In short
As of 27 November 2026, DC Market Insights tracks 13 government actions on data centers and power in Poland, 8 of them in force. We have found no moratorium or restriction on new data centers in force in Poland. 1 incentive scheme applies: Polish Investment Zone (PSI) support decisions available to data centers.
Market snapshot
Poland power and policy: key facts
- Industrial electricity price: 197 USD/MWh (2026). Rank 4 of 34 tracked countries, highest first.
- Renewable share of electricity generation: 31.4% (2025). Rank 30 of 50 tracked countries, highest first.
- Latest change: Capacity fee 2027: quarterly rates for non-household users (URE (Energy Regulatory Office), 30 Oct 2026).
- By type: 4 plan or strategy, 3 power tariff, 2 efficiency rule and 1 incentive.
Power indicators for Poland
Latest official figure for each indicator, with earlier years where we have them.
In force now in Poland
Grid access (1)
Energy Law amendment of 13 March 2026: grid connection reform
Act of 13 March 2026 amending the Energy Law (Dz.U. 2026 poz. 516, published 15 Apr 2026). Advance payment for connection conditions above 1 kV set at PLN 60 per kW of requested connection capacity; system operators may sign flexible connection agreements where full connection needs grid expansion; connection agreements lapse if the applicant does not obtain a final building permit in time (24 months for most installations); cable pooling at one connection point above 1 kV. Applies to large loads such as data centers.
Power tariff (2)
Lower quality fee for the largest energy-intensive consumers (odbiorca specjalny)
Amendment to the tariff regulation (Dec 2025) cuts the grid quality fee for special customers connected at 110 kV or above that take at least 200 GWh a year for own use, use at least 50% of contracted capacity and whose electricity cost is at least 15% of production value (e.g. Tauron 2026: PLN 3.27/MWh vs 33.06). Data centers are not named; eligibility of large data centers not confirmed.
Capacity fee (opłata mocowa) 2026: flat rate for non-household users
URE set the 2026 capacity fee for non-household final users at PLN 0.2194/kWh net, charged on energy taken in the 15 working-day hours 07:00-22:00, from 1 Jan to 31 Dec 2026; no profile groups.
Incentive (1)
Polish Investment Zone (PSI) support decisions available to data centers
In its reply to interpellation 17787 the Ministry of Development and Technology states that building or expanding a data center is eligible for Polish Investment Zone support decisions (income tax exemption) and for grant programmes, and that several decisions have already been issued for data center projects. Key siting factors named: high-capacity power connections and water for cooling.
Renewable energy (1)
Direct line (linia bezpośrednia) liberalisation
Energy Law amendment (Dz.U. 2023 poz. 1681) ends the need for the URE President's consent to build a direct line from a generator to a consumer: notification and entry in the URE register are enough; surplus may be fed into the grid and direct-line users who rely on the grid pay a solidarity fee. Makes on-site or adjacent renewable supply to large consumers such as data centers easier.
Efficiency rule (1)
Data center energy performance reporting for 500 kW+ IT load (EU Delegated Regulation 2024/1364)
Owners and operators of data centers with installed IT power demand of at least 500 kW must report energy performance indicators to the EU database each year by 15 May for the previous year (first report 15 Sep 2024). The Ministry of Climate and Environment points operators to the EU reporting; Poland has no separate national system.
Regulation (1)
National Cybersecurity System (KSC) amendment transposing NIS2
Act of 23 January 2026 (Dz.U. 2026 poz. 252) replaces operators of essential services and digital service providers with key and important entities; digital infrastructure, which under NIS2 includes data center service providers, is a key sector. In force 3 April 2026.
Plan or strategy (1)
Digital State Strategy (Strategia Cyfryzacji Państwa)
Adopted by Council of Ministers Resolution No. 130 of 9 June 2026 (Monitor Polski 2026 poz. 620). Its analysis calls Poland's modern data center sector small and lists energy costs, emissions, regulatory costs and local opposition as factors that reduce the attractiveness of data center investment.
Announced and proposed
Measures that are not yet in force. Status changes when the rule takes effect or is withdrawn.
Capacity fee 2027: quarterly rates for non-household users
URE published 2027 capacity fee rates for non-household users, set per quarter for the first time to reward load management: PLN 0.1925 (Q1), 0.2141 (Q2), 0.1984 (Q3) and 0.1950 (Q4) per kWh, all lower than the 2026 rate of 0.2194; charged on energy taken 07:00-22:00 on working days.
