As of 22 October 2026, DC Market Insights tracks 11 government actions on data centers and power in Venezuela, 8 of them in force. We have found no moratorium or restriction on new data centers in force in Venezuela. 1 incentive scheme applies: Organic Law of Special Economic Zones: fiscal and customs incentives, technology parks eligible.

11Actions tracked
8In force
—Industrial power price
77%Renewable share of generation

Market snapshot

Venezuela power and policy: key facts

  • Renewable share of electricity generation: 77% (2023). Rank 5 of 37 tracked countries, highest first.
  • Latest change: Public-sector reduced working hours to ease pressure on the power grid (August 2026) (Presidency (acting president Delcy Rodríguez), 13 Aug 2026).
  • By type: 5 regulation, 1 other, 1 restriction and 1 incentive.

Power indicators for Venezuela

Latest official figure for each indicator, with earlier years where we have them.

Renewable share of electricity generation 77% 2023 · Share of renewables in electricity generation 2023 as stated by IRENA (%): renewable 68,557 GWh of 88,555 GWh total = 77% stated; almost all hydro and marine (68,515 GWh). Profile last updated 22 September 2025.

In force now in Venezuela

Grid access (1)

  • Grid accessIn force

    Ministry authorisation (habilitación) required for self-generation of 2 MW or more (LOSSE Arts. 45-46)

    Self-generation is allowed only for the exclusive consumption of the producer and operates independently of the national grid. Installations of 2 MW or more need a habilitación from MPPEE. Data centers relying on on-site diesel or gas generation at that scale therefore need ministry approval, and the law in force gives no route to sell surplus to the grid.

    2 MW Self-generation capacity at or above which MPPEE authorisation is required

    Ministerio del Poder Popular para la Energía Eléctrica (MPPEE) · Effective 14 Dec 2010 · Ley Orgánica del Sistema y Servicio Eléctrico (Gaceta Oficial 39.573), copy hosted by Ministerio del Poder Popular para la Defensa

Power tariff (1)

  • Power tariffIn force

    Electricity tariffs set by the Ministry of Electric Energy, reviewed annually (LOSSE Arts. 59-66)

    Tariffs are not market prices: MPPEE designs the tariff scheme from activity costs and user classification (use, consumption level, location, technical characteristics), must review system costs every year to decide on tariff adjustments, must include incentives for efficient use, and may set targeted subsidies including for productive sectors it wants to incentivise. No current published tariff schedule for industrial or commercial users was found.

    Ministerio del Poder Popular para la Energía Eléctrica (MPPEE) · Effective 14 Dec 2010 · Ley Orgánica del Sistema y Servicio Eléctrico (Gaceta Oficial 39.573), copy hosted by Ministerio del Poder Popular para la Defensa

Incentive (1)

  • IncentiveIn force

    Organic Law of Special Economic Zones: fiscal and customs incentives, technology parks eligible

    The 2022 Special Economic Zones law lets national or foreign companies that sign an economic activity agreement with the National Superintendency of SEZs claim incentives, including import duty drawback and refunds of other national taxes as set in each zone's creation decree. Technology activities (technology parks, telecoms, informatics, telematics and software systems) are an eligible sector. The finance ministry caps total incentives by reference to prior-year income tax collection.

    Asamblea Nacional; Superintendencia Nacional de las Zonas Económicas Especiales · Effective 20 Jul 2022

Efficiency rule (1)

Regulation (4)

  • RegulationIn force

    Crypto-asset decree: digital miners must register with SUNACRIP

    The Constituent Decree on the Integral System of Crypto-assets (Gaceta 41.575) regulates digital mining among other crypto activities and requires miners and other participants to register in SUNACRIP registries. SUNACRIP was intervened in 2023 and its current functioning was not verified.

    Asamblea Nacional Constituyente; SUNACRIP · Effective 30 Jan 2019

  • RegulationIn force

    Foreign investment registration with EUR 800,000 minimum (Ley Constitucional de Inversión Extranjera Productiva)

    To register a foreign investment, contributions must reach at least EUR 800,000 or CNY 6.5 million (or equivalent) at the official exchange rate; the ministry may lower the minimum to no less than 10% of that amount for sector or SME reasons. Registered investments sign investment contracts that detail incentives, the region of the investment and duration; preferred sectors defined by the Executive get more favourable incentives.

    800,000 EUR Minimum contribution to register a foreign investment (Art. 19)

    Asamblea Nacional Constituyente; Ministerio del Poder Popular para el Comercio Exterior e Inversión Internacional · Effective 29 Dec 2017

  • RegulationIn force

    Ley de Infogobierno: public bodies must use free software and open standards

    The Infogovernment Law governs IT use by all public bodies and promotes technological independence. Public bodies may only use free software and open standards; proprietary software needs an exceptional authorisation of up to three years from the National IT Commission (CONATI). This shapes public-sector IT and hosting procurement. No general personal data protection law was found.

