Proprietary data

Data Center Power & Policy in Israel

Every government action on data centers and power in Israel that we have verified: moratoriums, grid rules, incentives, tariffs and plans, with the power indicators that drive site selection.

In short

As of 26 November 2026, DC Market Insights tracks 13 government actions on data centers and power in Israel, 8 of them in force. Israel has 1 restriction on new data centers in force: Temporary freeze on grid connection processing for data centers of 8 MVA and above (Decision 74506).

13Actions tracked
8In force
—Industrial power price
14.6%Renewable share of generation

Market snapshot

Israel power and policy: key facts

  • Renewable share of electricity generation: 14.6% (2024). Rank 41 of 48 tracked countries, highest first.
  • Grid emission factor: 0.41 kgCO2/kWh (2024). Rank 14 of 41 tracked countries, highest first.
  • Data centers’ share of electricity demand: 0.5% (2024). Rank 6 of 6 tracked countries, highest first.
  • Latest change: Proposed 200 MW cap per new data center in large-consumer connection rules (Electricity Authority (Rashut HaChashmal), 19 Oct 2026).
  • By type: 3 power tariff, 3 plan or strategy, 2 grid access and 2 regulation.

Power indicators for Israel

Latest official figure for each indicator, with earlier years where we have them.

Renewable share of electricity generation 14.6% 2024 · Actual renewable consumption rate during 2024 (%); potential rate at year-end 16.2%. 2025 figure not found. Electricity Authority – Report on the State of the Electricity Sector, September 2025
Grid emission factor 0.41 kgCO2/kWh 2024 · Source states 413 gram CO2 per kWh produced (2024); converted g to kg only. Electricity Authority – Report on the State of the Electricity Sector, September 2025
Data centers’ share of electricity demand 0.5% 2024 · Estimated share of server farms in overall electricity consumption (%); report adds 5-7% possible by 2030. Electricity Authority – Report on the State of the Electricity Sector, September 2025
Installed generation capacity 24.6 GW 2024 · Sector capacity in 2024, GW as stated. Electricity Authority – Report on the State of the Electricity Sector, September 2025

In force now in Israel

Moratorium (1)

  • MoratoriumIn force

    Temporary freeze on grid connection processing for data centers of 8 MVA and above (Decision 74506)

    Temporary provision: the system operator (Noga) suspends handling, review and answers to connection requests under criteria 35יב(א)/35כג(א) for server farms of 8 MVA and above, accepts no new information requests and gives no new grid capacity reservations based on earlier answers not yet turned into binding commitments. Projects with signed commitments in technical coordination continue. The Authority cites about 19,000 MW of new data-center requests within roughly two months on top of an 8,000 MW backlog (27 GW total) and about 1.5 GW already committed. Valid 140 days, to 7 Dec 2026; public comments were due 19 Aug 2026.

    8 MVA Threshold connection size covered by the freeze; 140-day validity

    Electricity Authority (Rashut HaChashmal) · Ends 7 Dec 2026 · Electricity Authority Decision 74506 (meeting 745, 15.07.2026)

Power tariff (2)

  • Power tariffIn force

    Semi-annual tariff update from 1 July 2026 (amended by Decision 74010)

    Decision 74010 (30 Apr 2026) amended Decision 72806's network and supply update formulas (capacity and energy components indexed at each half-year update; generation variable component and system tariff updated yearly for excise). Under it the Authority updated all tariff tables from 1 July 2026, using CPI 143.30 (2006=100), risk-free rate 2.09, representative rate 3.01 ILS/USD and API2 coal 111.82 USD/ton.

    Electricity Authority (Rashut HaChashmal) · Effective 1 Jul 2026 · Electricity Authority notice on tariff update from 1.7.2026

  • Power tariffIn force

    New electricity tariff structure from 1 Jan 2026 (Decision 72806)

    Decision 72806 (8 Dec 2025) replaces tariff tables 1-6.3 and 8.1, fixes 2025 tariffs as the starting point per segment and indexes them with automatic update coefficients; tariff tables are updated each calendar half-year on 1 January and 1 July. It merges TOU time bands, changes network capacity/energy weights and sets a coefficient for the rising excise (gas excise 33 to 54 ILS/ton in 2026 and 80 ILS/ton in 2027). The Authority notes close to 60% of electricity is now produced by private producers and about 350,000 customers have moved to private suppliers. In force 1 Jan 2026; structure from 2029 to be decided by 31 Dec 2028.

