Data Center Power & Policy in India

Every government action on data centers and power in India that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.

In short

As of 15 November 2026, DC Market Insights tracks 17 government actions on data centers and power in India, 11 of them in force. India has 1 restriction on new data centers in force: Guidelines regulating groundwater extraction for infrastructure/commercial projects (S.O. 3289(E)). 5 incentive schemes apply, including Uttar Pradesh Data Centre Policy 2026.

17Actions tracked
11In force
82.1 USD/MWhIndustrial power price
28.7%Renewable share of generation

Market snapshot

India power and policy: key facts

  • Industrial electricity price: 82.1 USD/MWh (2025). Rank 23 of 30 tracked countries, highest first.
  • Renewable share of electricity generation: 28.7% (2026). Rank 26 of 42 tracked countries, highest first.
  • Grid emission factor: 0.68 kgCO2/kWh (2025). Rank 5 of 36 tracked countries, highest first.
  • Latest change: Uttar Pradesh Data Centre Policy 2026 (Department of IT & Electronics, Government of Uttar Pradesh, 13 Aug 2026).
  • By type: 8 incentive, 6 regulation, 1 power tariff and 1 plan or strategy.

Power indicators for India

Latest official figure for each indicator, with earlier years where we have them.

Industrial electricity price 82.1 USD/MWh 2025 · TGSPDCL (Telangana, TGERC-approved) FY 2025-26 tariff (applicable 01.05.2025-31.03.2026), HT-I(A) Industry General 33 kV energy charge Rs 7.15/unit (HT billed per kVAh; treated as kWh at unity power factor; excludes demand charge Rs 500/kVA/month and duti Southern Power Distribution Company of Telangana Ltd (TGSPDCL)
Renewable share of electricity generation 28.7% 2026 · CEA Broad Overview of RE Generation Aug 2026, Table 7: RE incl. large hydro as % of total generation, FY 2026-27 to date (Apr-Aug 2026, monsoon-weighted partial year) 2024: 22.9% Central Electricity Authority
Grid emission factor 0.68 kgCO2/kWh 2025 · CEA CO2 Baseline Database v22.0, Table B weighted average emission rate incl. RES and imports, FY 2025-26 (tCO2/MWh = kgCO2/kWh) 2024: 0.71 kgCO2/kWh Central Electricity Authority
Peak electricity demand 256 GW 2026 · All-time high peak demand met on 25 April 2026, 'over 256 GW' (Prasar Bharati / All India Radio report of Ministry of Power data) News On AIR (Prasar Bharati)
Installed generation capacity 555 GW 2026 · CEA All India installed capacity as on 31.08.2026: 554,544.23 MW Central Electricity Authority

In force now in India

Restriction (1)

Power tariff (1)

  • Power tariffIn force

    Notification on exemption from payment of electricity duty to IT/ITeS and Data Centre units (CEI-2025/CR-158/Energy-1)

    Notification of 22 June 2026 under the Maharashtra Electricity Duty Act, 2016, supporting the IT/ITeS Policy 2023 and the Policy for Integrated Green Data Centre Parks; new and existing data centre units qualify for a 20-year electricity duty exemption.

    20 years electricity duty exemption

    Government of Maharashtra (Energy Department) · Maharashtra

Incentive (5)

  • IncentiveIn force

    Uttar Pradesh Data Centre Policy 2026

    Promulgation notified 13/08/2026, notification published 22/08/2026. UPLC lists policy targets of INR 2 lakh crore+ investment and 2 GW+ capacity, a special package for projects over 500 MW, 7% capital subsidy up to INR 20 crore, 100% electricity duty exemption for 10 years and dual grid supply for the first 8 DC parks.

    2 GW capacity target

    Department of IT & Electronics, Government of Uttar Pradesh · Uttar Pradesh · UPLC, Government of Uttar Pradesh

  • IncentiveIn force

    Haryana State Data Center Policy, 2022: declaration of Data Centers as a separate Infrastructure Industry

    Notification No. 02/13/2023-4IB-II dated 22 November 2023 declares data centers covered under the Haryana State Data Center Policy, 2022 (notified 7 July 2022) a separate Infrastructure Industry, effective from the date of notification.

    Industries & Commerce Department, Government of Haryana · Haryana · Effective 22 Nov 2023 · Industries & Commerce Department, Government of Haryana

  • IncentiveIn force

    Maharashtra Information Technology and IT Enabled Services Policy 2023

    Resolution dated 27 June 2023. Grants permanent electricity duty exemption to new and existing registered data center units and a power tariff subsidy of INR 1 per unit for five years for new data center units outside Zone-I. Valid five years from 27 June 2023 or until a new policy is released.

