Data Center Power & Policy in Ireland
Every government action on data centers and power in Ireland that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.
In short
As of 8 October 2026, DC Market Insights tracks 9 government actions on data centers and power in Ireland, 8 of them in force. Ireland has 2 restrictions on new data centers in force, the latest: EirGrid Data Centre Constrained Area Overview (May 2026).
Market snapshot
Ireland power and policy: key facts
- Industrial electricity price: 234 USD/MWh (2025). Rank 2 of 30 tracked countries, highest first.
- Renewable share of electricity generation: 41.3% (2024). Rank 21 of 42 tracked countries, highest first.
- Grid emission factor: 0.20 kgCO2/kWh (2025). Rank 22 of 36 tracked countries, highest first.
- Data centers’ share of electricity demand: 22% (2024). Rank 1 of 5 tracked countries, highest first.
- Latest change: Data Centre Connection Offer Process and Policy (DCCOPP) Version 3 (EirGrid, 20 May 2026).
- By type: 3 grid access, 2 plan or strategy, 1 restriction and 1 renewable energy.
Power indicators for Ireland
Latest official figure for each indicator, with earlier years where we have them.
In force now in Ireland
Moratorium (1)
EirGrid position on new data centre connections in the greater Dublin area
EirGrid stated it would not accept new data centre applications in the Dublin region for the foreseeable future, possibly until 2028, saying the greater Dublin area is a constrained area; applications already in the pipeline proceed and applications elsewhere are assessed case by case. Reported as a de facto moratorium.
2,028 earliest year for new Dublin connections Reported possible end of restriction; not a fixed date
Restriction (1)
EirGrid Data Centre Constrained Area Overview (May 2026)
EirGrid classifies the greater Dublin region as fully constrained for data centres due to high short-circuit levels and overloads; the greater Dublin and surrounding areas are expected to be constrained for large data centre developments until further 400 kV reinforcement. Published as Revision R1 under CRU/2025236.
Grid access (2)
Data Centre Connection Offer Process and Policy (DCCOPP) Version 3
EirGrid connection process for data centres implementing CRU/2025236: mandatory pre-application meeting, online application with EUR 7,000 first fee instalment, about 7.5 to 18 months processing depending on nominated generation status; applications in constrained areas cannot be progressed.
Large Energy User Connection Policy Decision (CRU/2025236)
New data centre connections must provide generation or storage matching requested maximum import capacity, onsite or local, participating in the wholesale market, and meet at least 80% of annual demand with additional renewable electricity within six years. System Operators assess constrained vs unconstrained location and had to publish a connection process by 31 March 2026.
80 % annual demand from additional renewabl
Renewable energy (1)
CRU clarification permitting private wire connections for data centres (CRU/2025236)
As part of the Large Energy User connection policy decision published 12 December 2025, the CRU clarified that private wire connections between generators and data centres that bypass the public grid are permitted, subject to licensing requirements and market rules.
Efficiency rule (1)
Data Centre Energy and Sustainability Performance Reporting Obligations
Data centres in Ireland with installed IT power demand of at least 500 kW must report energy and sustainability performance under EU Delegated Regulation 2024/1364; reports are due by 15 May each year. The first deadline was 15 September 2024 for calendar year 2023. Date shown is the first reporting deadline; the page gives no adoption date.
500 kW IT power threshold
Plan or strategy (2)
Large Energy User Action Plan (LEAP)
Government action plan with 17 enabling actions for energy-intensive developments, including data centres, built on siting new large demand near renewable sources and a plan-led approach for very large investments, including green energy parks. Complements the CRU December 2025 connection policy.
17 enabling actions
Government Statement on the Role of Data Centres in Ireland's Enterprise Strategy
Revised Government statement setting principles for data centre development, with a preference for projects associated with strong economic activity and employment; developments not consistent with the principles are not in line with government policy.