    Electricity Authority (Rashut HaChashmal) · Effective 1 Jan 2026 · Electricity Authority Decision 72806 – update of the electricity tariff structure

Regulation (1)

  • RegulationIn force

    Privacy Protection Law Amendment 13 in force

    Amendment 13 to the Privacy Protection Law went into effect on 14 Aug 2025, strengthening the Privacy Protection Authority's enforcement tools, limiting mandatory database registration to public bodies and data-trading databases of 10,000+ people, requiring DPOs for public bodies and large/sensitive-data processors, and allowing exemplary damages up to NIS 10,000 per violation. The source does not cover cross-border transfer rules.

    Knesset / Privacy Protection Authority · Effective 14 Aug 2025

Plan or strategy (3)

  • Plan or strategyIn force

    Government Decision 4194: staff work on server-farm incentives near the Lebanon border

    Government Decision 4194 (2 June 2026), the 2026-2030 programme for communities 0-9 km from the Lebanon border, includes staff work to examine incentives and barriers for building server farms in national-priority areas, including removing planning barriers, the energy supply for server farms and high-capacity connectivity; conclusions are to feed into the national plan the National AI Directorate brings to government.

    Government of Israel (Prime Minister's Office) · Government Decision 4194

  • Plan or strategyIn force

    Government Decision 3907: promoting advanced server farms for AI leadership

    Government Decision 3907 of 22 Feb 2026 on promoting advanced server farms. Per press coverage, server farms and data-center complexes are to be recognised as national infrastructure and planned directly by the National Infrastructure Committee (VTL), with targeted incentives in areas with electrical priority. The Electricity Authority cites its annex 3 requiring priority for locations that minimise grid development, and approval by the National AI Directorate for server farms with a 50 MW connection in certain circumstances.

    Government of Israel · Electricity Authority hearing – connection criteria for consumers ≥50 MVA

  • Plan or strategyIn force

    Government Decision 3586: electricity sector readiness for AI and renewables

    Government Decision 3586 of 4 Dec 2025, 'readiness of the electricity sector for growth in AI needs and renewable energies', instructed the Electricity Authority to examine dedicated rules for connecting server farms with regard to grid survivability, stability and reliability. An inter-ministerial team's interim conclusions favour siting server farms outside central Israel, shorter planning in preferred areas and preventing speculative grid bookings (as described in the Authority's June 2026 hearing).

    Government of Israel · Electricity Authority hearing – connection criteria for consumers ≥50 MVA (explanatory notes)

Other (1)

  • OtherIn force

    Government Resolution 171: 27% cut in electricity CO2 by 2030 vs 2015

    Government Resolution 171 (25 July 2021) set an absolute target of a 27% emissions reduction by 2030 relative to 2015; the Electricity Authority's September 2025 report says the electricity sector is expected to partially meet it from 2025 as CCGT 70 and 80 come online and coal units convert to gas.

    27 % Emissions reduction target vs 2015

    Government of Israel · Electricity Authority – Report on the State of the Electricity Sector, September 2025

Announced and proposed

Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.

  • RestrictionProposed

    Proposed 200 MW cap per new data center in large-consumer connection rules

    Trade press reports that the Electricity Authority published the main points of new rules for connecting large data centers to the grid, under which the capacity of a single new data center would be capped at 200 MW. The full decision was to be published for a three-week public consultation and may change before taking effect. Primary text not retrieved (gov.il pages blocked).

    200 MW Proposed per-facility cap

    Electricity Authority (Rashut HaChashmal)

  • Power tariffProposed

    Hearing on 2025 tariff differences: no segment changes, IEC add-on of 1.72 agorot/kWh in 2027

    Hearing of 18 Oct 2026 reviewing 2025 cost differences under Decision 72806: proposes no changes to segment tariffs or half-yearly update rules, a discussion during 2027 on generation and system tariffs, and a temporary provision for 1 Jan – 31 Dec 2027 under which the system operator pays IEC an additional 1.72 agorot per kWh injected by IEC generating units.

    1.72 ILS agorot/kWh

    Electricity Authority (Rashut HaChashmal) · Effective 1 Jan 2027 · Ends 31 Dec 2027 · Electricity Authority hearing – 2025 band differences

  • Grid accessProposed

    Hearing: dedicated connection track for consumers of 50 MVA and above to the transmission grid

    Electricity Authority hearing (meeting 743, 10 June 2026) proposing a dedicated connection track for consumers requesting 50 MVA or more on the transmission grid, replacing criterion 35כג for them: a voluntary paid feasibility check, then payment stages for connection and offtake commitment; applies on publication in Reshumot. It defines 'preferred areas' (zones 4-5 and others on the map) that export energy and are favoured for large consumers including server farms, with faster connection; it cites Government Decisions 3586 and 3907. Not adopted as of the sources found; the 74506 freeze says the final decision will follow this hearing.