    1 INR/kWh power tariff subsidy 5 years, new DC units outside Zone-I

    Government of Maharashtra · Maharashtra · Ends 27 Jun 2028

  • IncentiveIn force

    Inclusion of Data Centres in the Harmonized Master List of Infrastructure Sub-sectors (F. No. 13/1/2017-INF)

    Department of Economic Affairs notification dated 11 October 2022 adds Data Centres under the Communication category of the Harmonized Master List of Infrastructure sub-sectors, defined as a data centre in a dedicated/centralized building with a minimum capacity of 5 MW of IT load.

    5 MW minimum IT load

    Department of Economic Affairs, Ministry of Finance

  • IncentiveIn force

    Odisha Data Centre Policy-2022

    Offers a capital investment subsidy of 20% of fixed capital investment excluding land (cap Rs 25 crore per unit), 100% electricity duty exemption up to 5 MVA contract demand for 10 years, 30% power bill subsidy for 5 years (cap Rs 2 crore), 100% reimbursement of transmission and wheeling charges for captive renewable power, and industrial power tariff. (source gives year only)

    20 % capital subsidy cap Rs 25 crore per data centre unit

    Electronics & Information Technology Department, Government of Odisha · Odisha · Government of Odisha

Regulation (4)

  • RegulationIn force

    Environmental Clearance for AI Data Centres under the EIA Notification, 2006 (Rajya Sabha written reply)

    In a written reply in the Rajya Sabha, MoEFCC said AI data centres do not, per se, require Environmental Clearance under the EIA Notification, 2006. Prior EC is needed only when a data centre is part of a Building and Construction Project (Item 8(a)) or a Township and Area Development Project (Item 8(b)) above the stated thresholds. For building projects the EC is granted by the State Environment Impact Assessment Authority (SEIAA). Freshwater availability in water-stressed regions and greywater reuse are considered at appraisal.

    20,000 sq. m Value is the Item 8(a) built-up area threshold. The Item 8(b) township thresholds stand in value_text as the source writes them. There is no category for data centres themselves.

    Ministry of Environment, Forest and Climate Change · Press Information Bureau (Ministry of Environment, Forest and Climate Change), Parliament Question: Effective use of water in AI Data centres

  • RegulationIn force

    CERC (Connectivity and General Network Access to the inter-State Transmission System) (Third Amendment) Regulations, 2025

    This third amendment to India's ISTS connectivity and GNA framework was notified by CERC on 31 August 2025 and took effect on 9 September 2025. It changed how in-principle and final grants of connectivity are issued, including the coordinates and land-document timelines tied to ISTS substations. It also added transition rules requiring pending in-principle cases to be moved to final grants.

    Central Electricity Regulatory Commission · Effective 9 Sep 2025 · CERC Order dated 10.04.2026 in Petition No. 666/MP/2025

  • RegulationIn force

    Declaration of Data Center Industries as an essential service (Uttar Pradesh)

    Uttar Pradesh Government Order dated 11 October 2022 declaring data center industries an essential service, issued under the UP Data Center Policy framework.

    Department of IT & Electronics, Government of Uttar Pradesh · Uttar Pradesh · UPLC, Government of Uttar Pradesh

  • RegulationIn force

    One-time GNA charge under CERC GNA Regulations, 2022

    Under Regulation 22.2(d) of the CERC GNA Regulations, entities connecting directly to ISTS under Regulation 4.1 or 17.1(iii) pay a one-time GNA charge per MW of GNA quantum. Clause 17.1(iii) is the route for directly connected drawee entities such as bulk consumers. If unpaid, the charge is recovered from the Conn-BGs, and the proceeds reduce monthly transmission charges. The draft fourth amendment would move the due date to within 15 days after GNA becomes effective and would bar entities without subsisting BGs from grid transactions until they pay.

    Central Electricity Regulatory Commission · CERC, Explanatory Memorandum to Draft CERC (Connectivity and GNA to ISTS) (Fourth Amendment) Regulations, 2026

Announced and proposed

Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.

  • RegulationProposed

    Draft CERC GNA Fourth Amendment – new Regulation 23A (Transfer of GNA)

    The draft proposes that drawal GNA granted for an identified load at a single drawal point moves to the new owner when that load is sold. The transfer is allowed only after the GNA has become effective and the original grantee has cleared its dues. The current regulations have no explicit transfer provision for drawal GNA.

    Central Electricity Regulatory Commission · CERC Draft Notification, CERC (Connectivity and GNA to ISTS) (Fourth Amendment) Regulations, 2026

  • RegulationProposed

    Draft CERC GNA Fourth Amendment – new Regulation 17.5 (drawee entities connecting to both ISTS and State networks)

    CERC's draft fourth amendment proposes Regulation 17.5. A drawee entity already connected to a State transmission or distribution network could connect directly to ISTS for the same drawal capacity, with STU consent and continued payment of applicable charges. The reverse would also be allowed, subject to Nodal Agency consent on technical feasibility. Entities holding GNA-RE would be excluded unless they convert to GNA.

