Data Center Power & Policy in Germany

Every government action on data centers and power in Germany that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.

In short

As of 15 November 2026, DC Market Insights tracks 28 government actions on data centers and power in Germany, 19 of them in force. Germany has 1 restriction on new data centers in force: Rechenzentrenkonzept – Aktualisierung des Gewerbeflächenentwicklungsprogramms (Stadtverordnetenbeschluss § 1838).

28Actions tracked
19In force
180 USD/MWhIndustrial power price
58.8%Renewable share of generation

Market snapshot

Germany power and policy: key facts

  • Industrial electricity price: 180 USD/MWh (2025). Rank 8 of 30 tracked countries, highest first.
  • Renewable share of electricity generation: 58.8% (2025). Rank 14 of 42 tracked countries, highest first.
  • Grid emission factor: 0.34 kgCO2/kWh (2025). Rank 15 of 36 tracked countries, highest first.
  • Latest change: Gesetz zur Beschleunigung der Umsetzung der Energieeffizienzrichtlinie (EnEfG-Novelle), Drucksache 21/8027 (Bundesregierung / Deutscher Bundestag, 24 Sep 2026).
  • By type: 13 grid access, 3 efficiency rule, 3 restriction and 3 regulation.

Power indicators for Germany

Latest official figure for each indicator, with earlier years where we have them.

Industrial electricity price 180 USD/MWh 2025 · Eurostat nrg_pc_205, non-household, band IE (20,000-69,999 MWh), excl. VAT and recoverable taxes: 2025-S1 0.1584 and 2025-S2 0.1595 EUR/kWh, mean 158.95 EUR/MWh; converted at 2025 ECB annual average 1.1300 USD/EUR (Eurostat ert_bil_eur_a). 2026-S1: 0.1464 2024: 184 USD/MWh Eurostat
Renewable share of electricity generation 58.8% 2025 · Share of renewables in net electricity generation fed into the grid (SMARD), 257.5 of 437.6 TWh 2024: 58.5% Bundesnetzagentur (SMARD)
Grid emission factor 0.34 kgCO2/kWh 2025 · UBA CO2 emission factor of the German electricity mix, 344 g CO2/kWh; 2025 value is an estimate (UBA, 23.03.2026) 2024: 0.35 kgCO2/kWh Umweltbundesamt

In force now in Germany

Restriction (1)

  • RestrictionIn force

    Rechenzentrenkonzept – Aktualisierung des Gewerbeflächenentwicklungsprogramms (Stadtverordnetenbeschluss § 1838)

    Frankfurt city council, in its 13th session on 09.06.2022 (§ 1838), approved Magistrat proposal M 44 (Vortrag of 21.03.2022) in the version submitted: the data centre concept (Rechenzentrenkonzept) updating the city's Gewerbeflächenentwicklungsprogramm (GEP).

    Stadtverordnetenversammlung Frankfurt am Main · Frankfurt am Main · Stadtplanungsamt Frankfurt am Main

Grid access (11)

  • Grid accessIn force

    Batteriespeicher-Anschlussbegehren bei den ÜNB im ersten Quartal 2026

    Bundesnetzagentur data as at 1 April 2026 show new battery storage connection applications received by the TSOs in the first months of 2026. By the same date the TSOs had made 64 offers in 2026, including on older requests, totalling about 24.7 GW, almost as much as in all of 2025.

    6 GW Status as at 1 April 2026, published 2026-08-20. value_text shortens the quote with an ellipsis, hence confidence partly.

    Bundesnetzagentur (SMARD) · SMARD (Bundesnetzagentur) – Status of battery storage applications in 2025/2026

  • Grid accessIn force

    Bundesnetzagentur-Monitoring: Netzanschlussbegehren für Batteriespeicher 2025

    From its monitoring survey, the Bundesnetzagentur reports that German TSOs and DSOs received 18,158 connection requests for commercial battery storage at medium voltage and above in 2025. The BNetzA notes that some requests are for the same project at several sites. In 2025 operators made 1,937 offers covering 54.2 GW, including offers on older requests.

    573.5 GW Battery storage only, not data centres; relevant as competing demand in connection queues. value_text shortens the quote with an ellipsis, hence confidence partly.