Timeline of data center and power policy in Ireland
| Date | Action | Type | Status | Authority |
|---|---|---|---|---|
| 20 May 2026 | Data Centre Connection Offer Process and Policy (DCCOPP) Version 3 | Grid access | In force | EirGrid |
| 20 May 2026 | EirGrid Data Centre Constrained Area Overview (May 2026) Greater Dublin | Restriction | In force | EirGrid |
| 13 Jan 2026 | Large Energy User Action Plan (LEAP) | Plan or strategy | In force | Government of Ireland (Department of Enterprise, Tourism and Employment) |
| 12 Dec 2025 | CRU clarification permitting private wire connections for data centres (CRU/2025236) | Renewable energy | In force | Commission for Regulation of Utilities (CRU) |
| 12 Dec 2025 | Large Energy User Connection Policy Decision (CRU/2025236) | Grid access | In force | Commission for Regulation of Utilities (CRU) |
| 15 Sep 2024 | Data Centre Energy and Sustainability Performance Reporting Obligations | Efficiency rule | In force | Department of Climate, Energy and the Environment |
| 27 Jul 2022 | Government Statement on the Role of Data Centres in Ireland's Enterprise Strategy | Plan or strategy | In force | Department of Enterprise, Trade and Employment |
| 11 Jan 2022 | EirGrid position on new data centre connections in the greater Dublin area Greater Dublin | Moratorium | In force | EirGrid |
| 23 Nov 2021 | CRU/21/124 Direction to the System Operators related to Data Centre grid connection processing | Grid access | Expired | Commission for Regulation of Utilities (CRU) |
How Ireland compares
Latest official figures for the countries we track.
| Country | Industrial power price | Renewable share | Grid emission factor | Restrictions in force | Incentives in force |
|---|---|---|---|---|---|
| Argentina | — | 19.6% (2025) | 0.28 kgCO2/kWh (2022) | 0 | 2 |
| Australia | — | 39% (2025) | — | 0 | 2 |
| Austria | 169 USD/MWh (2026) | 78% (2025) | 0.15 kgCO2/kWh (2023) | 0 | 0 |
| Bangladesh | — | 2% (2025) | — | 0 | 0 |
| Belgium | 183 USD/MWh (2025) | 34.3% (2025) | 0.19 kgCO2/kWh (2024) | 0 | 0 |
| Brazil | — | 86.8% (2025) | 0.07 kgCO2/kWh (2025) | 0 | 1 |
| Canada | — | 63.9% (2024) | 0.10 kgCO2/kWh (2022) | 6 | 0 |
| Chile | — | 66% (2025) | 0.24 kgCO2/kWh (2023) | 0 | 0 |
| China | — | 38% (2025) | 0.53 kgCO2/kWh (2023) | 2 | 0 |
| Colombia | — | — | 0.22 kgCO2/kWh (2024) | 0 | 2 |
| Denmark | 134 USD/MWh (2025) | 81.5% (2024) | 0.11 kgCO2/kWh (2024) | 1 | 0 |
| Ecuador | — | — | 0.16 kgCO2/kWh (2024) | 1 | 0 |
| Finland | 58.4 USD/MWh (2025) | 57% (2024) | 0.03 kgCO2/kWh (2025) | 0 | 0 |
| France | 104 USD/MWh (2025) | 27% (2025) | 0.02 kgCO2/kWh (2025) | 0 | 1 |
| Germany | 180 USD/MWh (2025) | 58.8% (2025) | 0.34 kgCO2/kWh (2025) | 1 | 0 |
| Guatemala | 84.5 USD/MWh (2025) | 53.5% (2024) | 0.29 kgCO2/kWh (2024) | 0 | 2 |
| Hong Kong | 180 USD/MWh (2026) | — | 0.59 kgCO2/kWh (2025) | 0 | 2 |
| Iceland | 42.9 USD/MWh (2022) | 100% (2026) | — | 1 | 2 |
| India | 82.1 USD/MWh (2025) | 28.7% (2026) | 0.68 kgCO2/kWh (2025) | 1 | 5 |
| Indonesia | 62.9 USD/MWh (2024) | 16.3% (2025) | 0.68 kgCO2/kWh (2024) | 0 | 1 |
| Ireland | 234 USD/MWh (2025) | 41.3% (2024) | 0.20 kgCO2/kWh (2025) | 2 | 0 |
| Italy | 184 USD/MWh (2025) | 48% (2025) | 0.20 kgCO2/kWh (2025) | 0 | 0 |
