Proprietary data
Data Center Power & Policy in Australia
Every government action on data centers and power in Australia that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.
In short
As of 16 November 2026, DC Market Insights tracks 17 government actions on data centers and power in Australia, 7 of them in force. We have found no moratorium or restriction on new data centers in force in Australia. 2 incentive schemes apply, including Investment Delivery Authority endorsement of 15 data centre projects.
Market snapshot
Australia power and policy: key facts
- Renewable share of electricity generation: 39% (2025). Rank 22 of 42 tracked countries, highest first.
- Latest change: Data centre contracting obligation for firmed energy (ERC0461) (Australian Energy Market Commission (proponent: Minister for Climate Change and Energy), 20 Oct 2026).
- By type: 4 plan or strategy, 3 regulation, 3 power tariff and 3 restriction.
Power indicators for Australia
Latest official figure for each indicator, with earlier years where we have them.
In force now in Australia
Power tariff (1)
Jemena site-specific (individually calculated) network tariffs for large HV and sub-transmission customers
In its April 2026 final decision on Jemena's 2026-31 tariff structure statement, the AER amended the statement to set out site-specific tariffs. Large customers connecting above 22kV, whether new connections or significant upgrades, can request one. Customers can opt out to a standard tariff. Prices are set in line with long run marginal cost (LRMC) and the NER pricing principles, using the same structure as the equivalent standard tariff. Jemena's discretion applies to negotiating prices, not to assigning customers.
22 kV Eligibility threshold as stated: >22kV. The statement applies from 1 July 2026 for the rest of the 2026-31 regulatory control period.
Incentive (2)
Investment Delivery Authority endorsement of 15 data centre projects
NSW Government announced 15 data centre projects collectively worth $51.9 billion will progress through the Investment Delivery Authority; about $40.7 billion of data centre and technology proposals were not endorsed as too early or too speculative. NSW has 90 operating data centres.
51.9 AUD billion endorsed project value 15 projects
Development Facilitation Program expedited planning pathways – Data centre
Victoria's Development Facilitation Program lists 'Data centre' under Digital technologies as eligible for expedited planning pathways, with estimated development cost thresholds of $10 million in regional areas and $20 million in metropolitan areas. Note: the page does not state when data centres were added; only a 'Page last updated: 17/09/25' line and metadata dates (created 2025-08-27) appear, so the date is year-only.
20 AUD million development cost threshold ( Regional threshold AUD 10 million
Regulation (1)
Hosting Certification Framework
Commonwealth framework requiring customers procuring hosting for sensitive government data, whole-of-government systems and PROTECTED-classified systems to use certified providers; currently applies to Data Centre Providers and Cloud Service Providers, with Strategic and Assured certification levels covering ownership and control safeguards. Requirements apply to new contracts and extensions to existing contracts from 30 June 2022. Released March 2021 (source gives month only).
Plan or strategy (3)
2026 Electricity Statement of Opportunities – data centre forecasts
AEMO's 2026 ESOO forecasts NEM data centre consumption rising from about 5 TWh (around 165 data centres) to around 15 TWh (7.8% of operational consumption) by FY30 and around 34 TWh (13%) by FY36 in Step Change; 225 known projects considered.
34 TWh data centre consumption by FY36 Step Change scenario
2026 Integrated System Plan (ISP)
AEMO's 2026 ISP for the NEM (version 1.0 released 25 June 2026) assumes in the Step Change scenario that data centres reach almost 10% of NEM underlying demand by 2050; total underlying consumption forecast to rise from 205 TWh to about 390 TWh in 2050.
10 % of NEM underlying demand by 2050 Step Change scenario
Expectations for Data Centres and AI Infrastructure Developers
Commonwealth Expectations for Data Centres and AI Infrastructure Developers, published by the Albanese Government in the same week as the NSW release of 27 March 2026, which says the NSW announcement 'follows and supports' it. Commonwealth page could not be opened; facts taken from the NSW Government release. (source gives month only)
Announced and proposed
Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.
Data centre contracting obligation for firmed energy (ERC0461)
The federal Minister for Climate Change and Energy has asked the AEMC to change the National Electricity Rules to create a contracting obligation for data centres to back their demand with firmed energy. The AEMC lists the project as pending and has not yet initiated it. A consultation paper will be published once the process starts. Related AEMC projects include connections framework enhancements for co-located plant and flexible loads, and the data centre advice to ECMC.