    Bundesnetzagentur (SMARD) · SMARD (Bundesnetzagentur) – Status of battery storage applications in 2025/2026

  • Grid accessIn force

    Batteriespeicher-Anschlussbegehren bei den Verteilnetzbetreibern 2025

    Bundesnetzagentur monitoring data show the 2025 battery storage connection requests received by DSOs. Offers were made for 1,429 of them, about 8% of requests and about 4% of requested capacity.

    406.8 GW Applications newly received by DSOs in 2025, battery storage only.

    Bundesnetzagentur (SMARD) · SMARD (Bundesnetzagentur) – Status of battery storage applications in 2025/2026

  • Grid accessIn force

    Batteriespeicher-Anschlussbegehren bei den ÜNB 2025

    According to Bundesnetzagentur monitoring data, the TSOs received battery storage connection applications in 2025 as stated. Offers were made for 39 of them, about 10% of applications. Counting older requests, TSOs made 71 offers in 2025 with about 27.3 GW.

    166.7 GW Applications newly received by TSOs in 2025, battery storage only.

    Bundesnetzagentur (SMARD) · SMARD (Bundesnetzagentur) – Status of battery storage applications in 2025/2026

  • Grid accessIn force

    Positionspapier der Übertragungsnetzbetreiber (ÜNB) zu Netzanschlüssen – Reifegradverfahren

    Joint position paper of the four German TSOs (ÜNB), dated 05.02.2026, proposing a readiness-based allocation procedure (Reifegradverfahren) for transmission grid connections, which the TSOs intended to introduce on 1 April 2026; the paper names data centres among the connection requests to be handled and proposes capacity quotas for certain uses.

    50Hertz, Amprion, TenneT, TransnetBW (ÜNB) · Effective 1 Apr 2026

  • Grid accessIn force

    Verbindliche Reservierungen für Datacenter-Anschlüsse bei MITNETZ STROM

    Of the data centre connection requests in the MITNETZ STROM area, nine projects have a binding capacity reservation of about 1.4 GW in total. This shows how much of the data centre queue in this East German distribution grid has a firm reservation.

    1.4 GW A subset of the 90 data centre requests in the same press release.

    MITNETZ STROM (Mitteldeutsche Netzgesellschaft Strom mbH)

  • Grid accessIn force

    Warteschlange für Datacenter-Netzanschlüsse im Verteilnetz von MITNETZ STROM

    The distribution system operator MITNETZ STROM (enviaM group), whose grid covers parts of Saxony, Saxony-Anhalt, Brandenburg and Thuringia, reported 90 data centre connection requests with a combined 16.8 GW. On the demand side its grid so far has only three smaller data centres. The Lübbenau data centre is described as its largest single grid connection in recent years.

    16.8 GW Requested capacity across all data centre connection requests in the operator's area at the time of the press release.

    MITNETZ STROM (Mitteldeutsche Netzgesellschaft Strom mbH)

  • Grid accessIn force

    Verteilte Anschlusskapazität im Berliner Repartierungsverfahren 2025

    In the 2025 round Stromnetz Berlin shared out the capacity available in three grid areas pro rata among 37 requests. Ten otherwise eligible requests got nothing because the minimum partial capacity they would accept was above their pro-rata share. Connection concepts and offers for the 37 requests were due by 31 January 2026, and the next round was expected to start in April 2026.

    365 MVA Capacity available and allocated in the 2025 round across three grid areas.

    Stromnetz Berlin GmbH

  • Grid accessIn force

    Angefragte Leistung im Berliner Repartierungsverfahren 2025

    In Stromnetz Berlin's 2025 repartitioning round for very large high and medium voltage connections, 70 requests were received by the deadline. Stromnetz Berlin says the requested load is around 10 percent above the current annual peak load of the whole Berlin grid. After review, 47 requests were complete and eligible for allocation.

    2,300 MVA Requested capacity at the 30 June 2025 deadline, all applicant types (not only data centres).