Government resolution backing the Baltic AI Gigafactory bid
Council of Ministers resolution lets Poland join the EuroHPC AI Gigafactories call by guaranteeing purchases of AI compute (EUR 100m over 2028-2033, matched by the EU; over PLN 400m in total). The planned facility would start with at least 25,000 H100-equivalent accelerators and grow to 75,000; a private consortium would invest. No site chosen yet.
Draft Energy Law amendment UC121: waste-heat cost-benefit analysis for data centers above 1 MW
Ministry of Energy draft of 15 May 2026 transposing EU Directive 2023/1791: data centers with total rated input power above 1 MW would have to carry out a cost-benefit analysis of using their waste heat, unless shown to be technically or economically infeasible. Draft only; read in a consultation copy hosted by Związek Powiatów Polskich.
PSE draft Transmission Network Development Plan 2027-2036 with data center demand forecast
The TSO's draft development plan (consultation version, January 2026) treats data centers as one of the fastest-growing consumer groups and forecasts data center demand rising from about 200 MW in 2024 to 3,093 MW in 2036 and 5,018 MW (29.4 TWh) in 2040, based on connection applications; Warsaw, Poznań, Kraków and Wrocław are named as the main locations. Document dated January 2026, day not stated.
Gaia AI Factory in Kraków (second Polish EuroHPC AI Factory, after PIAST AI in Poznań)
Poland's second EuroHPC AI Factory, Gaia AI Factory at Cyfronet AGH in Kraków, has a budget of about PLN 300m (EUR 70m), co-funded 50/50 by Poland and the European Commission, for a supercomputer with more than 1,000 GPUs. The first Polish AI Factory is PIAST AI in Poznań (PCSS).
Timeline of data center and power policy in Poland
| Date | Action | Type | Status | Authority |
|---|---|---|---|---|
| 30 Oct 2026 | Capacity fee 2027: quarterly rates for non-household users | Power tariff | Announced | URE (Energy Regulatory Office) |
| 14 Jul 2026 | Government resolution backing the Baltic AI Gigafactory bid | Plan or strategy | Announced | Council of Ministers / Ministry of Digital Affairs |
| 8 Jul 2026 | Polish Investment Zone (PSI) support decisions available to data centers | Incentive | In force | Ministry of Development and Technology |
| 9 Jun 2026 | Digital State Strategy (Strategia Cyfryzacji Państwa) | Plan or strategy | In force | Council of Ministers / Ministry of Digital Affairs |
| 15 May 2026 | Draft Energy Law amendment UC121: waste-heat cost-benefit analysis for data centers above 1 MW | Efficiency rule | Proposed | Ministry of Energy |
| 13 Mar 2026 | Energy Law amendment of 13 March 2026: grid connection reform | Grid access | In force | Sejm / Ministry of Energy |
| 23 Jan 2026 | National Cybersecurity System (KSC) amendment transposing NIS2 | Regulation | In force | Ministry of Digital Affairs |
| 1 Jan 2026 | PSE draft Transmission Network Development Plan 2027-2036 with data center demand forecast | Plan or strategy | Proposed | PSE S.A. (transmission system operator) |
| 12 Dec 2025 | Lower quality fee for the largest energy-intensive consumers (odbiorca specjalny) | Power tariff | In force | Ministry of Energy |
| 30 Oct 2025 | Capacity fee (opłata mocowa) 2026: flat rate for non-household users | Power tariff | In force | URE (Energy Regulatory Office) |
| 10 Oct 2025 | Gaia AI Factory in Kraków (second Polish EuroHPC AI Factory, after PIAST AI in Poznań) | Plan or strategy | Announced | Ministry of Digital Affairs |
| 6 Jun 2024 | Data center energy performance reporting for 500 kW+ IT load (EU Delegated Regulation 2024/1364) | Efficiency rule | In force | Ministry of Climate and Environment (EU EED Art. 12) |
| 28 Jul 2023 | Direct line (linia bezpośrednia) liberalisation | Renewable energy | In force | Sejm / Ministry of Development and Technology; register kept by URE |
How Poland compares
Latest official figures for the countries we track.
