Data Center Power & Policy in Netherlands

Every government action on data centers and power in Netherlands that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.

In short

As of 16 November 2026, DC Market Insights tracks 17 government actions on data centers and power in Netherlands, 12 of them in force. Netherlands has 4 restrictions on new data centers in force, the latest: Geactualiseerde Datacenterstrategie Noord-Holland 2025-2027.

17Actions tracked
12In force
148 USD/MWhIndustrial power price
49%Renewable share of generation

Market snapshot

Netherlands power and policy: key facts

  • Industrial electricity price: 148 USD/MWh (2025). Rank 11 of 30 tracked countries, highest first.
  • Renewable share of electricity generation: 49% (2025). Rank 19 of 42 tracked countries, highest first.
  • Grid emission factor: 0.20 kgCO2/kWh (2024). Rank 20 of 36 tracked countries, highest first.
  • Data centers’ share of electricity demand: 4.6% (2024). Rank 2 of 5 tracked countries, highest first.
  • Latest change: Codebesluit operationalisering TDTR (Autoriteit Consument & Markt (ACM), 7 May 2026).
  • By type: 4 moratorium, 4 restriction, 3 regulation and 3 grid access.

Power indicators for Netherlands

Latest official figure for each indicator, with earlier years where we have them.

Industrial electricity price 148 USD/MWh 2025 · Eurostat nrg_pc_205, band IE (20,000-69,999 MWh), excluding VAT and other recoverable taxes: 2025-S1 0.1432 and 2025-S2 0.1182 EUR/kWh, mean 130.7 EUR/MWh; converted at 2025 annual average 1.1300 USD/EUR (Eurostat ert_bil_eur_a) = 147.69 USD/MWh 2024: 156 USD/MWh Eurostat
Renewable share of electricity generation 49% 2025 · CBS: renewable sources share of total electricity production 2025 (132 billion kWh produced); published 9 March 2026 CBS
Grid emission factor 0.20 kgCO2/kWh 2024 · CBS Energie- en emissiefactoren elektriciteit, update 2024: CO2 per kWh produced electricity, integrale methode (average of total production) 2023: 0.22 kgCO2/kWh CBS
Data centers’ share of electricity demand 4.6% 2024 · CBS: data centres used 5,100 GWh in 2024 (provisional), 4.6% of total Dutch electricity use (table value 4.58%); published 15 December 2025 2023: 4.2% CBS

In force now in Netherlands

Moratorium (1)

  • MoratoriumIn force

    Geactualiseerde Datacenterstrategie Noord-Holland 2025-2027

    Provincial strategy for 2025-2027: no new hyperscale data centre initiatives allowed in Noord-Holland during its term. Data centres above 2,000 m2 and/or 5 MVA may locate only in designated clusters in Amsterdam, Haarlemmermeer and Hollands Kroon under the Omgevingsverordening NH2022; the province is competent authority above 50 MW. Waste-heat use is a siting condition. (source gives year only)

    5 MVA threshold for strategy scope Applies to data centres above 2,000 m2 and/or 5 MVA

    Gedeputeerde Staten van Noord-Holland · Noord-Holland · Effective 1 Jan 2025 · Provincie Noord-Holland

Restriction (3)

  • RestrictionIn force

    Besluit van 20 december 2023 houdende wijziging van Besluit kwaliteit leefomgeving in verband met een instructieregel voor hyperscale datacentra

    Amends the Besluit kwaliteit leefomgeving: municipalities may not allow new hyperscale data centres (built area above 10 ha and connection capacity of 70 MW or more) in their omgevingsplan, except in the Eemshaven area (Het Hogeland) and Agriport A7 (Hollands Kroon). Existing and permitted sites are not affected. Municipalities have until 1 January 2032 to comply. In force 1 January 2024 (Staatsblad 2023, 492).