    Stromnetz Berlin GmbH

  • Grid accessIn force

    Positionspapier zur Bemessung und Erhebung von Baukostenzuschüssen für Netzanschlüsse

    The Bundesnetzagentur published a position paper on construction cost contributions (Baukostenzuschuss), the one-off payment new or expanded grid connections make towards network expansion. Contributions are based on capacity. TSOs are to differentiate them into five tiers by grid connection point, depending on how a new load affects transmission needs, so that large consumers, storage and electrolysers are steered to grid-friendly sites. Contributions already agreed for projects concluded by 2024 or for 2025 remain valid. Feed-in plants are exempt by law.

    Bundesnetzagentur (Beschlusskammer 8) · Bundesnetzagentur – Pressemitteilung Positionspapier zu regionalen Preissignalen

  • Grid accessIn force

    Neues Zuteilungsverfahren für sehr große Netzanschlüsse in Berlin

    Stromnetz Berlin, together with the Berlin Senate economics department, introduced an allocation procedure for very large grid connections, for example data centres or large heat pumps. Previously these requests were served in order of completed application. Now the available capacity is set once a year for each grid area, published, and shared equally among all applicants. Smaller connections are not affected.

    3.5 MW The threshold applies to connection capacity above the stated figure.

    Stromnetz Berlin GmbH / Senatsverwaltung für Wirtschaft, Energie und Betriebe Berlin · Senatsverwaltung für Wirtschaft, Energie und Betriebe Berlin – Gemeinsame Pressemitteilung mit Stromnetz Berlin

Renewable energy (1)

  • Renewable energyIn force

    Energieeffizienzgesetz (EnEfG) § 11 Abs. 5 – Stromversorgung von Rechenzentren aus erneuerbaren Energien

    EnEfG § 11 Abs. 5: data centre operators must cover 50 percent of electricity consumption with renewable electricity on a balance-sheet basis from 1 January 2024 and 100 percent from 1 January 2027. The pending amendment bill (PP-DE-010) would move the 100 percent date to 1 January 2030.

    100 % renewable electricity required 50% from 1 Jan 2024; 100% from 1 Jan 2027 under current law

    Bundestag / Bundesregierung (BMWK) · Effective 1 Jan 2024

Efficiency rule (2)

  • Efficiency ruleIn force

    Energieeffizienzgesetz (EnEfG) § 11 Abs. 2 – Anteil wiederverwendeter Energie (Abwärmenutzung) in Rechenzentren

    EnEfG § 11 Abs. 2: data centres starting operation from 1 July 2026 must have a share of reused energy under DIN EN 50600-4-6 of at least 10 percent; 15 percent for those starting from 1 July 2027 and a planned 20 percent for those starting from 1 July 2028. Abs. 3 lists exemptions, e.g. heat-network agreements.

    10 % reused energy (ERF) minimum 10% from 1 July 2026, 15% from 1 July 2027, 20% (planned) from 1 July 2028

    Bundestag / Bundesregierung (BMWK) · Effective 1 Jul 2026

  • Efficiency ruleIn force

    Energieeffizienzgesetz (EnEfG) § 11 – Energieverbrauchseffektivität (PUE) von Rechenzentren

    EnEfG of 13.11.2023, § 11: data centres starting operation before 1 July 2026 must reach a PUE of 1.5 or less from 1 July 2027 and 1.3 or less from 1 July 2030 (annual average); data centres starting operation from 1 July 2026 must reach a PUE of 1.2 or less, within two years of commissioning. A government amendment bill (see PP-DE-010) proposes changes.

    1.2 PUE limit New DCs from 1 July 2026; existing DCs 1.5 from 1 July 2027 and 1.3 from 1 July 2030

    Bundestag / Bundesregierung (BMWK) · Effective 1 Jul 2026

Regulation (2)

  • RegulationIn force

    Möglichkeit des Ausschlusses von Rechenzentren in Bebauungsplänen (Antwort der Hessischen Landesregierung)

    The Hessian economy ministry states that data centers usually count as businesses that cause no significant disturbance. That makes them generally permitted in most land-use categories. Municipalities can exclude them in development plans where special urban-planning reasons exist, for example on the basis of a development concept under the Baugesetzbuch. Such concepts apply only to new or amended plans, not retroactively.