| Country | Industrial power price | Renewable share | Grid emission factor | Restrictions in force | Incentives in force |
|---|---|---|---|---|---|
| Argentina | — | 19.6% (2025) | 0.28 kgCO2/kWh (2022) | 0 | 2 |
| Australia | — | 39% (2025) | — | 0 | 2 |
| Austria | 169 USD/MWh (2026) | 78% (2025) | 0.15 kgCO2/kWh (2023) | 0 | 0 |
| Bangladesh | — | 2% (2025) | — | 0 | 0 |
| Belgium | 183 USD/MWh (2025) | 34.3% (2025) | 0.19 kgCO2/kWh (2024) | 0 | 0 |
| Brazil | — | 86.8% (2025) | 0.07 kgCO2/kWh (2025) | 0 | 1 |
| Canada | — | 63.9% (2024) | 0.10 kgCO2/kWh (2022) | 6 | 0 |
| Chile | — | 66% (2025) | 0.24 kgCO2/kWh (2023) | 0 | 0 |
| China | — | 38% (2025) | 0.53 kgCO2/kWh (2023) | 2 | 0 |
| Colombia | — | — | 0.22 kgCO2/kWh (2024) | 0 | 2 |
| Costa Rica | — | 98.6% (2025) | 0.04 kgCO2/kWh (2025) | 1 | 1 |
| Denmark | 134 USD/MWh (2025) | 81.5% (2024) | 0.11 kgCO2/kWh (2024) | 1 | 0 |
| Ecuador | — | — | 0.16 kgCO2/kWh (2024) | 1 | 0 |
| Finland | 58.4 USD/MWh (2025) | 57% (2024) | 0.03 kgCO2/kWh (2025) | 0 | 0 |
| France | 104 USD/MWh (2025) | 27% (2025) | 0.02 kgCO2/kWh (2025) | 0 | 1 |
| Germany | 180 USD/MWh (2025) | 58.8% (2025) | 0.34 kgCO2/kWh (2025) | 1 | 0 |
| Guatemala | 84.5 USD/MWh (2025) | 53.5% (2024) | 0.29 kgCO2/kWh (2024) | 0 | 2 |
| Hong Kong | 180 USD/MWh (2026) | — | 0.59 kgCO2/kWh (2025) | 0 | 2 |
| Iceland | 42.9 USD/MWh (2022) | 100% (2026) | — | 1 | 2 |
| India | 82.1 USD/MWh (2025) | 28.7% (2026) | 0.68 kgCO2/kWh (2025) | 1 | 5 |
| Indonesia | 62.9 USD/MWh (2024) | 16.3% (2025) | 0.68 kgCO2/kWh (2024) | 0 | 1 |
| Ireland | 234 USD/MWh (2025) | 41.3% (2024) | 0.20 kgCO2/kWh (2025) | 2 | 0 |
| Israel | — | 14.6% (2024) | 0.41 kgCO2/kWh (2024) | 1 | 0 |
| Italy | 184 USD/MWh (2025) | 48% (2025) | 0.20 kgCO2/kWh (2025) | 0 | 0 |
| Japan | — | 23.1% (2024) | 0.45 kgCO2/kWh (2024) | 0 | 0 |
| Kazakhstan | — | 14.6% (2025) | 0.81 kgCO2/kWh (2025) | 0 | 0 |
| Kyrgyzstan | 41.7 USD/MWh (2026) | 88% (2024) | 0.16 kgCO2/kWh (2019) | 1 | 1 |
| Luxembourg | 165 USD/MWh (2025) | 23.3% (2025) | — | 0 | 0 |
| Malaysia | 105 USD/MWh (2026) | 21% (2025) | 0.74 kgCO2/kWh (2024) | 1 | 1 |
| Mexico | — | — | 0.44 kgCO2/kWh (2023) | 0 | 0 |
| Morocco | — | 27% (2024) | — | 0 | 0 |
| Nepal | — | — | — | 0 | 0 |
| Netherlands | 148 USD/MWh (2025) | 49% (2025) | 0.20 kgCO2/kWh (2024) | 4 | 0 |
| New Zealand | — | 88.5% (2025) | 0.08 kgCO2/kWh (2025) | 0 | 0 |
| Nigeria | 154 USD/MWh (2026) | 32.7% (2025) | — | 0 | 1 |
| Norway | 100 USD/MWh (2026) | 96% (2025) | 0.01 kgCO2/kWh (2025) | 1 | 0 |
| Pakistan | 97.5 USD/MWh (2026) | 34.7% (2025) | — | 0 | 1 |
| Panama | 66.3 USD/MWh (2025) | 74.7% (2025) | 0.15 kgCO2/kWh (2024) | 0 | 1 |
| Paraguay | 33.0 USD/MWh (2026) | — | — | 1 | 2 |
| Peru | — | 62.6% (2025) | — | 0 | 1 |
| Philippines | — | 22.2% (2024) | 0.71 kgCO2/kWh (2017) | 1 | 2 |
| Poland | 197 USD/MWh (2026) | 31.4% (2025) | — | 0 | 1 |
| Russia | — | 17.6% (2025) | — | 2 | 0 |
| Singapore | 189 USD/MWh (2025) | 2.1% (2024) | 0.40 kgCO2/kWh (2024) | 1 | 0 |
| South Africa | — | 9% (2024) | — | 1 | 1 |
| South Korea | — | 9.8% (2025) | — | 0 | 0 |
| Spain | 113 USD/MWh (2025) | 55.5% (2025) | — | 1 | 0 |
| Sri Lanka | — | 60.2% (2025) | — | 0 | 0 |