    Asamblea Nacional; Comisión Nacional de las Tecnologías de Información (CONATI) · Effective 17 Oct 2013

  • RegulationIn force

    State reservation of all electricity activities (LOSSE Art. 8)

    The Organic Law of the Electric System and Service reserves generation, transmission, distribution and commercialisation to the State through the single operator and service provider (CORPOELEC), and system dispatch to the Ministry of Electric Energy (MPPEE). Under the law in force a data center cannot buy power from a private generator; the only grid supplier is the state operator. Mixed companies supplying inputs to the sector require at least 60% State capital (Art. 10).

    Asamblea Nacional; Ministerio del Poder Popular para la Energía Eléctrica (MPPEE) · Effective 14 Dec 2010 · Ley Orgánica del Sistema y Servicio Eléctrico (Gaceta Oficial 39.573), copy hosted by Ministerio del Poder Popular para la Defensa

Announced and proposed

Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.

  • OtherAnnounced

    Public-sector reduced working hours to ease pressure on the power grid (August 2026)

    Acting leader Delcy Rodríguez announced that the public sector will work reduced hours (alternate days and half days, except essential services such as health) to relieve the strained national grid. No end date was given. It indicates ongoing supply shortfalls and load-management measures relevant to data center reliability planning.

    Presidency (acting president Delcy Rodríguez)

  • RegulationProposed

    Partial reform of the electricity law to open generation and commercialisation to private investment

    On 2 June 2026 the National Assembly unanimously approved at first reading a 42-article reform of the Organic Law of the Electric System and Service. It would allow mixed and private capital under concessions with public supervision (the Republic keeps over 50% of mixed companies), open generation and commercialisation to national and foreign private investment, prioritise solar and wind, and move to cost-reflective tariffs. The second reading was postponed on 15 October 2026; acting president Delcy Rodríguez said on 8 October no reform would pass this year.

    Asamblea Nacional; MPPEE · Asamblea Nacional de Venezuela

  • RestrictionAnnounced

    Disconnection of all crypto-mining farms from the national grid (SEN)

    In May 2024 the Ministry of Electric Energy announced a plan, with CORPOELEC and the Public Ministry, to disconnect all cryptocurrency mining farms from the national electric system to relieve demand, following seizures of mining equipment. It was announced on social media; no Gaceta Oficial instrument was found. It signals grid-access risk for large high-density compute loads.

    Ministerio del Poder Popular para la Energía Eléctrica (MPPEE); CORPOELEC

Timeline of data center and power policy in Venezuela

DateActionTypeStatusAuthority
13 Aug 2026Public-sector reduced working hours to ease pressure on the power grid (August 2026)OtherAnnouncedPresidency (acting president Delcy Rodríguez)
2 Jun 2026Partial reform of the electricity law to open generation and commercialisation to private investmentRegulationProposedAsamblea Nacional; MPPEE
17 May 2024Disconnection of all crypto-mining farms from the national grid (SEN)RestrictionAnnouncedMinisterio del Poder Popular para la Energía Eléctrica (MPPEE); CORPOELEC
20 Jul 2022Organic Law of Special Economic Zones: fiscal and customs incentives, technology parks eligibleIncentiveIn forceAsamblea Nacional; Superintendencia Nacional de las Zonas Económicas Especiales
30 Jan 2019Crypto-asset decree: digital miners must register with SUNACRIPRegulationIn forceAsamblea Nacional Constituyente; SUNACRIP
29 Dec 2017Foreign investment registration with EUR 800,000 minimum (Ley Constitucional de Inversión Extranjera Productiva)RegulationIn forceAsamblea Nacional Constituyente; Ministerio del Poder Popular para el Comercio Exterior e Inversión Internacional
17 Oct 2013Ley de Infogobierno: public bodies must use free software and open standardsRegulationIn forceAsamblea Nacional; Comisión Nacional de las Tecnologías de Información (CONATI)
14 Dec 2010Ministry authorisation (habilitación) required for self-generation of 2 MW or more (LOSSE Arts. 45-46)Grid accessIn forceMinisterio del Poder Popular para la Energía Eléctrica (MPPEE)
14 Dec 2010Mandatory energy-efficiency plan for users above 2 MW (LOSSE)Efficiency ruleIn forceAsamblea Nacional; MPPEE
14 Dec 2010Electricity tariffs set by the Ministry of Electric Energy, reviewed annually (LOSSE Arts. 59-66)Power tariffIn forceMinisterio del Poder Popular para la Energía Eléctrica (MPPEE)
14 Dec 2010State reservation of all electricity activities (LOSSE Art. 8)RegulationIn forceAsamblea Nacional; Ministerio del Poder Popular para la Energía Eléctrica (MPPEE)

How Venezuela compares

Latest official figures for the countries we track.