    50 MVA Connection size threshold for the proposed track

    Electricity Authority (Rashut HaChashmal) · Electricity Authority hearing – connection criteria for consumers ≥50 MVA

  • RegulationProposed

    Planning and Building Law (Amendment 168) bill: AI server farms as national infrastructure

    Government bill published 20 May 2026 adding 'server farm intended for AI uses' to the definition of national infrastructure in the Planning and Building Law 1965, so plans can be prepared (including by authorised private bodies) and filed directly with the National Infrastructure Committee; such a facility's compute power draw is expected to be at least 50 MW; no more than ten such plans may be filed with the VTL per calendar year. Follows Government Decision 3907. Enactment status not confirmed.

    50 MW Minimum expected power draw for an 'AI server farm' under the bill; cap of 10 plans per year

    Knesset (government bill) · Knesset – Hatza'ot Hok HaMemshala, Planning and Building Bill (Amendment No. 168) 5786-2026

  • Grid accessAnnounced

    Amended criteria for feasibility surveys, planning and grid connection (Decision 73305)

    Decision 73305 (28 Jan 2026) amends the service criteria so that surveys are distinguished by complexity (complex surveys, e.g. large-capacity facilities, get longer system-operator timelines up to a ceiling), amends related tariff tables and requires Noga to report annually all connection and planning surveys and 35כג answers. Amendments take effect on publication in Reshumot (publication date not confirmed) and apply to requests filed afterwards.

    Electricity Authority (Rashut HaChashmal) · Electricity Authority Decision 73305

Timeline of data center and power policy in Israel

DateActionTypeStatusAuthority
19 Oct 2026Proposed 200 MW cap per new data center in large-consumer connection rulesRestrictionProposedElectricity Authority (Rashut HaChashmal)
18 Oct 2026Hearing on 2025 tariff differences: no segment changes, IEC add-on of 1.72 agorot/kWh in 2027Power tariffProposedElectricity Authority (Rashut HaChashmal)
15 Jul 2026Temporary freeze on grid connection processing for data centers of 8 MVA and above (Decision 74506)MoratoriumIn forceElectricity Authority (Rashut HaChashmal)
10 Jun 2026Hearing: dedicated connection track for consumers of 50 MVA and above to the transmission gridGrid accessProposedElectricity Authority (Rashut HaChashmal)
2 Jun 2026Government Decision 4194: staff work on server-farm incentives near the Lebanon borderPlan or strategyIn forceGovernment of Israel (Prime Minister's Office)
20 May 2026Planning and Building Law (Amendment 168) bill: AI server farms as national infrastructureRegulationProposedKnesset (government bill)
30 Apr 2026Semi-annual tariff update from 1 July 2026 (amended by Decision 74010)Power tariffIn forceElectricity Authority (Rashut HaChashmal)
22 Feb 2026Government Decision 3907: promoting advanced server farms for AI leadershipPlan or strategyIn forceGovernment of Israel
28 Jan 2026Amended criteria for feasibility surveys, planning and grid connection (Decision 73305)Grid accessAnnouncedElectricity Authority (Rashut HaChashmal)
8 Dec 2025New electricity tariff structure from 1 Jan 2026 (Decision 72806)Power tariffIn forceElectricity Authority (Rashut HaChashmal)
4 Dec 2025Government Decision 3586: electricity sector readiness for AI and renewablesPlan or strategyIn forceGovernment of Israel
14 Aug 2025Privacy Protection Law Amendment 13 in forceRegulationIn forceKnesset / Privacy Protection Authority
25 Jul 2021Government Resolution 171: 27% cut in electricity CO2 by 2030 vs 2015OtherIn forceGovernment of Israel

How Israel compares

Latest official figures for the countries we track.