    70 MW connection threshold Hyperscale = above 10 ha and 70 MW or more

    Kroon / Minister voor Volkshuisvesting en Ruimtelijke Ordening · Effective 1 Jan 2024 · Staatsblad (officielebekendmakingen.nl)

  • RestrictionIn force

    Vestigingsbeleid datacenters gemeente Amsterdam 2020-2030 (Amsterdam Duurzaam Digitaal)

    Siting policy adopted by the Amsterdam city council in December 2020. Caps data centre growth at 670 MVA until 2030 with connection capacity growth of at most 67 MW per year, limits new data centres to the clusters Haven, Schinkelkwartier, Amstel III and Sciencepark, and requires use of residual heat. (source gives month only)

    670 MVA cap to 2030 Growth cap to 2030 in original 2020 policy; 67 MW/year

    Gemeenteraad Amsterdam · Amsterdam · Ends 31 Dec 2030 · Gemeente Amsterdam (via Omgevingsdienst Noordzeekanaalgebied)

  • RestrictionIn force

    Datacenterbeleid gemeente Haarlemmermeer

    Caps total data centre connection capacity at 750 MVA to 2030, with growth of at most 70 MVA per year. Data centres are allowed only on Polanenpark (100 MVA, 7.9 ha), Corneliahoeve (100 MVA), Schiphol-Rijk (350 MVA) and Schiphol Trade Park (200 MVA, 10 ha). Operators above 80 MVA must build their own 150 kV substation. No new data centres outside these areas; no extra space after 2030. Valid from 24 November 2020.

    750 MVA cap to 2030 Municipal cap on data centre connection capacity to 2030; 70 MVA per year growth limit

    Gemeenteraad Haarlemmermeer · Haarlemmermeer · Effective 24 Nov 2020 · Lokale regelgeving (overheid.nl)

Grid access (3)

  • Grid accessIn force

    Wachtlijst TenneT – afname (november 2025)

    Netbeheer Nederland reported on 6 November 2025 that TenneT's waiting list held 212 unique offtake requests (38 GW) and 161 feed-in requests (34 GW). The requests cover both firm capacity and alternative transport rights.

    38 GW Offtake 38 GW. Feed-in 34 GW is reported in the same sentence.

    Netbeheer Nederland

  • Grid accessIn force

    Wachtlijst regionale netbeheerders – afname (november 2025)

    In a news item of 6 November 2025, Netbeheer Nederland said 14,044 unique offtake requests, together 9,131 MW, were on the regional grid operators' waiting lists. The requests include both firm transport capacity and capacity under alternative transport rights.

    9,131 MW Snapshot at publication date. This is a different reference date from the end-2025 figure (9.305 MW) in the LAN report.

    Netbeheer Nederland

  • Grid accessIn force

    Stand van de Uitvoering 2025: wachtlijsten netcongestie

    Grid operators' status report (reference date 1 September 2025): 14,044 unique offtake requests on regional operators' waiting lists and 8,539 feed-in requests; at TenneT 212 offtake requests (38 GW) and 161 feed-in requests (34 GW). TenneT's waiting list includes requests from industrial large consumers, batteries and data centres.

    38 GW TenneT offtake queue 212 offtake requests on TenneT waiting list

    Netbeheer Nederland

Efficiency rule (2)

  • Efficiency ruleIn force

    Rapportageplicht datacentra (EED artikel 12, Gedelegeerde Verordening (EU) 2024/1364)

    Owners or operators of data centres with installed IT power of at least 500 kW must report energy performance yearly to the European database, covering energy efficiency, water usage efficiency, energy reuse factor and renewable energy factor. Based on EED article 12 and Delegated Regulation (EU) 2024/1364 of 14 March 2024; implemented via the Besluit activiteiten leefomgeving (stb-2024-122) and a Regeling (stcrt-2024-18837). The 2026 window ran 16 March to 15 May 2026.

    500 kW installed IT power threshold

    European Commission; implemented by Rijksoverheid / RVO · RVO

  • Efficiency ruleIn force

    Energiebesparingsplicht en informatieplicht voor datacenters

    Since 2019 some data centres had to apply power management; from 2023 all data centres in the Netherlands have an energy-saving obligation. They must carry out all energy-saving measures with a payback period of 5 years or less and report on measures taken once every 4 years. Measures are listed in the Erkende Maatregelenlijsten (EML), supplemented for data centres. (source gives year only)

    5 years max payback for mandatory measures Measures with payback of 5 years or less are mandatory

    Rijksdienst voor Ondernemend Nederland (RVO) · Effective 1 Jan 2023 · RVO

Regulation (3)

  • RegulationIn force

    Codebesluit operationalisering TDTR

    ACM approved a joint grid operators' proposal to improve the conditions of the TDTR on TenneT's grid. Connected parties now learn earlier whether they get transport rights, so they can still take part in the balancing market. The code text was also made clearer.