    Hessisches Ministerium für Wirtschaft, Energie, Verkehr, Wohnen und ländlichen Raum · Hessischer Landtag, Drucksache 21/1061

  • RegulationIn force

    Rechenzentrumsregister (Energieeffizienzregister für Rechenzentren) – Meldepflicht nach § 13 EnEfG und Delegierter Verordnung (EU) 2024/1364

    BMWK portal run by BAFA/Bundesstelle für Energieeffizienz. Operators of data centres with non-redundant rated connection capacity of 300 kW or more must report energy data under § 13 EnEfG (Annex 3); 500 kW+ by 15 August 2024, 300-500 kW by 1 July 2025, then annually by 31 March. The page cites Delegated Regulation (EU) 2024/1364 of 14 March 2024 and requires an energy or environmental management system by 1 July 2025.

    300 kW reporting threshold

    BMWK / BAFA (Bundesstelle für Energieeffizienz); European Commission · Effective 15 Aug 2024 · Bundesministerium für Wirtschaft (RZReg portal)

Plan or strategy (2)

  • Plan or strategyIn force

    Rechenzentrumsstrategie der Bundesregierung

    National data centre strategy published by BMDS on 18.03.2026 after a federal cabinet decision. Targets: double data centre IT connected capacity by 2030 versus 2025 and at least quadruple AI data centre capacity. Measures cover TSO/DSO connection allocation, flexible connection agreements, power prices (EU electricity price compensation for DCs), grid tariffs (AgNES) and waste heat.

    2 x DC IT capacity by 2030 vs 2025

    Bundesministerium für Digitales und Staatsmodernisierung (BMDS) · Publikationen der Bundesregierung (BMDS)

  • Plan or strategyIn force

    Offenbach am Main: städtebauliches Entwicklungskonzept für unternehmensunabhängige Rechenzentren

    Offenbach's city council adopted an urban development concept for siting independent data centers, based on a potential analysis. The Hessian government's answer lists it next to Frankfurt's concept as a municipal tool to steer data center siting. It is meant to guide future land-use planning in the city.

    Stadtverordnetenversammlung der Stadt Offenbach am Main · Hessischer Landtag, Drucksache 21/1061 (Antwort des Ministers für Wirtschaft, Energie, Verkehr, Wohnen und ländlichen Raum)

Announced and proposed

Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.

  • Efficiency ruleProposed

    Gesetz zur Beschleunigung der Umsetzung der Energieeffizienzrichtlinie (EnEfG-Novelle), Drucksache 21/8027

    Government bill, first reading in the Bundestag on 24 September 2026, referred to the Ausschuss für Wirtschaft und Energie (hearing 5 October 2026). It loosens minimum efficiency requirements for data centres, extends the deadline for new facilities from two to four years, moves the 100 percent renewable electricity requirement to 1 January 2030, and limits waste heat use to cases with a suitable nearby heat network.

    Bundesregierung / Deutscher Bundestag · Deutscher Bundestag

  • Grid accessProposed

    Vorrang von Erneuerbaren und Batteriespeichern beim Netzanschluss gegenüber Rechenzentren (Antrag Die Linke, Drucksache 21/8111, II.3)

    The motion asks for a bill that would give renewable energy plants and battery storage priority over data centers for grid connection. This would put data centers behind these users in the connection order. It is a proposal only.

    Deutscher Bundestag (Antrag der Fraktion Die Linke) · Deutscher Bundestag, Drucksache 21/8111

  • RestrictionProposed

    Verbot zusätzlicher Flächenversiegelung für neue Rechenzentren (Antrag Die Linke, Drucksache 21/8111, II.2 h)

    Among the conditions the motion proposes for building new data centers: no additional land may be sealed for their construction. This is part of an opposition motion and has not been adopted.

    Deutscher Bundestag (Antrag der Fraktion Die Linke) · Deutscher Bundestag, Drucksache 21/8111

  • RegulationProposed

    Gesetzliche Zulässigkeitsregulierung für neue Rechenzentren (Antrag Die Linke, Drucksache 21/8111, II.2)

    The motion asks the government for a bill that regulates whether new data centers above a grid connection threshold may be built. Approval would require a strict weighing of power and water use, lifecycle emissions, public benefit and actual demand. It also asks for stricter renewable, waste-heat and reporting duties.

    100 kW Threshold above which the proposed approval regime would apply; opposition motion.

