid access | In force | ONS (Operador Nacional do Sistema Elétrico) |
| 6 Oct 2026 | ANEEL Public Consultation 36/2026: transition rule for large-load expansions under PNAST | Grid access | Proposed | National Electric Energy Agency (ANEEL) |
| 15 Sep 2026 | Law 15.504/2026: Redata special tax regime for data center services | Incentive | In force | Presidency of the Republic / National Congress |
| 16 Jul 2026 | Ceará Law 19.849/2026 – environmental licensing regime for data centers by size and polluting potential | Regulation | In force | Governo do Estado do Ceará; Assembleia Legislativa do Estado do Ceará; Semace |
| 16 Jun 2026 | Bill PL 1.680/2025: National Data Center Policy | Plan or strategy | Proposed | Chamber of Deputies |
| 24 Apr 2026 | MME Normative Ordinance 129/2026: rules for PNAST Access Seasons | Grid access | In force | Ministry of Mines and Energy (MME) |
| 9 Feb 2026 | PL 414/2026 – mandatory EIA/RIMA for large data centers | Regulation | Proposed | Câmara dos Deputados (Dep. Vanderlan Alves) |
| 9 Feb 2026 | PL 414/2026 – siting ban for large data centers near homes, schools, hospitals and traditional communities | Restriction | Proposed | Câmara dos Deputados (Dep. Vanderlan Alves) |
| 4 Feb 2026 | Deadline of 29 May 2026 for new Rede Básica access requests outside Access Seasons | Grid access | Expired | ONS (Operador Nacional do Sistema Elétrico) |
| 5 Dec 2025 | Decree 12.772/2025: National Transmission Access Policy (PNAST) | Grid access | In force | Presidency of the Republic / Ministry of Mines and Energy |
| 17 Sep 2025 | Provisional Measure 1.318/2025 creating Redata (lapsed) | Incentive | Expired | Presidency of the Republic |
How Brazil compares
Latest official figures for the countries we track.
| Country | Industrial power price | Renewable share | Grid emission factor | Restrictions in force | Incentives in force |
|---|---|---|---|---|---|
| Argentina | — | 19.6% (2025) | 0.28 kgCO2/kWh (2022) | 0 | 2 |
| Australia | — | 39% (2025) | — | 0 | 2 |
| Austria | 169 USD/MWh (2026) | 78% (2025) | 0.15 kgCO2/kWh (2023) | 0 | 0 |
| Bangladesh | — | 2% (2025) | — | 0 | 0 |
| Belgium | 183 USD/MWh (2025) | 34.3% (2025) | 0.19 kgCO2/kWh (2024) | 0 | 0 |
| Brazil | — | 86.8% (2025) | 0.07 kgCO2/kWh (2025) | 0 | 1 |
| Canada | — | 63.9% (2024) | 0.10 kgCO2/kWh (2022) | 6 | 0 |
| Chile | — | 66% (2025) | 0.24 kgCO2/kWh (2023) | 0 | 0 |
| China | — | 38% (2025) | 0.53 kgCO2/kWh (2023) | 2 | 0 |
| Colombia | — | — | 0.22 kgCO2/kWh (2024) | 0 | 2 |
| Denmark | 134 USD/MWh (2025) | 81.5% (2024) | 0.11 kgCO2/kWh (2024) | 1 | 0 |
| Ecuador | — | — | 0.16 kgCO2/kWh (2024) | 1 | 0 |
| Finland | 58.4 USD/MWh (2025) | 57% (2024) | 0.03 kgCO2/kWh (2025) | 0 | 0 |
| France | 104 USD/MWh (2025) | 27% (2025) | 0.02 kgCO2/kWh (2025) | 0 | 1 |
| Germany | 180 USD/MWh (2025) | 58.8% (2025) | 0.34 kgCO2/kWh (2025) | 1 | 0 |
| Guatemala | 84.5 USD/MWh (2025) | 53.5% (2024) | 0.29 kgCO2/kWh (2024) | 0 | 2 |
| Hong Kong | 180 USD/MWh (2026) | — | 0.59 kgCO2/kWh (2025) | 0 | 2 |
| Iceland | 42.9 USD/MWh (2022) | 100% (2026) | — | 1 | 2 |
| India | 82.1 USD/MWh (2025) | 28.7% (2026) | 0.68 kgCO2/kWh (2025) | 1 | 5 |