    85 % van de tijd Decision date 23-04-2026, published 07-05-2026 (Staatscourant 2026, 17010). The effective date is not stated on the page, hence confidence partly. Case number ACM/25/199016.

    Autoriteit Consument & Markt (ACM) · ACM – Codebesluit operationalisering TDTR

  • RegulationIn force

    Codebesluit prioriteringsruimte transportverzoeken 2025

    ACM amended the Netcode elektriciteit with a new prioritisation framework. It replaces the 2024 framework, which the CBb annulled. In congestion areas, grid operators must depart from first-come-first-served and can give priority to three categories: congestion relievers (highest), safety functions, and basic needs such as housing, education, telecom and public transport. Priority is not automatic. Applicants must prove eligibility with evidence. ACM received 106 consultation responses.

    Autoriteit Consument & Markt (ACM) · Effective 1 Jan 2026 · ACM – Codebesluit prioriteringsruimte transportverzoeken 2025

  • RegulationIn force

    Codebesluit Alternatieve transportrechten

    ACM introduced two alternative transport rights. The time-duration right (TDTR) is on TenneT's national high-voltage grid and guarantees transport for at least 85% of hours per year. The time-block right is on regional grids. Users of alternative transport rights pay a lower network tariff. The decision applies from 1 April 2025. TenneT may offer TDTR until 1 October 2025 and must offer it from that date.

    85 % van de uren op jaarbasis Decision date 16-07-2024, published 19-07-2024. TenneT must offer TDTR from 1 October 2025. Case number ACM/23/187219.

    Autoriteit Consument & Markt (ACM) · Effective 1 Apr 2025 · ACM – Codebesluit Alternatieve transportrechten

Announced and proposed

Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.

  • Plan or strategyAnnounced

    Kabinetsstandpunt Europese AI-gigafabriekeninitiatief (Kamerstuk 26 643, nr. 1499)

    Letter of 31 March 2026: the cabinet will not reserve public capacity in EuroHPC AI gigafactories within the current budget, prefers market-financed gigafactories, aims to streamline data centre permitting, and notes grid congestion and spatial scarcity. The state invests EUR 71 million in an AI factory in Groningen, part of over EUR 200 million with the region and the European Commission.

    71 EUR million state investment AI factory Groningen; total over EUR 200 million

    Staatssecretaris van Economische Zaken en Klimaat · Groningen · Tweede Kamer (officielebekendmakingen.nl)

  • RestrictionAnnounced

    Vestigingsbeleid datacenters Amsterdam 2020-2030, eerste herziening

    Revision dated 3 November 2023 of Amsterdam's 2020-2030 data centre siting policy. Sets 350 MVA as the new maximum connection capacity in the municipality (down from 670 MVA), a design PUE target of at most 1.16, and limits new allocations to Sciencepark, Amstel III, Schinkelkwartier and Haven. A paraplubestemmingsplan to make it legally binding was in preparation.

    350 MVA cap New maximum connection capacity; design PUE target 1.16

    Gemeente Amsterdam · Amsterdam · Gemeente Amsterdam (ruimtelijkeplannen.nl)