Cost recovery for network augmentations – Package 1 (ERC0448)
Rule change requests from Minister Chris Bowen (ERC0448, ERC0456) to require data centres and other large loads to cover network costs they cause or accelerate when connecting to the NEM. Initiated 24 September 2026; submissions close 5 November 2026; draft determination due 1 April 2027.
Sustainable Data Centre Action Plan – siting prohibitions
Under Victoria's Sustainable Data Centre Action Plan, data centres will be prohibited in residential zones. They will also not be built near schools and childcare centres, or in rural areas that cannot support them. The government describes these as part of its rules to protect homes and roads.
Sustainable Data Centre Action Plan – buffer zone for new data centres
On 22 September 2026 the Victorian Government released its Sustainable Data Centre Action Plan. Under the plan, a buffer zone will apply between new data centre buildings and homes. The same release says the plan also bars data centres from residential zones, keeps them away from schools, childcare centres and rural areas that cannot support them, and requires them to bring their own renewable supply and use recycled or non-drinking water for cooling.
150 metres The source says the new rules won't be retrospective for applications under assessment. It gives no commencement date.
Proposed national location requirement for large data centres
The federal consultation paper says the mandatory standards will include requiring large data centres to be located away from sensitive community areas where impacts cannot be appropriately avoided or managed. It asks whether data centres should have to sit a minimum distance from sensitive sites such as schools or homes, what that distance should be, and which level of government should administer location requirements.
Getting it right: Building AI infrastructure that works for Australia (consultation paper)
The Australian Government consulted on legislated national mandatory minimum requirements for large data centres covering energy, water, costs, community engagement, location and workforce. States and territories keep planning and approval powers and can set higher requirements. The paper proposes tiered thresholds by network connection capacity, with more substantial requirements for the largest facilities. Submissions closed 9 October 2026.
30 MW This is a consultation proposal; the threshold tiers are the starting point for consultation. The release date comes from the PM&C resource listing.
AEMC data centre advice to Energy and Climate Change Ministerial Council (ERC0452)
AEMC advice (ERC0452) requested by the Energy and Climate Change Ministerial Council on 8 May 2026 and completed 28 July 2026, with four recommendations: mandate data centres to offset consumption with REGO certificates linked to new renewable generation; a data centre contract obligation for firming capacity; market registration requirements for data centres; and connection agreements supporting demand flexibility and co-location. Based on preliminary analysis; further work is required before implementation.
Ausgrid new sub-threshold (trial) tariff EA905 for large business flexible load, 2026-27
In its 2026-27 pricing proposal to the AER, Ausgrid listed four new sub-threshold (trial) tariffs that continue its Project Edith. One is EA905, a flexible load tariff for large businesses, alongside a high-voltage dynamic connection tariff (EA976). The trial tariffs are open only to retailers that have signed a trial tariff memorandum of understanding with Ausgrid.
NSW Data Centre Consultation Paper
NSW Government released a consultation paper on a principles-based approach to data centre investment, including a proposed Data Centre Strategy considering energy and water use and infrastructure capacity; written feedback open for six weeks. The consultation has closed.
Improving NEM access standards – Package 2 (large inverter-based loads)
AEMO rule change request to set a tiered framework of access standards for large inverter-based loads such as data centres, including disturbance ride-through standards. Initiated 8 May 2025; draft determination 12 March 2026; final determination expected 29 October 2026.