    Central Electricity Regulatory Commission · CERC Draft Notification, CERC (Connectivity and GNA to ISTS) (Fourth Amendment) Regulations, 2026, No. L-1/261/2021/CERC

  • Plan or strategyProposed

    Draft Data Centre Policy 2020 (Ministry of Electronics and Information Technology)

    MeitY draft policy proposing infrastructure status for the data centre sector, declaration of data centres as an essential service under ESMA 1968, simplified clearances, and at least four Data Centre Economic Zones through a DCEZ scheme. No final national policy has been notified.

    4 data centre economic zones (proposed)

    Ministry of Electronics and Information Technology (MeitY)

Timeline of data center and power policy in India

DateActionTypeStatusAuthority
13 Aug 2026Uttar Pradesh Data Centre Policy 2026 Uttar PradeshIncentiveIn forceDepartment of IT & Electronics, Government of Uttar Pradesh
6 Aug 2026Environmental Clearance for AI Data Centres under the EIA Notification, 2006 (Rajya Sabha written reply)RegulationIn forceMinistry of Environment, Forest and Climate Change
22 Jun 2026Notification on exemption from payment of electricity duty to IT/ITeS and Data Centre units (CEI-2025/CR-158/Energy-1) MaharashtraPower tariffIn forceGovernment of Maharashtra (Energy Department)
20 May 2026Draft CERC GNA Fourth Amendment – new Regulation 23A (Transfer of GNA)RegulationProposedCentral Electricity Regulatory Commission
20 May 2026Draft CERC GNA Fourth Amendment – new Regulation 17.5 (drawee entities connecting to both ISTS and State networks)RegulationProposedCentral Electricity Regulatory Commission
31 Aug 2025CERC (Connectivity and General Network Access to the inter-State Transmission System) (Third Amendment) Regulations, 2025RegulationIn forceCentral Electricity Regulatory Commission
22 Nov 2023Haryana State Data Center Policy, 2022: declaration of Data Centers as a separate Infrastructure Industry HaryanaIncentiveIn forceIndustries & Commerce Department, Government of Haryana
27 Jun 2023Maharashtra Information Technology and IT Enabled Services Policy 2023 MaharashtraIncentiveIn forceGovernment of Maharashtra
11 Oct 2022Declaration of Data Center Industries as an essential service (Uttar Pradesh) Uttar PradeshRegulationIn forceDepartment of IT & Electronics, Government of Uttar Pradesh
11 Oct 2022Inclusion of Data Centres in the Harmonized Master List of Infrastructure Sub-sectors (F. No. 13/1/2017-INF)IncentiveIn forceDepartment of Economic Affairs, Ministry of Finance
7 Jun 2022One-time GNA charge under CERC GNA Regulations, 2022RegulationIn forceCentral Electricity Regulatory Commission
1 Jan 2022Odisha Data Centre Policy-2022 OdishaIncentiveIn forceElectronics & Information Technology Department, Government of Odisha
23 Nov 2021Tamil Nadu Data Centre Policy 2021 (G.O.(Ms.) No. 33 dated 23.11.2021) Tamil NaduIncentiveExpiredInformation Technology and Digital Services Department, Government of Tamil Nadu
6 Sep 2021West Bengal Data Centre Policy, 2021 West BengalIncentiveExpiredDepartment of Information Technology & Electronics, Government of West Bengal
9 Apr 2021Uttar Pradesh Data Center Policy 2021 Uttar PradeshIncentiveExpiredDepartment of IT & Electronics, Government of Uttar Pradesh
9 Nov 2020Draft Data Centre Policy 2020 (Ministry of Electronics and Information Technology)Plan or strategyProposedMinistry of Electronics and Information Technology (MeitY)
24 Sep 2020Guidelines regulating groundwater extraction for infrastructure/commercial projects (S.O. 3289(E))RestrictionIn forceMinistry of Jal Shakti

How India compares

Latest official figures for the countries we track.