Timeline of data center and power policy in Netherlands

DateActionTypeStatusAuthority
7 May 2026Codebesluit operationalisering TDTRRegulationIn forceAutoriteit Consument & Markt (ACM)
31 Mar 2026Kabinetsstandpunt Europese AI-gigafabriekeninitiatief (Kamerstuk 26 643, nr. 1499) GroningenPlan or strategyAnnouncedStaatssecretaris van Economische Zaken en Klimaat
12 Dec 2025Codebesluit prioriteringsruimte transportverzoeken 2025RegulationIn forceAutoriteit Consument & Markt (ACM)
6 Nov 2025Wachtlijst TenneT – afname (november 2025)Grid accessIn forceNetbeheer Nederland
6 Nov 2025Wachtlijst regionale netbeheerders – afname (november 2025)Grid accessIn forceNetbeheer Nederland
1 Sep 2025Stand van de Uitvoering 2025: wachtlijsten netcongestieGrid accessIn forceNetbeheer Nederland
1 Jan 2025Geactualiseerde Datacenterstrategie Noord-Holland 2025-2027 Noord-HollandMoratoriumIn forceGedeputeerde Staten van Noord-Holland
19 Jul 2024Codebesluit Alternatieve transportrechtenRegulationIn forceAutoriteit Consument & Markt (ACM)
14 Mar 2024Rapportageplicht datacentra (EED artikel 12, Gedelegeerde Verordening (EU) 2024/1364)Efficiency ruleIn forceEuropean Commission; implemented by Rijksoverheid / RVO
20 Dec 2023Besluit van 20 december 2023 houdende wijziging van Besluit kwaliteit leefomgeving in verband met een instructieregel voor hyperscale datacentraRestrictionIn forceKroon / Minister voor Volkshuisvesting en Ruimtelijke Ordening
3 Nov 2023Vestigingsbeleid datacenters Amsterdam 2020-2030, eerste herziening AmsterdamRestrictionAnnouncedGemeente Amsterdam
1 Jan 2023Energiebesparingsplicht en informatieplicht voor datacentersEfficiency ruleIn forceRijksdienst voor Ondernemend Nederland (RVO)
16 Feb 2022Voorbereidingsbesluit hyperscale datacentra (Kamerbrief 26 643, nr. 819)MoratoriumExpiredMinister voor Volkshuisvesting en Ruimtelijke Ordening
1 Dec 2020Vestigingsbeleid datacenters gemeente Amsterdam 2020-2030 (Amsterdam Duurzaam Digitaal) AmsterdamRestrictionIn forceGemeenteraad Amsterdam
24 Nov 2020Datacenterbeleid gemeente Haarlemmermeer HaarlemmermeerRestrictionIn forceGemeenteraad Haarlemmermeer
13 Jul 2019Voorbereidingsbesluit datacenters gemeente Amsterdam (temporary halt on new data centres, 2019) AmsterdamMoratoriumExpiredGemeente Amsterdam
11 Jul 2019Voorbereidingsbesluit Datacenters gemeente Haarlemmermeer HaarlemmermeerMoratoriumExpiredGemeenteraad Haarlemmermeer

How Netherlands compares

Latest official figures for the countries we track.