    Deutscher Bundestag (Antrag der Fraktion Die Linke) · Deutscher Bundestag, Drucksache 21/8111

  • RestrictionProposed

    Obergrenze Netzanschlusskapazität für neue Rechenzentren (Antrag Die Linke, Drucksache 21/8111, II.2 d)

    The same Die Linke motion asks for a bill that would cap the grid connection capacity of new data centers. The stated reason is that data centers above a certain size can no longer be run sustainably. This is a proposal only.

    100 MW Proposed cap per new data center; part of opposition motion, not adopted.

    Deutscher Bundestag (Antrag der Fraktion Die Linke) · Deutscher Bundestag, Drucksache 21/8111

  • MoratoriumProposed

    Kein grenzenloser Ausbau von Rechenzentren – Echte Nachhaltigkeitsstandards gewährleisten (Antrag, Drucksache 21/8111)

    The Die Linke parliamentary group filed a motion in the Bundestag. It asks the federal government to bring in a moratorium on approving new data centers. The moratorium would last until a robust analysis of demand and capacity and a statutory basis for regulation exist. This is an opposition motion, not adopted law.

    Deutscher Bundestag (Antrag der Fraktion Die Linke) · Deutscher Bundestag, Drucksache 21/8111

  • Power tariffProposed

    Zuschuss zur anteiligen Finanzierung der Übertragungsnetzkosten 2027 bis 2029 (geplanter § 24d EnWG)

    Das Bundeskabinett hat Anfang September 2026 einen Zuschuss zu den Übertragungsnetzkosten beschlossen. Er soll aus dem Klima- und Transformationsfonds kommen und in einem neuen § 24d EnWG verankert werden. Laut dem Gesetzentwurf soll der Zuschuss bis einschließlich 2029 weiterlaufen. Für 2027 fällt er knapp eine Milliarde Euro niedriger aus als für 2026. Die vier ÜNB haben ihre vorläufigen Entgelte für 2027 mit diesem Zuschuss berechnet. Gibt es bis zum 7. Dezember 2026 keine Rechtssicherheit, erwarten sie höhere endgültige Entgelte für 2027.

    5.53 billion EUR per year Der Wert gilt pro Jahr für den Zeitraum bis einschließlich 2029 laut Gesetzentwurf vom 02.09.2026. Zum Zeitpunkt der Quelle (01.10.2026) war das Gesetz noch nicht verabschiedet.

    Bundesregierung (Bundeskabinett); Gesetzgebungsverfahren im Deutschen Bundestag

  • Grid accessProposed

    Netzanschlusspaket (Entwurf zur Änderung von EnWG, EEG, WindSeeG, KWKG, KraftNAV und StromNEV)

    Federal cabinet adopted the draft on 29 July 2026. It lets TSOs prioritise connection requests in a uniform procedure instead of first-come first-served, requires TSOs to submit uniform procedures to BNetzA by 1 January 2027, and adds digital connection processes from 1 January 2028. The source names data centres and battery storage as drivers of connection bottlenecks. Parliamentary deliberation pending.

    Bundesregierung (BMWE)

  • IncentiveAnnounced

    Industriestrompreis – Richtlinie für strom- und handelsintensive Unternehmen (Abrechnungsjahre 2026 bis 2028)

    Die Europäische Kommission hat am 16.04.2026 die nationale Richtlinie zum Industriestrompreis beihilferechtlich genehmigt. Laut BMWE führt die Bundesregierung das Instrument für die Jahre 2026 bis 2028 ein. Es soll strom- und handelsintensive Unternehmen aus 91 Sektoren entlasten; der Zielpreis wird auf Grundlage des Großhandelsstrompreises bestimmt. Weitere (Teil-)Sektoren können nach Genehmigung durch die Kommission später einbezogen werden. Die Anträge laufen über das BAFA, mit Beginn Anfang 2027 rückwirkend für das Gesamtjahr 2026.