| Indonesia | 62.9 USD/MWh (2024) | 16.3% (2025) | 0.68 kgCO2/kWh (2024) | 0 | 1 |
| Ireland | 234 USD/MWh (2025) | 41.3% (2024) | 0.20 kgCO2/kWh (2025) | 2 | 0 |
| Italy | 184 USD/MWh (2025) | 48% (2025) | 0.20 kgCO2/kWh (2025) | 0 | 0 |
| Japan | — | 23.1% (2024) | 0.45 kgCO2/kWh (2024) | 0 | 0 |
| Kazakhstan | — | 14.6% (2025) | 0.81 kgCO2/kWh (2025) | 0 | 0 |
| Kyrgyzstan | 41.7 USD/MWh (2026) | 88% (2024) | 0.16 kgCO2/kWh (2019) | 1 | 1 |
| Luxembourg | 165 USD/MWh (2025) | 23.3% (2025) | — | 0 | 0 |
| Malaysia | 105 USD/MWh (2026) | 21% (2025) | 0.74 kgCO2/kWh (2024) | 1 | 1 |
| Mexico | — | — | 0.44 kgCO2/kWh (2023) | 0 | 0 |
| Nepal | — | — | — | 0 | 0 |
| Netherlands | 148 USD/MWh (2025) | 49% (2025) | 0.20 kgCO2/kWh (2024) | 4 | 0 |
| Pakistan | 97.5 USD/MWh (2026) | 34.7% (2025) | — | 0 | 1 |
| Panama | 66.3 USD/MWh (2025) | 74.7% (2025) | 0.15 kgCO2/kWh (2024) | 0 | 1 |
| Paraguay | 33.0 USD/MWh (2026) | — | — | 1 | 2 |
| Peru | — | 62.6% (2025) | — | 0 | 1 |
| Philippines | — | 22.2% (2024) | 0.71 kgCO2/kWh (2017) | 1 | 2 |
| Russia | — | 17.6% (2025) | — | 2 | 0 |
| Singapore | 189 USD/MWh (2025) | 2.1% (2024) | 0.40 kgCO2/kWh (2024) | 1 | 0 |
| South Korea | — | 9.8% (2025) | — | 0 | 0 |
| Spain | 113 USD/MWh (2025) | 55.5% (2025) | — | 1 | 0 |
| Sri Lanka | — | 60.2% (2025) | — | 0 | 0 |
| Sweden | 78.5 USD/MWh (2025) | — | 0.06 kgCO2/kWh (2023) | 0 | 0 |
| Switzerland | 240 USD/MWh (2026) | 70.8% (2025) | 0.13 kgCO2/kWh (2022) | 0 | 0 |
| Taiwan | — | 12.7% (2025) | 0.47 kgCO2/kWh (2024) | 1 | 0 |
| Thailand | 120 USD/MWh (2026) | — | 0.48 kgCO2/kWh (2026) | 0 | 2 |
| United Arab Emirates | 120 USD/MWh (2026) | 8.8% (2024) | 0.47 kgCO2/kWh (2024) | 0 | 0 |
| United Kingdom | 234 USD/MWh (2026) | 52.1% (2025) | 0.15 kgCO2/kWh (2026) | 1 | 1 |
| United States | 86.2 USD/MWh (2025) | 24% (2025) | 0.35 kgCO2/kWh (2023) | 0 | 1 |
| Uruguay | 101 USD/MWh (2026) | 98% (2025) | 0.01 kgCO2/kWh (2025) | 0 | 3 |
| Uzbekistan | 83.3 USD/MWh (2026) | 19.4% (2025) | — | 1 | 0 |
| Venezuela | — | 77% (2023) | — | 0 | 1 |
Questions
Is there a data center moratorium in Brazil?
We have found no moratorium or restriction on new data centers in force in Brazil as of 16 November 2026. Proposed or announced measures, if any, are listed in the timeline.
What incentives does Brazil offer data centers?
In force: Law 15.504/2026: Redata special tax regime for data center services. Each is listed with its authority and dates on this page.
How much of Brazil’s electricity is renewable?
Renewables supplied 86.8% of electricity generation in Brazil in 2025.
Where does this data come from?
Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.
What counts as a restriction or moratorium?
A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.
How are power prices compared?
We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.
How often is it updated?
Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.
Global capacity
How much data center capacity does Brazil have?
Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.
Choosing a market or a site?
Our analysts prepare country briefings on power, grid access, incentives and permits, with every source, in Excel.