Timeline of data center and power policy in Australia
| Date | Action | Type | Status | Authority |
|---|---|---|---|---|
| 20 Oct 2026 | Data centre contracting obligation for firmed energy (ERC0461) | Regulation | Proposed | Australian Energy Market Commission (proponent: Minister for Climate Change and Energy) |
| 24 Sep 2026 | Cost recovery for network augmentations – Package 1 (ERC0448) | Power tariff | Proposed | Australian Energy Market Commission (AEMC) |
| 22 Sep 2026 | Sustainable Data Centre Action Plan – siting prohibitions | Restriction | Announced | Victorian Government (Office of the Premier) |
| 22 Sep 2026 | Sustainable Data Centre Action Plan – buffer zone for new data centres | Restriction | Announced | Victorian Government (Office of the Premier) |
| 17 Sep 2026 | Proposed national location requirement for large data centres | Restriction | Proposed | Department of the Prime Minister and Cabinet (Office of AI) |
| 17 Sep 2026 | Getting it right: Building AI infrastructure that works for Australia (consultation paper) | Regulation | Proposed | Department of the Prime Minister and Cabinet (Office of AI) |
| 25 Aug 2026 | 2026 Electricity Statement of Opportunities – data centre forecasts | Plan or strategy | In force | Australian Energy Market Operator (AEMO) |
| 28 Jul 2026 | AEMC data centre advice to Energy and Climate Change Ministerial Council (ERC0452) | Renewable energy | Proposed | Australian Energy Market Commission (AEMC) |
| 25 Jun 2026 | 2026 Integrated System Plan (ISP) | Plan or strategy | In force | Australian Energy Market Operator (AEMO) |
| 30 Apr 2026 | Jemena site-specific (individually calculated) network tariffs for large HV and sub-transmission customers | Power tariff | In force | Australian Energy Regulator (AER) |
| 31 Mar 2026 | Ausgrid new sub-threshold (trial) tariff EA905 for large business flexible load, 2026-27 | Power tariff | Announced | Ausgrid (pricing proposal to the Australian Energy Regulator) |
| 27 Mar 2026 | NSW Data Centre Consultation Paper NSW | Plan or strategy | Proposed | NSW Government / Infrastructure NSW |
| 27 Mar 2026 | Investment Delivery Authority endorsement of 15 data centre projects NSW | Incentive | In force | NSW Treasury / Investment Delivery Authority |
| 1 Mar 2026 | Expectations for Data Centres and AI Infrastructure Developers | Plan or strategy | In force | Australian Government |
| 8 May 2025 | Improving NEM access standards – Package 2 (large inverter-based loads) | Grid access | Proposed | Australian Energy Market Commission (AEMC) |
| 1 Jan 2025 | Development Facilitation Program expedited planning pathways – Data centre VIC | Incentive | In force | Victorian Department of Transport and Planning |
| 1 Mar 2021 | Hosting Certification Framework | Regulation | In force | Australian Government (Digital Transformation Agency; now Department of Home Affairs) |
How Australia compares
Latest official figures for the countries we track.
| Country | Industrial power price | Renewable share | Grid emission factor | Restrictions in force | Incentives in force |
|---|---|---|---|---|---|
| Argentina | — | 19.6% (2025) | 0.28 kgCO2/kWh (2022) | 0 | 2 |
| Australia | — | 39% (2025) | — | 0 | 2 |
| Austria | 169 USD/MWh (2026) | 78% (2025) | 0.15 kgCO2/kWh (2023) | 0 | 0 |
| Bangladesh | — | 2% (2025) | — | 0 | 0 |
| Belgium | 183 USD/MWh (2025) | 34.3% (2025) | 0.19 kgCO2/kWh (2024) | 0 | 0 |
| Brazil | — | 86.8% (2025) | 0.07 kgCO2/kWh (2025) | 0 | 1 |
| Canada | — | 63.9% (2024) | 0.10 kgCO2/kWh (2022) | 6 | 0 |
| Chile | — | 66% (2025) | 0.24 kgCO2/kWh (2023) | 0 | 0 |
| China | — | 38% (2025) | 0.53 kgCO2/kWh (2023) | 2 | 0 |
| Colombia | — | — | 0.22 kgCO2/kWh (2024) | 0 | 2 |
| Denmark | 134 USD/MWh (2025) | 81.5% (2024) | 0.11 kgCO2/kWh (2024) | 1 | 0 |
| Ecuador | — | — | 0.16 kgCO2/kWh (2024) | 1 | 0 |