CountryIndustrial power priceRenewable shareGrid emission factorRestrictions in forceIncentives in force
Argentina—19.6% (2025)0.28 kgCO2/kWh (2022)02
Australia—39% (2025)—02
Austria169 USD/MWh (2026)78% (2025)0.15 kgCO2/kWh (2023)00
Bangladesh—2% (2025)—00
Belgium183 USD/MWh (2025)34.3% (2025)0.19 kgCO2/kWh (2024)00
Brazil—86.8% (2025)0.07 kgCO2/kWh (2025)01
Canada—63.9% (2024)0.10 kgCO2/kWh (2022)60
Chile—66% (2025)0.24 kgCO2/kWh (2023)00
China—38% (2025)0.53 kgCO2/kWh (2023)20
Colombia——0.22 kgCO2/kWh (2024)02
Denmark134 USD/MWh (2025)81.5% (2024)0.11 kgCO2/kWh (2024)10
Ecuador——0.16 kgCO2/kWh (2024)10
Finland58.4 USD/MWh (2025)57% (2024)0.03 kgCO2/kWh (2025)00
France104 USD/MWh (2025)27% (2025)0.02 kgCO2/kWh (2025)01
Germany180 USD/MWh (2025)58.8% (2025)0.34 kgCO2/kWh (2025)10
Guatemala84.5 USD/MWh (2025)53.5% (2024)0.29 kgCO2/kWh (2024)02
Hong Kong180 USD/MWh (2026)—0.59 kgCO2/kWh (2025)02
Iceland42.9 USD/MWh (2022)100% (2026)—12
India82.1 USD/MWh (2025)28.7% (2026)0.68 kgCO2/kWh (2025)15
Indonesia62.9 USD/MWh (2024)16.3% (2025)0.68 kgCO2/kWh (2024)01
Ireland234 USD/MWh (2025)41.3% (2024)0.20 kgCO2/kWh (2025)20
Italy184 USD/MWh (2025)48% (2025)0.20 kgCO2/kWh (2025)00
Japan—23.1% (2024)0.45 kgCO2/kWh (2024)00
Kazakhstan—14.6% (2025)0.81 kgCO2/kWh (2025)00
Kyrgyzstan41.7 USD/MWh (2026)88% (2024)0.16 kgCO2/kWh (2019)11
Luxembourg165 USD/MWh (2025)23.3% (2025)—00
Malaysia105 USD/MWh (2026)21% (2025)0.74 kgCO2/kWh (2024)11
Mexico——0.44 kgCO2/kWh (2023)00
Nepal———00
Netherlands148 USD/MWh (2025)49% (2025)0.20 kgCO2/kWh (2024)40
Pakistan97.5 USD/MWh (2026)34.7% (2025)—01
Panama66.3 USD/MWh (2025)74.7% (2025)0.15 kgCO2/kWh (2024)01
Paraguay33.0 USD/MWh (2026)——12
Peru—62.6% (2025)—01
Philippines—22.2% (2024)0.71 kgCO2/kWh (2017)12
Russia—17.6% (2025)—20
Singapore189 USD/MWh (2025)2.1% (2024)0.40 kgCO2/kWh (2024)10
South Korea—9.8% (2025)—00
Spain113 USD/MWh (2025)55.5% (2025)—10
Sri Lanka—60.2% (2025)—00
Sweden78.5 USD/MWh (2025)—0.06 kgCO2/kWh (2023)00
Switzerland240 USD/MWh (2026)70.8% (2025)0.13 kgCO2/kWh (2022)00
Taiwan—12.7% (2025)0.47 kgCO2/kWh (2024)10
Thailand120 USD/MWh (2026)—0.48 kgCO2/kWh (2026)02
United Arab Emirates120 USD/MWh (2026)8.8% (2024)0.47 kgCO2/kWh (2024)00
United Kingdom234 USD/MWh (2026)52.1% (2025)0.15 kgCO2/kWh (2026)11
United States86.2 USD/MWh (2025)24% (2025)0.35 kgCO2/kWh (2023)01
Uruguay101 USD/MWh (2026)98% (2025)0.01 kgCO2/kWh (2025)03
Uzbekistan83.3 USD/MWh (2026)19.4% (2025)—10
Venezuela—77% (2023)—01

Questions

Is there a data center moratorium in India?

Yes. 1 restriction on new data centers is in force in India: Guidelines regulating groundwater extraction for infrastructure/commercial projects (S.O. 3289(E)).

What incentives does India offer data centers?

In force: Uttar Pradesh Data Centre Policy 2026, Haryana State Data Center Policy, 2022: declaration of Data Centers as a separate Infrastructure Industry, Maharashtra Information Technology and IT Enabled Services Policy 2023 and Inclusion of Data Centres in the Harmonized Master List of Infrastructure Sub-sectors (F. No. 13/1/2017-INF). Each is listed with its authority and dates on this page.

What does electricity cost for data centers in India?

The industrial electricity price in India was 82.1 USD/MWh in 2025 (TGSPDCL (Telangana, TGERC-approved) FY 2025-26 tariff (applicable 01.05.2025-31.03.2026), HT-I(A) Industry General 33 kV energy charge Rs 7.15/unit (HT billed per kVAh; treated as kWh at unity power factor; excludes demand charge Rs 500/kVA/month and duti). Data center contracts can differ by voltage level, contract length and location.

How much of India’s electricity is renewable?

Renewables supplied 28.7% of electricity generation in India in 2026.

Where does this data come from?

Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.

What counts as a restriction or moratorium?

A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.

How are power prices compared?

We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.

How often is it updated?

Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.

Global capacity

How much data center capacity does India have?

Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.

See India capacity