CountryIndustrial power priceRenewable shareGrid emission factorRestrictions in forceIncentives in force
Argentina—19.6% (2025)0.28 kgCO2/kWh (2022)02
Australia—39% (2025)—02
Austria169 USD/MWh (2026)78% (2025)0.15 kgCO2/kWh (2023)00
Bangladesh—2% (2025)—00
Belgium183 USD/MWh (2025)34.3% (2025)0.19 kgCO2/kWh (2024)00
Brazil—86.8% (2025)0.07 kgCO2/kWh (2025)01
Canada—63.9% (2024)0.10 kgCO2/kWh (2022)60
Chile—66% (2025)0.24 kgCO2/kWh (2023)00
China—38% (2025)0.53 kgCO2/kWh (2023)20
Colombia——0.22 kgCO2/kWh (2024)02
Costa Rica—98.6% (2025)0.04 kgCO2/kWh (2025)11
Denmark134 USD/MWh (2025)81.5% (2024)0.11 kgCO2/kWh (2024)10
Ecuador——0.16 kgCO2/kWh (2024)10
Finland58.4 USD/MWh (2025)57% (2024)0.03 kgCO2/kWh (2025)00
France104 USD/MWh (2025)27% (2025)0.02 kgCO2/kWh (2025)01
Germany180 USD/MWh (2025)58.8% (2025)0.34 kgCO2/kWh (2025)10
Guatemala84.5 USD/MWh (2025)53.5% (2024)0.29 kgCO2/kWh (2024)02
Hong Kong180 USD/MWh (2026)—0.59 kgCO2/kWh (2025)02
Iceland42.9 USD/MWh (2022)100% (2026)—12
India82.1 USD/MWh (2025)28.7% (2026)0.68 kgCO2/kWh (2025)15
Indonesia62.9 USD/MWh (2024)16.3% (2025)0.68 kgCO2/kWh (2024)01
Ireland234 USD/MWh (2025)41.3% (2024)0.20 kgCO2/kWh (2025)20
Israel—14.6% (2024)0.41 kgCO2/kWh (2024)10
Italy184 USD/MWh (2025)48% (2025)0.20 kgCO2/kWh (2025)00
Japan—23.1% (2024)0.45 kgCO2/kWh (2024)00
Kazakhstan—14.6% (2025)0.81 kgCO2/kWh (2025)00
Kyrgyzstan41.7 USD/MWh (2026)88% (2024)0.16 kgCO2/kWh (2019)11
Luxembourg165 USD/MWh (2025)23.3% (2025)—00
Malaysia105 USD/MWh (2026)21% (2025)0.74 kgCO2/kWh (2024)11
Mexico——0.44 kgCO2/kWh (2023)00
Morocco—27% (2024)—00
Nepal———00
Netherlands148 USD/MWh (2025)49% (2025)0.20 kgCO2/kWh (2024)40
New Zealand—88.5% (2025)0.08 kgCO2/kWh (2025)00
Norway100 USD/MWh (2026)96% (2025)0.01 kgCO2/kWh (2025)10
Pakistan97.5 USD/MWh (2026)34.7% (2025)—01
Panama66.3 USD/MWh (2025)74.7% (2025)0.15 kgCO2/kWh (2024)01
Paraguay33.0 USD/MWh (2026)——12
Peru—62.6% (2025)—01
Philippines—22.2% (2024)0.71 kgCO2/kWh (2017)12
Russia—17.6% (2025)—20
Singapore189 USD/MWh (2025)2.1% (2024)0.40 kgCO2/kWh (2024)10
South Africa—9% (2024)—11
South Korea—9.8% (2025)—00
Spain113 USD/MWh (2025)55.5% (2025)—10
Sri Lanka—60.2% (2025)—00
Sweden78.5 USD/MWh (2025)—0.06 kgCO2/kWh (2023)00
Switzerland240 USD/MWh (2026)70.8% (2025)0.13 kgCO2/kWh (2022)00
Taiwan—12.7% (2025)0.47 kgCO2/kWh (2024)10
Thailand120 USD/MWh (2026)—0.48 kgCO2/kWh (2026)02
Türkiye70.3 USD/MWh (2026)—0.44 kgCO2/kWh (2022)11
United Arab Emirates120 USD/MWh (2026)8.8% (2024)0.47 kgCO2/kWh (2024)00
United Kingdom234 USD/MWh (2026)52.1% (2025)0.15 kgCO2/kWh (2026)11
United States86.2 USD/MWh (2025)24% (2025)0.35 kgCO2/kWh (2023)01
Uruguay101 USD/MWh (2026)98% (2025)0.01 kgCO2/kWh (2025)03
Uzbekistan83.3 USD/MWh (2026)19.4% (2025)—10
Venezuela—77% (2023)—01

Questions

Is there a data center moratorium in Israel?

Yes. 1 restriction on new data centers is in force in Israel: Temporary freeze on grid connection processing for data centers of 8 MVA and above (Decision 74506).

How much of Israel’s electricity is renewable?

Renewables supplied 14.6% of electricity generation in Israel in 2024.

Where does this data come from?

Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.

What counts as a restriction or moratorium?

A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.

How are power prices compared?

We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.

How often is it updated?

Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.

Global capacity

How much data center capacity is installed worldwide?

Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.

Open the Global Capacity Tracker

Choosing a market or a site?

Our analysts prepare country briefings on power, grid access, incentives and permits, with every source, in Excel.

Talk to an analyst