| Finland | 58.4 USD/MWh (2025) | 57% (2024) | 0.03 kgCO2/kWh (2025) | 0 | 0 |
| France | 104 USD/MWh (2025) | 27% (2025) | 0.02 kgCO2/kWh (2025) | 0 | 1 |
| Germany | 180 USD/MWh (2025) | 58.8% (2025) | 0.34 kgCO2/kWh (2025) | 1 | 0 |
| Guatemala | 84.5 USD/MWh (2025) | 53.5% (2024) | 0.29 kgCO2/kWh (2024) | 0 | 2 |
| Hong Kong | 180 USD/MWh (2026) | — | 0.59 kgCO2/kWh (2025) | 0 | 2 |
| Iceland | 42.9 USD/MWh (2022) | 100% (2026) | — | 1 | 2 |
| India | 82.1 USD/MWh (2025) | 28.7% (2026) | 0.68 kgCO2/kWh (2025) | 1 | 5 |
| Indonesia | 62.9 USD/MWh (2024) | 16.3% (2025) | 0.68 kgCO2/kWh (2024) | 0 | 1 |
| Ireland | 234 USD/MWh (2025) | 41.3% (2024) | 0.20 kgCO2/kWh (2025) | 2 | 0 |
| Italy | 184 USD/MWh (2025) | 48% (2025) | 0.20 kgCO2/kWh (2025) | 0 | 0 |
| Japan | — | 23.1% (2024) | 0.45 kgCO2/kWh (2024) | 0 | 0 |
| Kazakhstan | — | 14.6% (2025) | 0.81 kgCO2/kWh (2025) | 0 | 0 |
| Kyrgyzstan | 41.7 USD/MWh (2026) | 88% (2024) | 0.16 kgCO2/kWh (2019) | 1 | 1 |
| Luxembourg | 165 USD/MWh (2025) | 23.3% (2025) | — | 0 | 0 |
| Malaysia | 105 USD/MWh (2026) | 21% (2025) | 0.74 kgCO2/kWh (2024) | 1 | 1 |
| Mexico | — | — | 0.44 kgCO2/kWh (2023) | 0 | 0 |
| Nepal | — | — | — | 0 | 0 |
| Netherlands | 148 USD/MWh (2025) | 49% (2025) | 0.20 kgCO2/kWh (2024) | 4 | 0 |
| Pakistan | 97.5 USD/MWh (2026) | 34.7% (2025) | — | 0 | 1 |
| Panama | 66.3 USD/MWh (2025) | 74.7% (2025) | 0.15 kgCO2/kWh (2024) | 0 | 1 |
| Paraguay | 33.0 USD/MWh (2026) | — | — | 1 | 2 |
| Peru | — | 62.6% (2025) | — | 0 | 1 |
| Philippines | — | 22.2% (2024) | 0.71 kgCO2/kWh (2017) | 1 | 2 |
| Russia | — | 17.6% (2025) | — | 2 | 0 |
| Singapore | 189 USD/MWh (2025) | 2.1% (2024) | 0.40 kgCO2/kWh (2024) | 1 | 0 |
| South Korea | — | 9.8% (2025) | — | 0 | 0 |
| Spain | 113 USD/MWh (2025) | 55.5% (2025) | — | 1 | 0 |
| Sri Lanka | — | 60.2% (2025) | — | 0 | 0 |
| Sweden | 78.5 USD/MWh (2025) | — | 0.06 kgCO2/kWh (2023) | 0 | 0 |
| Switzerland | 240 USD/MWh (2026) | 70.8% (2025) | 0.13 kgCO2/kWh (2022) | 0 | 0 |
| Taiwan | — | 12.7% (2025) | 0.47 kgCO2/kWh (2024) | 1 | 0 |
| Thailand | 120 USD/MWh (2026) | — | 0.48 kgCO2/kWh (2026) | 0 | 2 |
| United Arab Emirates | 120 USD/MWh (2026) | 8.8% (2024) | 0.47 kgCO2/kWh (2024) | 0 | 0 |
| United Kingdom | 234 USD/MWh (2026) | 52.1% (2025) | 0.15 kgCO2/kWh (2026) | 1 | 1 |
| United States | 86.2 USD/MWh (2025) | 24% (2025) | 0.35 kgCO2/kWh (2023) | 0 | 1 |
| Uruguay | 101 USD/MWh (2026) | 98% (2025) | 0.01 kgCO2/kWh (2025) | 0 | 3 |
| Uzbekistan | 83.3 USD/MWh (2026) | 19.4% (2025) | — | 1 | 0 |
| Venezuela | — | 77% (2023) | — | 0 | 1 |
Questions
Is there a data center moratorium in Australia?
We have found no moratorium or restriction on new data centers in force in Australia as of 16 November 2026. Proposed or announced measures, if any, are listed in the timeline.
What incentives does Australia offer data centers?
In force: Investment Delivery Authority endorsement of 15 data centre projects and Development Facilitation Program expedited planning pathways – Data centre. Each is listed with its authority and dates on this page.
How much of Australia’s electricity is renewable?
Renewables supplied 39% of electricity generation in Australia in 2025.
Where does this data come from?
Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.
What counts as a restriction or moratorium?
A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.
How are power prices compared?
We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.
How often is it updated?
Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.
Global capacity
How much data center capacity does Australia have?
Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.
Choosing a market or a site?
Our analysts prepare country briefings on power, grid access, incentives and permits, with every source, in Excel.