    5 EUR ct/kWh Laut Pressemitteilung sollte die Richtlinie in Kürze im Bundesanzeiger veröffentlicht werden und damit in Kraft treten; das Datum der Veröffentlichung wurde nicht in einer Primärquelle geprüft. Die Laufzeit 2026 bis 2028 steht im Quelltext. Ein genaues En

    Bundesministerium für Wirtschaft und Energie (BMWE); beihilferechtliche Genehmigung durch die Europäische Kommission; Durchführung durch das BAFA · Bundesministerium für Wirtschaft und Energie (BMWE), Pressemitteilung vom 16.04.2026

Timeline of data center and power policy in Germany

DateActionTypeStatusAuthority
24 Sep 2026Gesetz zur Beschleunigung der Umsetzung der Energieeffizienzrichtlinie (EnEfG-Novelle), Drucksache 21/8027Efficiency ruleProposedBundesregierung / Deutscher Bundestag
22 Sep 2026Vorrang von Erneuerbaren und Batteriespeichern beim Netzanschluss gegenüber Rechenzentren (Antrag Die Linke, Drucksache 21/8111, II.3)Grid accessProposedDeutscher Bundestag (Antrag der Fraktion Die Linke)
22 Sep 2026Verbot zusätzlicher Flächenversiegelung für neue Rechenzentren (Antrag Die Linke, Drucksache 21/8111, II.2 h)RestrictionProposedDeutscher Bundestag (Antrag der Fraktion Die Linke)
22 Sep 2026Gesetzliche Zulässigkeitsregulierung für neue Rechenzentren (Antrag Die Linke, Drucksache 21/8111, II.2)RegulationProposedDeutscher Bundestag (Antrag der Fraktion Die Linke)
22 Sep 2026Obergrenze Netzanschlusskapazität für neue Rechenzentren (Antrag Die Linke, Drucksache 21/8111, II.2 d)RestrictionProposedDeutscher Bundestag (Antrag der Fraktion Die Linke)
22 Sep 2026Kein grenzenloser Ausbau von Rechenzentren – Echte Nachhaltigkeitsstandards gewährleisten (Antrag, Drucksache 21/8111)MoratoriumProposedDeutscher Bundestag (Antrag der Fraktion Die Linke)
2 Sep 2026Zuschuss zur anteiligen Finanzierung der Übertragungsnetzkosten 2027 bis 2029 (geplanter § 24d EnWG)Power tariffProposedBundesregierung (Bundeskabinett); Gesetzgebungsverfahren im Deutschen Bundestag
20 Aug 2026Batteriespeicher-Anschlussbegehren bei den ÜNB im ersten Quartal 2026Grid accessIn forceBundesnetzagentur (SMARD)
20 Aug 2026Bundesnetzagentur-Monitoring: Netzanschlussbegehren für Batteriespeicher 2025Grid accessIn forceBundesnetzagentur (SMARD)
20 Aug 2026Batteriespeicher-Anschlussbegehren bei den Verteilnetzbetreibern 2025Grid accessIn forceBundesnetzagentur (SMARD)
20 Aug 2026Batteriespeicher-Anschlussbegehren bei den ÜNB 2025Grid accessIn forceBundesnetzagentur (SMARD)
29 Jul 2026Netzanschlusspaket (Entwurf zur Änderung von EnWG, EEG, WindSeeG, KWKG, KraftNAV und StromNEV)Grid accessProposedBundesregierung (BMWE)