CountryIndustrial power priceRenewable shareGrid emission factorRestrictions in forceIncentives in force
Argentina—19.6% (2025)0.28 kgCO2/kWh (2022)02
Australia—39% (2025)—02
Austria169 USD/MWh (2026)78% (2025)0.15 kgCO2/kWh (2023)00
Bangladesh—2% (2025)—00
Belgium183 USD/MWh (2025)34.3% (2025)0.19 kgCO2/kWh (2024)00
Brazil—86.8% (2025)0.07 kgCO2/kWh (2025)01
Canada—63.9% (2024)0.10 kgCO2/kWh (2022)60
Chile—66% (2025)0.24 kgCO2/kWh (2023)00
China—38% (2025)0.53 kgCO2/kWh (2023)20
Colombia——0.22 kgCO2/kWh (2024)02
Denmark134 USD/MWh (2025)81.5% (2024)0.11 kgCO2/kWh (2024)10
Ecuador——0.16 kgCO2/kWh (2024)10
Finland58.4 USD/MWh (2025)57% (2024)0.03 kgCO2/kWh (2025)00
France104 USD/MWh (2025)27% (2025)0.02 kgCO2/kWh (2025)01
Germany180 USD/MWh (2025)58.8% (2025)0.34 kgCO2/kWh (2025)10
Guatemala84.5 USD/MWh (2025)53.5% (2024)0.29 kgCO2/kWh (2024)02
Hong Kong180 USD/MWh (2026)—0.59 kgCO2/kWh (2025)02
Iceland42.9 USD/MWh (2022)100% (2026)—12
India82.1 USD/MWh (2025)28.7% (2026)0.68 kgCO2/kWh (2025)15
Indonesia62.9 USD/MWh (2024)16.3% (2025)0.68 kgCO2/kWh (2024)01
Ireland234 USD/MWh (2025)41.3% (2024)0.20 kgCO2/kWh (2025)20
Italy184 USD/MWh (2025)48% (2025)0.20 kgCO2/kWh (2025)00
Japan—23.1% (2024)0.45 kgCO2/kWh (2024)00
Kazakhstan—14.6% (2025)0.81 kgCO2/kWh (2025)00
Kyrgyzstan41.7 USD/MWh (2026)88% (2024)0.16 kgCO2/kWh (2019)11
Luxembourg165 USD/MWh (2025)23.3% (2025)—00
Malaysia105 USD/MWh (2026)21% (2025)0.74 kgCO2/kWh (2024)11
Mexico——0.44 kgCO2/kWh (2023)00
Nepal———00
Netherlands148 USD/MWh (2025)49% (2025)0.20 kgCO2/kWh (2024)40
Pakistan97.5 USD/MWh (2026)34.7% (2025)—01
Panama66.3 USD/MWh (2025)74.7% (2025)0.15 kgCO2/kWh (2024)01
Paraguay33.0 USD/MWh (2026)——12
Peru—62.6% (2025)—01
Philippines—22.2% (2024)0.71 kgCO2/kWh (2017)12
Russia—17.6% (2025)—20
Singapore189 USD/MWh (2025)2.1% (2024)0.40 kgCO2/kWh (2024)10
South Korea—9.8% (2025)—00
Spain113 USD/MWh (2025)55.5% (2025)—10
Sri Lanka—60.2% (2025)—00
Sweden78.5 USD/MWh (2025)—0.06 kgCO2/kWh (2023)00
Switzerland240 USD/MWh (2026)70.8% (2025)0.13 kgCO2/kWh (2022)00
Taiwan—12.7% (2025)0.47 kgCO2/kWh (2024)10
Thailand120 USD/MWh (2026)—0.48 kgCO2/kWh (2026)02
United Arab Emirates120 USD/MWh (2026)8.8% (2024)0.47 kgCO2/kWh (2024)00
United Kingdom234 USD/MWh (2026)52.1% (2025)0.15 kgCO2/kWh (2026)11
United States86.2 USD/MWh (2025)24% (2025)0.35 kgCO2/kWh (2023)01
Uruguay101 USD/MWh (2026)98% (2025)0.01 kgCO2/kWh (2025)03
Uzbekistan83.3 USD/MWh (2026)19.4% (2025)—10
Venezuela—77% (2023)—01

Questions

Is there a data center moratorium in Netherlands?

Yes. 4 restrictions on new data centers are in force in Netherlands: Geactualiseerde Datacenterstrategie Noord-Holland 2025-2027 (Noord-Holland), Besluit van 20 december 2023 houdende wijziging van Besluit kwaliteit leefomgeving in verband met een instructieregel voor hyperscale datacentra and Vestigingsbeleid datacenters gemeente Amsterdam 2020-2030 (Amsterdam Duurzaam Digitaal) (Amsterdam).

What does electricity cost for data centers in Netherlands?

The industrial electricity price in Netherlands was 148 USD/MWh in 2025 (Eurostat nrg_pc_205, band IE (20,000-69,999 MWh), excluding VAT and other recoverable taxes: 2025-S1 0.1432 and 2025-S2 0.1182 EUR/kWh, mean 130.7 EUR/MWh; converted at 2025 annual average 1.1300 USD/EUR (Eurostat ert_bil_eur_a) = 147.69 USD/MWh). Data center contracts can differ by voltage level, contract length and location.

How much of Netherlands’s electricity is renewable?

Renewables supplied 49% of electricity generation in Netherlands in 2025.

Where does this data come from?

Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.

What counts as a restriction or moratorium?

A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.

How are power prices compared?

We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.

How often is it updated?

Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.

Global capacity

How much data center capacity does Netherlands have?

Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.

See Netherlands capacity