| Sweden | 78.5 USD/MWh (2025) | — | 0.06 kgCO2/kWh (2023) | 0 | 0 |
| Switzerland | 240 USD/MWh (2026) | 70.8% (2025) | 0.13 kgCO2/kWh (2022) | 0 | 0 |
| Taiwan | — | 12.7% (2025) | 0.47 kgCO2/kWh (2024) | 1 | 0 |
| Thailand | 120 USD/MWh (2026) | — | 0.48 kgCO2/kWh (2026) | 0 | 2 |
| Türkiye | 70.3 USD/MWh (2026) | — | 0.44 kgCO2/kWh (2022) | 1 | 1 |
| United Arab Emirates | 120 USD/MWh (2026) | 8.8% (2024) | 0.47 kgCO2/kWh (2024) | 0 | 0 |
| United Kingdom | 234 USD/MWh (2026) | 52.1% (2025) | 0.15 kgCO2/kWh (2026) | 1 | 1 |
| United States | 86.2 USD/MWh (2025) | 24% (2025) | 0.35 kgCO2/kWh (2023) | 0 | 1 |
| Uruguay | 101 USD/MWh (2026) | 98% (2025) | 0.01 kgCO2/kWh (2025) | 0 | 3 |
| Uzbekistan | 83.3 USD/MWh (2026) | 19.4% (2025) | — | 1 | 0 |
| Venezuela | — | 77% (2023) | — | 0 | 1 |
Questions
Is there a data center moratorium in Poland?
We have found no moratorium or restriction on new data centers in force in Poland as of 27 November 2026. Proposed or announced measures, if any, are listed in the timeline.
What incentives does Poland offer data centers?
In force: Polish Investment Zone (PSI) support decisions available to data centers. Each is listed with its authority and dates on this page.
What does electricity cost for data centers in Poland?
The industrial electricity price in Poland was 197 USD/MWh in 2026 (Eurostat nrg_pc_205, non-household band IE (20,000-69,999 MWh/yr), 2026-S1, excl. VAT and recoverable taxes 0.1687 EUR/kWh = 168.7 EUR/MWh x ECB average USD/EUR Jan-Jun 2026 1.1671 (monthly 1.1738/1.1824/1.1558/1.1706/1.1673/1.1518) = 196.9 USD/MWh; excl.). Data center contracts can differ by voltage level, contract length and location.
How much of Poland’s electricity is renewable?
Renewables supplied 31.4% of electricity generation in Poland in 2025.
Where does this data come from?
Each action comes from a page we opened: a law, regulation, gazette notice, ministry or regulator release, grid operator notice or investment agency page, and only when official text is not available a company or trade publication. A second analyst re-opens the source before an item is published. Government sources are linked on the page; all sources come with the Excel data.
What counts as a restriction or moratorium?
A government or grid operator rule that stops, pauses, caps or conditions new data center capacity or grid connections, for a country or a region within it. Proposals are shown as proposed until they take effect.
How are power prices compared?
We use each country’s official statistics for industrial or non-household electricity, converted to US dollars per MWh at the average rate for the year where needed, and show the year and source. Contract prices for data centers can differ.
How often is it updated?
Countries are reviewed on a rolling schedule and changes are added as they are announced. Each item shows the date of the action.
Global capacity
How much data center capacity is installed worldwide?
Installed and forecast capacity in MW by region and country, 2020 to 2035, with low, base and high cases. Updated every quarter.
Choosing a market or a site?
Our analysts prepare country briefings on power, grid access, incentives and permits, with every source, in Excel.