16 Apr 2026Industriestrompreis – Richtlinie für strom- und handelsintensive Unternehmen (Abrechnungsjahre 2026 bis 2028)IncentiveAnnouncedBundesministerium für Wirtschaft und Energie (BMWE); beihilferechtliche Genehmigung durch die Europäische Kommission; Durchführung durch das BAFA
18 Mar 2026Rechenzentrumsstrategie der BundesregierungPlan or strategyIn forceBundesministerium für Digitales und Staatsmodernisierung (BMDS)
5 Feb 2026Positionspapier der Übertragungsnetzbetreiber (ÜNB) zu Netzanschlüssen – ReifegradverfahrenGrid accessIn force50Hertz, Amprion, TenneT, TransnetBW (ÜNB)
27 Nov 2025Verbindliche Reservierungen für Datacenter-Anschlüsse bei MITNETZ STROMGrid accessIn forceMITNETZ STROM (Mitteldeutsche Netzgesellschaft Strom mbH)
27 Nov 2025Warteschlange für Datacenter-Netzanschlüsse im Verteilnetz von MITNETZ STROMGrid accessIn forceMITNETZ STROM (Mitteldeutsche Netzgesellschaft Strom mbH)
23 Jul 2025Verteilte Anschlusskapazität im Berliner Repartierungsverfahren 2025Grid accessIn forceStromnetz Berlin GmbH
23 Jul 2025Angefragte Leistung im Berliner Repartierungsverfahren 2025Grid accessIn forceStromnetz Berlin GmbH
30 Nov 2024Möglichkeit des Ausschlusses von Rechenzentren in Bebauungsplänen (Antwort der Hessischen Landesregierung)RegulationIn forceHessisches Ministerium für Wirtschaft, Energie, Verkehr, Wohnen und ländlichen Raum
20 Nov 2024Positionspapier zur Bemessung und Erhebung von Baukostenzuschüssen für NetzanschlüsseGrid accessIn forceBundesnetzagentur (Beschlusskammer 8)
11 Oct 2024Neues Zuteilungsverfahren für sehr große Netzanschlüsse in BerlinGrid accessIn forceStromnetz Berlin GmbH / Senatsverwaltung für Wirtschaft, Energie und Betriebe Berlin
14 Mar 2024Rechenzentrumsregister (Energieeffizienzregister für Rechenzentren) – Meldepflicht nach § 13 EnEfG und Delegierter Verordnung (EU) 2024/1364RegulationIn forceBMWK / BAFA (Bundesstelle für Energieeffizienz); European Commission
1 Feb 2024Offenbach am Main: städtebauliches Entwicklungskonzept für unternehmensunabhängige RechenzentrenPlan or strategyIn forceStadtverordnetenversammlung der Stadt Offenbach am Main
13 Nov 2023Energieeffizienzgesetz (EnEfG) § 11 Abs. 5 – Stromversorgung von Rechenzentren aus erneuerbaren EnergienRenewable energyIn forceBundestag / Bundesregierung (BMWK)
13 Nov 2023Energieeffizienzgesetz (EnEfG) § 11 Abs. 2 – Anteil wiederverwendeter Energie (Abwärmenutzung) in RechenzentrenEfficiency ruleIn forceBundestag / Bundesregierung (BMWK)
13 Nov 2023Energieeffizienzgesetz (EnEfG) § 11 – Energieverbrauchseffektivität (PUE) von RechenzentrenEfficiency ruleIn forceBundestag / Bundesregierung (BMWK)
9 Jun 2022Rechenzentrenkonzept – Aktualisierung des Gewerbeflächenentwicklungsprogramms (Stadtverordnetenbeschluss § 1838) Frankfurt am MainRestrictionIn forceStadtverordnetenversammlung Frankfurt am Main