CountryIndustrial power priceRenewable shareGrid emission factorRestrictions in forceIncentives in force
Argentina—19.6% (2025)0.28 kgCO2/kWh (2022)02
Australia—39% (2025)—02
Bangladesh—2% (2025)—00
Belgium183 USD/MWh (2025)34.3% (2025)0.19 kgCO2/kWh (2024)00
Brazil—86.8% (2025)0.07 kgCO2/kWh (2025)01
Canada—63.9% (2024)0.10 kgCO2/kWh (2022)20
Chile—66% (2025)0.24 kgCO2/kWh (2023)00
Colombia——0.22 kgCO2/kWh (2024)02
Denmark134 USD/MWh (2025)81.5% (2024)0.11 kgCO2/kWh (2024)10
Ecuador——0.16 kgCO2/kWh (2024)10
Finland58.4 USD/MWh (2025)57% (2024)0.03 kgCO2/kWh (2025)00
France104 USD/MWh (2025)27% (2025)0.02 kgCO2/kWh (2025)01
Germany180 USD/MWh (2025)58.8% (2025)0.34 kgCO2/kWh (2025)10
Guatemala84.5 USD/MWh (2025)53.5% (2024)0.29 kgCO2/kWh (2024)02
Hong Kong180 USD/MWh (2026)—0.59 kgCO2/kWh (2025)02
India82.1 USD/MWh (2025)28.7% (2026)0.68 kgCO2/kWh (2025)05
Indonesia62.9 USD/MWh (2024)16.3% (2025)0.68 kgCO2/kWh (2024)01
Ireland234 USD/MWh (2025)41.3% (2024)0.20 kgCO2/kWh (2025)20
Italy184 USD/MWh (2025)48% (2025)0.20 kgCO2/kWh (2025)00
Japan—23.1% (2024)0.45 kgCO2/kWh (2024)00
Kazakhstan—14.6% (2025)0.81 kgCO2/kWh (2025)00
Kyrgyzstan41.7 USD/MWh (2026)88% (2024)0.16 kgCO2/kWh (2019)11
Luxembourg165 USD/MWh (2025)23.3% (2025)—00
Malaysia105 USD/MWh (2026)21% (2025)0.74 kgCO2/kWh (2024)11
Mexico——0.44 kgCO2/kWh (2023)00
Nepal———00
Netherlands148 USD/MWh (2025)49% (2025)0.20 kgCO2/kWh (2024)40
Pakistan97.5 USD/MWh (2026)34.7% (2025)—01
Panama66.3 USD/MWh (2025)74.7% (2025)0.15 kgCO2/kWh (2024)01
Paraguay33.0 USD/MWh (2026)——12
Peru—62.6% (2025)—01
Russia—17.6% (2025)—20
Singapore189 USD/MWh (2025)2.1% (2024)0.40 kgCO2/kWh (2024)00
South Korea—9.8% (2025)—00
Spain113 USD/MWh (2025)55.5% (2025)—00
Sri Lanka—60.2% (2025)—00
Sweden78.5 USD/MWh (2025)—0.06 kgCO2/kWh (2023)00
Switzerland240 USD/MWh (2026)70.8% (2025)0.13 kgCO2/kWh (2022)00
United Arab Emirates120 USD/MWh (2026)8.8% (2024)0.47 kgCO2/kWh (2024)00
United Kingdom234 USD/MWh (2026)52.1% (2025)0.15 kgCO2/kWh (2026)11
United States86.2 USD/MWh (2025)24% (2025)0.35 kgCO2/kWh (2023)01
Uruguay101 USD/MWh (2026)98% (2025)0.01 kgCO2/kWh (2025)03
Uzbekistan83.3 USD/MWh (2026)19.4% (2025)—10
Venezuela—77% (2023)—01

Questions

Is there a data center moratorium in Venezuela?

We have found no moratorium or restriction on new data centers in force in Venezuela as of 22 October 2026. Proposed or announced measures, if any, are listed in the timeline.

What incentives does Venezuela offer data centers?

In force: Organic Law of Special Economic Zones: fiscal and customs incentives, technology parks eligible. Each is listed with its authority and dates on this page.

How much of Venezuela’s electricity is renewable?

Renewables supplied 77% of electricity generation in Venezuela in 2023.

Where does this data come from?

Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.

What counts as a restriction or moratorium?

A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.

How are power prices compared?

We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.

How often is it updated?

Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.

Global capacity

How much data center capacity is installed worldwide?

Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.

Open the Global Capacity Tracker

Choosing a market or a site?

Our analysts prepare country briefings on power, grid access, incentives and permits, with every source, in Excel.

Talk to an analyst