| Japan | — | 23.1% (2024) | 0.45 kgCO2/kWh (2024) | 0 | 0 |
| Kazakhstan | — | 14.6% (2025) | 0.81 kgCO2/kWh (2025) | 0 | 0 |
| Kyrgyzstan | 41.7 USD/MWh (2026) | 88% (2024) | 0.16 kgCO2/kWh (2019) | 1 | 1 |
| Luxembourg | 165 USD/MWh (2025) | 23.3% (2025) | — | 0 | 0 |
| Malaysia | 105 USD/MWh (2026) | 21% (2025) | 0.74 kgCO2/kWh (2024) | 1 | 1 |
| Mexico | — | — | 0.44 kgCO2/kWh (2023) | 0 | 0 |
| Nepal | — | — | — | 0 | 0 |
| Netherlands | 148 USD/MWh (2025) | 49% (2025) | 0.20 kgCO2/kWh (2024) | 4 | 0 |
| Pakistan | 97.5 USD/MWh (2026) | 34.7% (2025) | — | 0 | 1 |
| Panama | 66.3 USD/MWh (2025) | 74.7% (2025) | 0.15 kgCO2/kWh (2024) | 0 | 1 |
| Paraguay | 33.0 USD/MWh (2026) | — | — | 1 | 2 |
| Peru | — | 62.6% (2025) | — | 0 | 1 |
| Philippines | — | 22.2% (2024) | 0.71 kgCO2/kWh (2017) | 1 | 2 |
| Russia | — | 17.6% (2025) | — | 2 | 0 |
| Singapore | 189 USD/MWh (2025) | 2.1% (2024) | 0.40 kgCO2/kWh (2024) | 1 | 0 |
| South Korea | — | 9.8% (2025) | — | 0 | 0 |
| Spain | 113 USD/MWh (2025) | 55.5% (2025) | — | 1 | 0 |
| Sri Lanka | — | 60.2% (2025) | — | 0 | 0 |
| Sweden | 78.5 USD/MWh (2025) | — | 0.06 kgCO2/kWh (2023) | 0 | 0 |
| Switzerland | 240 USD/MWh (2026) | 70.8% (2025) | 0.13 kgCO2/kWh (2022) | 0 | 0 |
| Taiwan | — | 12.7% (2025) | 0.47 kgCO2/kWh (2024) | 1 | 0 |
| Thailand | 120 USD/MWh (2026) | — | 0.48 kgCO2/kWh (2026) | 0 | 2 |
| United Arab Emirates | 120 USD/MWh (2026) | 8.8% (2024) | 0.47 kgCO2/kWh (2024) | 0 | 0 |
| United Kingdom | 234 USD/MWh (2026) | 52.1% (2025) | 0.15 kgCO2/kWh (2026) | 1 | 1 |
| United States | 86.2 USD/MWh (2025) | 24% (2025) | 0.35 kgCO2/kWh (2023) | 0 | 1 |
| Uruguay | 101 USD/MWh (2026) | 98% (2025) | 0.01 kgCO2/kWh (2025) | 0 | 3 |
| Uzbekistan | 83.3 USD/MWh (2026) | 19.4% (2025) | — | 1 | 0 |
| Venezuela | — | 77% (2023) | — | 0 | 1 |
Questions
Is there a data center moratorium in Ireland?
Yes. 2 restrictions on new data centers are in force in Ireland: EirGrid Data Centre Constrained Area Overview (May 2026) (Greater Dublin) and EirGrid position on new data centre connections in the greater Dublin area (Greater Dublin).
What does electricity cost for data centers in Ireland?
The industrial electricity price in Ireland was 234 USD/MWh in 2025 (Eurostat nrg_pc_205, band MWH20000-69999 (consumption 20 000-69 999 MWh), excl. VAT and other recoverable taxes (X_VAT): 2025-S1 0.2173 and 2025-S2 0.1970 EUR/kWh, average 207.15 EUR/MWh; converted at 2025 annual average 1.1300 USD/EUR (Eurostat ert_bil_e). Data center contracts can differ by voltage level, contract length and location.
How much of Ireland’s electricity is renewable?
Renewables supplied 41.3% of electricity generation in Ireland in 2024.
Where does this data come from?
Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.
What counts as a restriction or moratorium?
A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.
How are power prices compared?
We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.
How often is it updated?
Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.
Global capacity
How much data center capacity does Ireland have?
Installed capacity in MW (IT load), its share of the region, the largest tracked sites and the outlook to 2035.