How Germany compares

Latest official figures for the countries we track.

CountryIndustrial power priceRenewable shareGrid emission factorRestrictions in forceIncentives in force
Argentina—19.6% (2025)0.28 kgCO2/kWh (2022)02
Australia—39% (2025)—02
Austria169 USD/MWh (2026)78% (2025)0.15 kgCO2/kWh (2023)00
Bangladesh—2% (2025)—00
Belgium183 USD/MWh (2025)34.3% (2025)0.19 kgCO2/kWh (2024)00
Brazil—86.8% (2025)0.07 kgCO2/kWh (2025)01
Canada—63.9% (2024)0.10 kgCO2/kWh (2022)60
Chile—66% (2025)0.24 kgCO2/kWh (2023)00
China—38% (2025)0.53 kgCO2/kWh (2023)20
Colombia——0.22 kgCO2/kWh (2024)02
Denmark134 USD/MWh (2025)81.5% (2024)0.11 kgCO2/kWh (2024)10
Ecuador——0.16 kgCO2/kWh (2024)10
Finland58.4 USD/MWh (2025)57% (2024)0.03 kgCO2/kWh (2025)00
France104 USD/MWh (2025)27% (2025)0.02 kgCO2/kWh (2025)01
Germany180 USD/MWh (2025)58.8% (2025)0.34 kgCO2/kWh (2025)10
Guatemala84.5 USD/MWh (2025)53.5% (2024)0.29 kgCO2/kWh (2024)02
Hong Kong180 USD/MWh (2026)—0.59 kgCO2/kWh (2025)02
Iceland42.9 USD/MWh (2022)100% (2026)—12
India82.1 USD/MWh (2025)28.7% (2026)0.68 kgCO2/kWh (2025)15
Indonesia62.9 USD/MWh (2024)16.3% (2025)0.68 kgCO2/kWh (2024)01
Ireland234 USD/MWh (2025)41.3% (2024)0.20 kgCO2/kWh (2025)20
Italy184 USD/MWh (2025)48% (2025)0.20 kgCO2/kWh (2025)00
Japan—23.1% (2024)0.45 kgCO2/kWh (2024)00
Kazakhstan—14.6% (2025)0.81 kgCO2/kWh (2025)00
Kyrgyzstan41.7 USD/MWh (2026)88% (2024)0.16 kgCO2/kWh (2019)11
Luxembourg165 USD/MWh (2025)23.3% (2025)—00
Malaysia105 USD/MWh (2026)21% (2025)0.74 kgCO2/kWh (2024)11
Mexico——0.44 kgCO2/kWh (2023)00
Nepal———00
Netherlands148 USD/MWh (2025)49% (2025)0.20 kgCO2/kWh (2024)40
Pakistan97.5 USD/MWh (2026)34.7% (2025)—01
Panama66.3 USD/MWh (2025)74.7% (2025)0.15 kgCO2/kWh (2024)01
Paraguay33.0 USD/MWh (2026)——12
Peru—62.6% (2025)—01
Philippines—22.2% (2024)0.71 kgCO2/kWh (2017)12
Russia—17.6% (2025)—20
Singapore189 USD/MWh (2025)2.1% (2024)0.40 kgCO2/kWh (2024)10
South Korea—9.8% (2025)—00
Spain113 USD/MWh (2025)55.5% (2025)—10
Sri Lanka—60.2% (2025)—00
Sweden78.5 USD/MWh (2025)—0.06 kgCO2/kWh (2023)00
Switzerland240 USD/MWh (2026)70.8% (2025)0.13 kgCO2/kWh (2022)00
Taiwan—12.7% (2025)0.47 kgCO2/kWh (2024)10
Thailand120 USD/MWh (2026)—0.48 kgCO2/kWh (2026)02
United Arab Emirates120 USD/MWh (2026)8.8% (2024)0.47 kgCO2/kWh (2024)00
United Kingdom234 USD/MWh (2026)52.1% (2025)0.15 kgCO2/kWh (2026)11
United States86.2 USD/MWh (2025)24% (2025)0.35 kgCO2/kWh (2023)01
Uruguay101 USD/MWh (2026)98% (2025)0.01 kgCO2/kWh (2025)03
Uzbekistan83.3 USD/MWh (2026)19.4% (2025)—10
Venezuela—77% (2023)—01

Questions

Is there a data center moratorium in Germany?

Yes. 1 restriction on new data centers is in force in Germany: Rechenzentrenkonzept – Aktualisierung des Gewerbeflächenentwicklungsprogramms (Stadtverordnetenbeschluss § 1838) (Frankfurt am Main).

What does electricity cost for data centers in Germany?

The industrial electricity price in Germany was 180 USD/MWh in 2025 (Eurostat nrg_pc_205, non-household, band IE (20,000-69,999 MWh), excl. VAT and recoverable taxes: 2025-S1 0.1584 and 2025-S2 0.1595 EUR/kWh, mean 158.95 EUR/MWh; converted at 2025 ECB annual average 1.1300 USD/EUR (Eurostat ert_bil_eur_a). 2026-S1: 0.1464). Data center contracts can differ by voltage level, contract length and location.

How much of Germany’s electricity is renewable?

Renewables supplied 58.8% of electricity generation in Germany in 2025.

Where does this data come from?

Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.

What counts as a restriction or moratorium?

A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.

How are power prices compared?

We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.

How often is it updated?

Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.

Global capacity

How much data center capacity does Germany have?

Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.

See Germany capacity

Choosing a market or a site?

Our analysts prepare country briefings on power, grid access, incentives and permits, with every source, in Excel.

Talk to an analyst